Home / QBE / Determination 926530

Determination 926530

Claim settlement scope and cash settlement of boat accidental damage claim

FirmQBE
Decided2023-07-31
ProductGeneral Insurance · Other general
OutcomeFor the complainant in part
Amount awarded$4,286
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainants claimed accidental water damage to their boat and disputed the scope of the insurer's settlement, including PSS seal replacement, carpets and mechanical and electrical repairs. AFCA found the insurer need not replace the PSS seal or pay for maintenance-related mechanical and electrical works, and ordered a cash settlement of $4,286.04 plus carpet cleaning.

The policy covers accidental damage, but wear and tear and lack of maintenance are excluded, and the insurer may choose a fair cash settlement under the policy terms.

Issues

Subjects and remedies

home or building damagemotor vehicle collisionpay compensationrepair or rectify

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 926530 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 926530 Page 1 of 10 Case number: 926530 4 May 2023 1 Determination overview 1.1 Complaint The complainants hold a maritime insurance policy with the financial firm (insurer). On 13 July 2022 they lodged a claim for accidental damage to their boat caused by a water leak. The insurer accepted the claim and authorised repairs of what it says was the damage caused by the leak. The complainants dispute the scope of the insurer‟s proposed settlement of the claim. In particular, the complainants say that a packless sealing system shaft seal („PSS seal‟) that failed, as well as water-damaged carpets, should be replaced. The complainants also say that the insurer should be responsible for mechanical and electrical repairs to the vessel. During the ongoing dispute with the insurer, the complainants withdrew their permission for the authorised repairs to take place. The insurer therefore elected to offer a cash settlement. 1.2 Issues and key findings Should the insurer provide coverage for replacement of the PSS seal? No. The insurer is not obliged to pay for the replacement of the PSS seal. Should the insurer provide coverage for replacement carpets? The insurer has shown that the water-damaged carpets can likely be repaired, and that process should be attempted. If the result is unsatisfactory then the insurer should replace the carpets. Should the insurer provide coverage for mechanical and electrical repairs? No. The mechanical and electrical repairs are maintenance related. Is the insurer entitled to cash settle? Yes. The insurer is entitled to cash settle the claim. Why is the outcome fair? The events the complainants have described are unfortunate and I understand they have suffered a financial loss over and above the cash settlement sum offered by the insurer in circumstances that are out of their control. However, the outcome is fair because:-  The complainants established a valid claim for accidental damage to their boat after water ingressed the vessel due to a leak  The insurer accepted the claim and authorised repair works according to a scope of works („SOW‟)  The SOW was comprehensive, fair and reasonable  After adjustment and tightening, the PSS seal did not require replacement  The water-damaged carpets can likely be repaired Determination | Case number: 926530 Page 2 of 10  The mechanical and electrical repairs are maintenance related  The insurer is entitled to cash settle the balance of the claim  The insurer is entitled to rely upon the terms and conditions of the policy to determine its obligations to the complainants regarding the claim  Throughout this complaint AFCA‟s approach has remained objective, consistent with the facts and based on the law. 1.3 Determination This determination is in favour of the insurer. Within 14 days of receipt of notice that the complainants accept this determination, the insurer must pay a cash settlement sum to the complainant in the sum of $4,286.04, less any outstanding excess. The insurer must also arrange for the carpets to be cleaned and assess the efficacy of the cleaning process. Otherwise, the insurer is not required to do anything further regarding the claim. Determination | Case number: 926530 Page 3 of 10 2 Reasons for determination 2.1 Should the insurer provide coverage for the replacement of the PSS seal? Boat took on water in July 2022 The complainants purchased their Markline 1100 in 2019, planning to enjoy the vessel during their retirement. They say they spent about $50,000 making the vessel seaworthy, including replacing the port and starboard PSS seals in November 2019. A PSS seal is a dripless mechanical propeller shaft seal designed to prevent water ingress into the bilge of a boat. PSS seals are composed of high density carbon and high grade stainless steel sealing components. They have apparently become the industry standard propeller shaft seal as they have many advantages over traditional-type packing gland propeller seals and lip-seals. I have read the evidence which supports the claimants‟ contention that they arrange d for the PSS seals to be replaced in timely manner in November 2019 (see the email from AM dated 13 December 2022 and the accompanying invoice from DM dated 2 November 2019 for “ parts to replace 2 PSS seals ” in the sum of $775.88). Despite this and other extensive maintenance on the vessel which was carried out in mid-to- late 2020, the port side PSS seal began leaking and, on about 4 July 2022, the complainants received a telephone call advising them the vessel was listing on the port side. After immediately pumping out the vessel, the complainants drove the boat to a marina (MP) in the City of Lake Macquarie, New South Wales. The vessel was then dry-berthed at MP so that further water could be drained and the damage could be assessed. The boat was later inspected by BM on behalf of the insurer. BM provided three reports pursuant to its inspection and assessment of the vessel, dated 9 October 2022, 12 February 2023 and 14 February 2023. A copy of an informative document entitled “ PSS Shaft Seal Maintenance & User Guidelines ” was appended to the second BM report. BM‟s reports are logical, informative and helpful. I note the complainants have supplied a great deal of evidence about the extensive maintenance that was performed on the boat prior to the leak of the PSS seal in July 2022. However, they have elected not to have the vessel formally assessed by a licenced shipwright, boat-builder or marine mechanic (or other suitably qualified expert) for the purposes of this complaint. BM concluded that, despite the maintenance which had previously been carried out on the vessel, the port side PSS began leaking in July 2022, probably because one or more set screws were missing from the collar/rotor of the seal. This likely caused the locking collar of the seal to loosen. BM further noted that, after this problem had been remedied and the PSS seal had been tightened and adjusted, the leak ceased and the PSS seal began to operate effectively and efficiently again. In other words, the problem which caused the leak in July 2022 had been fixed. Determination | Case number: 926530 Page 4 of 10 Unfortunately, however, there was other damage to the vessel which had been caused by the leak and the ingress of water. Policy provides coverage for accidental damage T he policy provides coverage for a variety of events, including „accidental damage‟. Page 23 of the PDS includes:- We will cover you for: accidental damage-  if your boat is damaged accidentally  if your boat sinks accidentally, provided it was in seaworthy condition at the time of sinking. Page 16 of the PDS includes a definition of „accident‟: - An incident that is unforeseen and unintended and that causes loss of damage. This includes a series of accidents arising out of the one event. Insurer accepted claim and authorised repairs works Based upon the evidence of BM, and consistent with its obligations pursuant to the policy, the insurer accepted the claim and authorised repairs. The repair works included, as mentioned, adjustment and tightening of the offending PSS seal. Other repairs included in the SOW are set out in three quotations provided by MP dated 14 July 2022, 14 September 2022 and 26 September 2022. Notably, these include, amongst other things:  mechanical repairs such as the removal, flushing and replacement of engine, gearbox, and transmission fluids  the supply and fitting of a new N200 battery  cleaning of water internal marks on floors and bulkheads  repairs to a bilge pump  supply and fitting of a replacement float switch. I note the costs associated with the repairs and berth fees set out in the first and third MP quotations have been met by the insurer. However, the costs associated with the works set out in the second MP quote dated 14 September 2022 remain at issue. These costs total $3,571.70. In sum, a dispute remains about the adequacy of the SOW and the extent and costs of the repairs the insurer is prepared to cover. No need to replace PSS seals The complainants say that the costs associated with replacement of the PSS seals should be borne by the insurer. However, I disagree. Determination | Case number: 926530 Page 5 of 10 The failure of the locking collar of the port-side PSS seal was clearly identified, and I have no reason to doubt the conclusion of BM that, after tightening and adjustment, the seal operated effectively and the water ingress was stopped. Thus, the PSS seal was not damaged by the insured event (that is, the leak and water ingress that occurred in early July 2022). In fact, the evidence shows the port side PSS seal was the cause of the claim, and not a result of the claim event. Indeed, the insurer notes the port side PSS seal had a history of leaking, and points to an invoice for repairs from the complainants‟ preferred repairer, EM, dated 24 July 2020. The in voice includes a reference to, “ Test gears – found port PSS seal leaking” and “ adjust PSS” to stop the leak. The evidence shows that PSS seals require regular inspection and maintenance. The PSS Shaft Seal Maintenance & User Guidelines that was appended to the second BM report states that the seals should be inspected twice annually and replaced every six years, regardless of condition. Whilst the insurer has paid for the adjustment and tightening of the port side seal on this occasion (see the third MP quote dated 26 September 2022), regular inspection and maintenance of the seals in the future should be performed by the complainants. BM notes the estimated cost of a standard maintenance kit required for PSS seals is $374.50, plus GST. The cost of these kits, which will be required from time to time, should be borne by the complainants as they will form an integral part of the ongoing, long-term maintenance of the vessel. In sum, after the leak which began in July 2022, the port side PSS seal was adjusted/tightened. This remedied any defect and the seal began to function effectively again. Consequently, the insurer is not required to replace the PSS seals as part of this claim. Determination | Case number: 926530 Page 6 of 10 2.2 Should the insurer provide coverage for replacement carpets? Water-damaged carpet can likely be repaired I have seen the photographs which depict the water damaged carpets and I am aware the complainants say the carpets should be replaced. However, the insurer says the carpets can be cleaned. The insurer‟s letter dated 25 November 2022 includes the following: - The carpets were quoted as being able to be cleaned within the repair costs, in line with …. (MP‟s) expertise on these matters. Nevertheless, the next sentence of that letter states:- Should it transpire that cleaning of the carpets does not reinstate them to their pre-event condition, replacement considering new for old contribution would be reviewed at that time as required. I also note the second MP quotation dated 14 September 2022 includes the following:- Labour general hand, remove, clean, shampoo and replace all floor carpet, clean water marks off floor and bulk heads…. $727,27 (emphasis added). It therefore appears that, if cleaning of the carpets does not produce a satisfactory result, the insurer is prepared to replace the carpets. This is a fair and reasonable approach and should avoid any further dispute regarding this particular issue. Determination | Case number: 926530 Page 7 of 10 2.3 Should the insurer provide coverage for mechanical and electrical repairs? Complainants say water ingress caused mechanical and electrical damage over and above the SOW After BM‟s initial inspection of the vessel, quotations for various mechanical and electrical repairs were obtained. Some of these repairs were denied by the insurer for the following reasons:-  There was no evidence that suggested repairs to the drive shaft were required because of water immersion brought about by the leak of July 2022  The gearbox did not require an overhaul because, upon inspection, there was no evidence of water in the gearbox oil  The starter motors did not require replacement as both engines started at inspection  Various suggested electrical repairs were not required because of water damage, but rather to bring the vessel up to current regulatory condition. I note that the policy does not require the insurer to meet the cost of repairs or works aimed solely at bringing the vessel up to current regulatory condition. Finally, the insurer denied various suggested repairs because they either related to maintenance issues or were brought about by the processes associated with wear and tear. Damage caused by „wear and tear‟ and a „lack of maintenance‟ are expressly excluded from coverage under the terms and conditions of the policy. Page 16 of the PDS includes a definition of „damage‟: - Any form of physical harm to the boat but does not include wear and tear or anything that was present before this policy came into force (emphasis added). Moreover, page 26 of the PDS lists circumstances in which coverage will not be provided under the terms and conditions of the policy. These are called policy exclusions. They include the following:- We will not cover you for:  loss or damage caused by normal wear and tear  loss or damage caused by lack of maintenance. According, I agree with the insure r‟s decision to deny coverage for the costs of the following suggested works:-  repairs to the drive shaft  overhauling of the gearbox  replacement of oils and filters over and above those already replaced as per the three MP quotations  replacement of the starter motors  any electrical works aimed solely at bringing the vessel up to current regulatory condition  any electrical works over and above those already set out in the three MP quotations. Determination | Case number: 926530 Page 8 of 10 2.4 Is the insurer entitled to cash settle the claim? Complainants cancelled scheduled repairs The PDS includes the following on page 26:- We will, at our option,  repair or replace the item involved to as near as possible to the condition, standard and specification it was before the loss, or  pay you the reasonable cost of repairing, reinstating, or replacing the item involved to as near as possible condition, standard and specification it was before the loss. In other words, the policy allows the insurer to choose how to settle the claim, including by way of a cash settlement. The insurer‟s choice mu st be fair and must be based upon reasonable considerations. In this matter, the complainants cancelled the scheduled repairs that had been authorised by the insurer. The complainants say they were not comfortable proceeding with the repairs while they were still in dispute with the insurer. I cannot criticise the complainants for their decision to cancel the scheduled repairs in such circumstances. However, given the history associated with this complaint, and the friction which obviously exists between the parties, I am of the opinion that, in all the circumstances, the insurer‟s decision to cash settle the remainder of this claim is fair and reasonable. I therefore determine that, within 14 days of receipt of notice that the complainants accept this determination, the insurer must:-  pay to the complainants the sum of $3,571.70 as per the second MP quotation dated 14 September 2022, PLUS a 20% contingency on top of this to factor in the risk of the works passing to the complainants (that is, a total of $4,286.04), LESS any policy excess which remains outstanding. 2.5 Why is the outcome fair? The outcome is fair in all the circumstances because of the following considerations:-  The complainants established a valid claim for accidental damage to their boat after water ingressed the vessel due to a leak  The insurer accepted the claim and authorised repair works according to a SOW  The SOW was comprehensive, fair and reasonable  After adjustment, the PPS seals did not require replacement  The water-damaged carpets can likely be repaired  The mechanical and electrical repairs are maintenance related  The insurer is entitled to cash settle the balance of the claim  The insurer is entitled to rely upon the terms and conditions of the policy to determine its obligations to the complainants regarding the claim  Throughout this complaint AFCA‟s approach has remained objective, consistent with the facts and based on the law. Determination | Case number: 926530 Page 9 of 10 Determination | Case number: 926530 Page 10 of 10 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.