Loss of rent period and compensation for claim handling delays after malicious tenant damage

FirmIAG
Decided2023-09-04
ProductGeneral Insurance · Landlord
OutcomeFor the complainant
Amount awarded—
Non-financial loss$4,000
Amount claimed$15,000
SourceAFCA PDF

Summary

Insurer accepted a malicious damage claim for a tenanted unit but delayed responses and repairs. AFCA required additional loss of rent from 5 May to 31 August 2022 and increased non-financial loss compensation to $4,000.

Both parties contributed to delays, but the insurer's poor communication and delayed repairs meant the property was not tenantable until 31 August 2022, and its claim handling caused unusual stress and inconvenience.

Issues

Subjects and remedies

home or building damagethird party authoritypay claimpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 924836 Financial firm Insurance Australia Limited Determination | Case number: 924836 Page 1 of 8 Case number: 924836 1 September 2023 1 Determination overview 1.1 Complaint The complainant (unit owner(s) via representative for the owners ’ corporation) lodged a claim with the financial firm (insurer) for malicious damage sustained to a tenanted unit at the strata complex and loss of rent. The tenants damaged the property between 17 December 2020 and 9 July 2021, before being evicted. The insurer accepted the claim and arranged repairs. For ease of reference, the unit owner(s) and their representative from owners ’ corporation will be referred to as the ‘complainant’. The complainant is unhappy with the insurer’s service delays, claim handling and settlement offered. He expects the insurer to pay loss of rent until January 2023 and compensation for its poor service. 1.2 Issues and key findings Is the insurer required to increase loss of rent offer? Yes. The parties could have worked together to fast track the repairs. The complainant could have raised concerns earlier after the insurer’s builder completed the initial repairs. The insurer did not respond to the items disputed by complainant in a timely manner. The insurer has fairly settled the claim. However, its responses, actions and repairs were delayed. As a result, the property was not tenantable at least until 31 August 2022. It is fair in these circumstances the insurer covers loss of rent until 31 August 2022. Is the insurer required to increase compensation offer? Yes. The insurer could have handled the claim better. Better communication between the insurer, loss assessor, repairer and the complainant would have fast tracked the repairs. The insurer failed to provide timely responses to the complainant on the items disputed. The insurer’s claim handling and delays caused the complainant stress and inconvenience. The insurer should increase its offer for non-financial loss compensation from $2,500 to $4,000. Why is the outcome fair? The outcome is fair because whilst both parties contributed to the delays, the insurer should have done more to promptly resolve the claim . The insurer’s claim settlement was fair, but the property remained uninhabitable until repairs were reasonably completed by its builder. The insurer should pay compensation for its claim handling. 1.3 Determination This determination is substantially in favour of the complainant. The insurer should pay additional loss of rent from 5 May 2022 to 31 August 2022. It should also pay a total of $4,000 for non-financial loss compensation. Determination | Case number: 924836 Page 2 of 8 If the complainant accepts the determination, the insurer should settle the claim with 14 days of acceptance. Determination | Case number: 924836 Page 3 of 8 2 Reasons for determination 2.1 Is the insurer required to increase loss of rent offer? Yes. The parties could have worked together to fast track the repairs. The complainant could have raised concerns earlier after the insurer’s builder completed t he initial repairs. The insurer did not respond to the items disputed by complainant in a timely manner. The insurer has fairly settled the claim. However, its responses, actions and repairs were delayed. As a result, the property was not tenantable at least until 31 August 2022. It is fair in these circumstances the insurer covers loss of rent until 31 August 2022. Complainant seeks over $15,000 additional loss of rent payments The tenants caused malicious damage to the insured property (Unit 2) before they were evicted in July 2021. The insurer accepted the claim, appointed a loss assessor and builder to assess the claim and repair the damage to the property. The complainant says the property was not ready to be relet until the insurer ’s builder completed all repairs and handed them an operating remote for the front garage door. The complainant sought cover for several items denied by the insurer at various stages of the claim process. The insurer subsequently accepted most of the damage claimed by the complainant. The insurer paid loss of rent for the period of July 2021 to 4 May 2022. It says the property was habitable from 15 June 2022. The complainant does not accept the property was habitable from 15 June 2022. He seeks over $15,000 additional loss of rent for the period from 5 May 2022 to 15 January 2023. The complainant sold the unit on 28 November 2022 and the sale agreement settled in January 2023. Complainant cited concerns with the repairs after completion The complainant lodged the claim with the insurer in July 2021. The repairs to the property commenced in March 2022. The builder notified the insurer and the complainant the repairs were completed by 15 June 2022. The complainant identified several items were which not included in the scope of repairs or declined by the insurer throughout the claims process approximately for a period of one year from October 2021. The insurer says the outstanding items identified by the complainant finally in September 2022, three months after its builder completed repairs, do not render the property uninhabitable. Amongst these issues of concern were:  laundry tap not connected to water  upstairs powder room vanity taps not connected to water  floorboard on timber deck not replaced  architrave and wall of open plan area not patched and painted  garage door motor failed. Whilst I acknowledge the above issues required attention and were frustrating for the complainant, I accept they did not render the unit uninhabitable. Determination | Case number: 924836 Page 4 of 8 However, it is apparent the insurer did not immediately attend to these repairs. This is because as soon as the complainant received the repairer’s request to sign off on the repairs, he refused. The complainant did not consider the repairs were complete as he awaited the insurer’s decision on various items which had been declined, including damaged floorboards. I also do not agree the property was habitable and ready to be relet to a new tenant after 15 June 2022. Communication between the parties contributed to delays The insurer considers the complainant ’ s delay in reporting his concerns significantly contributed to the claim delays, which extended to three months. The complainant says he did not consider the repairs complete as he was awaiting the insurer’s decision on various items. The complainant also says the insurer at no time confirmed the repairs accepted in July 2022 and August 2022 were completed. The file notes confirm the insurer reviewed the request for loss of rent and awaited advice and recommendation from its experts at this time. These file notes show the insurer requested the complainant confirm if he was satisfied with the repairs on 26 August 2022. On balance, I am not satisfied the property was ready to be relet to a new tenant any time before the end of August 2022, as contractors were still completing work at the property. The insurer cash settled the complainant for the flooring in July 2022. The complainant says it could not have relet the property at an earlier date as a prospective new tenant would not appreciate contractors and external parties completing works at the property during tenancy. I agree. It is unreasonable to expect a new tenant to accommodate contractors working on pre-existing issues at the property during tenancy. I am of the view better communication between the complainant, insurer, loss assessor and builder could have fast tracked the repair process. This would have enabled the property to be relet at an earlier date. Insurer should extend loss of rent payments until 31 August 2022 The insurer says the builder was authorised to proceed with repairs in March 2022 and it issued a cash settlement for loss of rent from 3 July 2021 to 3 March 2022 amounting to $17,604. A second cash settlement of $3,912 for loss of rent was issued for the period of 4 March 2022 until 4 May 2022. The complainant rejected the third cash settlement offer of $2,151.60 for the period from 5 May 2022 to 15 June 2022. The complainant says he could not have rented the property until the insurer completed all accepted repairs and returned an operational remote for the garage door. Between October 2022 and January 2023, there were several discussions between the parties, including the builder, about the garage door and the remote. The insurer says its builder replaced the rear garage door and realigned the front garage door as per its initial scope. It provided the key to the new rear garage door. The builder had not tested the motor when it realigned the front garage door due to a power failure at the time. The builder says it was not given a remote to the front garage door when it commenced works at the property. It was unclear if the garage key was taken by the evicted tenants. The Determination | Case number: 924836 Page 5 of 8 insurer subsequently authorised replacement of the garage door motor and supplied a new remote. I acknowledge not having a garage remote was frustrating for the complainant and any prospective tenant. Moving large furniture and/or electrical items into the property might have been difficult. However, I am not satisfied this rendered the unit uninhabitable. The insurer says its builder rectified the plumbing issues to the upstairs powder room and laundry in October 2022. The insurer had also reimbursed the repair cost of another upstairs sink which was reportedly damaged in or about January 2023. I acknowledge it is unlikely the property could have been rented at the full market rate having plumbing issues, including the loss of use of a vanity, laundry and a non-functioning garage, as indicated by the complainant. It would have been cumbersome for the prospective tenant to have contractors attending to insurance-related repairs during tenancy. I consider the insurer has been fair and reasonable in its consideration of the claimed loss. The complainant disputed numerous items and I consider the insurer’s final evaluation of the claimable loss was fair. The acceptance of various disputed items, however occurred only after negotiations and meticulous follow up by the complainant. This took several months to finalise. On balance, I am satisfied both parties contributed to the claim delays. The complainant did not address issues promptly and the i nsurer’s communication about progress and issues in dispute should have been better. The initial repairs should also have been completed to a better standard. I accept this likely delayed the complainant ’ s ability to secure a new tenant. Given this, I consider the loss of rent paid by the insurer should be extended. However, I do not accept the complainant’s submission this should exten d to January 2023. Given the factors present and the contribution of both parties to the delays, I am satisfied the insurer is only required to extend its loss of rent payments until 31 August 2023. Cash settlement offered for flooring does not relate to issue about loss of rent The insurer initially denied liability for the floorboards on the basis they were not maliciously damaged by the tenant. The insurer concluded the damage was a result of wear and tear, and usage over time. The complainant disputed the insurer’s decision. The insurer subsequently accepted cover for the floorboards with its complaint review. It accepted the floorboards sustained damage because of the previous tenant’s deliberate acts, exposing the flooring to weather events. As the damage could not be repaired, the insurer cash settled the complainant $13,576.20 for the replacement of the floorboards in July 2022. The complainant opted to restore the flooring before the property was sold. The flooring was not replaced. The complainant says it was not satisfied with the replacement flooring offered by one of the flooring specialists. He then decided to restore the flooring instead of replacing it. The insurer now says it overpaid the damaged flooring aspect of the loss. It says this was not covered under the policy. I do not agree. The insurer’s complaint review team accepted the flooring was damaged by the tenant ’ s deliberate acts. The insurer compensated the complainant for the loss by way of a cash settlement. It is for the complainant to decide if he wished to replace the flooring or Determination | Case number: 924836 Page 6 of 8 restore the damaged flooring. The purpose of cash settlement is to offer compensation for the loss suffered by the complainant. I am satisfied the settlement offered was fair, being based on a quote from the insurer’s repairer. 2.2 Is the insurer required to increase compensation? Yes. The insurer could have handled the claim better. Better communication between the insurer, loss assessor, repairer and the complainant would have fast tracked the repairs. The insurer failed to provide timely responses to the complainant on the items disputed. The insurer’s claim handling and delays caused the complainant stress and inconvenience. The insurer should increase its offer for non-financial loss compensation from $2,500 to $4,000. AFCA may award compensation in certain circumstances Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $5,400) where the insurer’s actions have caused an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant’s expec tation of enjoyment or peace of mind. We take a conservative approach to compensation and expect a complainant to bear a normal degree of inconvenience during a claim. When considering non-financial loss compensation AFCA looks at what is reasonable and fair in all the circumstances. In considering what is fair in all the circumstances, it is appropriate to factor the overall claims experience, rather than focusing on specific individual events. Insurer caused delays with claim process The complainant lodged the claim in July 2021 and the initial scope of works were prepared by August 2021. Once the complainant had an opportunity review the scope of works, on 29 October 2021, he requested the insurer clarify the reasons why many items were excluded. The ins urer’s builder commenced repairs in March 2022. The insurer responded to the complainant’s email from October 2021 about items excluded or declined only on 27 April 2022. The complainant sought further clarification and reason for the denial of certain parts of the claim on 3 May 2022. This was not responded to by the insurer until July 2022. The complainant consistently sought updates and followed up the insurer’s response to queries. Timely communication and intervention between the insurer, loss adjuster and builder would have alleviated the unnecessary delayed experienced throughout the claim process. The insurer has not presented a timeline of events but says there was constant communication between the builder and the complainant. However, there are several emails and phone calls to the insurer from the complainant following up on the outstanding issues raised, indicating certain delays were caused by the insurer rather than its appointed loss assessor and builder. Insurer’s claim handling caused stress and inconvenience The complainant says the insurer backtracked on multiple items throughout the claim process by initially approving and subsequently retracting certain items. These include the garage remote, ferns and loss of rent payments between May 2022 and June 2022. Determination | Case number: 924836 Page 7 of 8 The complainant was struggling to meet the mortgage payments and had to request his bank to pause mortgage repayments as he could not meet them without the insurer reimbursing loss of rent. He also could not afford the electricity and water used for repairs and council rates. The complainant says he raised two service complaints with the insurer over the claims period. The first process took one month with no outcome for loss of rent, while the second process took three months with continued delays from the insurer. The complainant says he had experienced extreme stress of having to challenge, refute and scrutinise the numerous mistakes, omissions and retractions across more than 400 emails over the past eighteen months. This had significantly impacted his mental health resulting in suffering from chronic stress. I accept the insurer could have better managed the claim process and provided timely responses and claim decisions. Its delays caused an unusual and unnecessary degree of stress and inconvenience for the complainant. I consider an award of compensation for non- financial loss is warranted. Based on the exchanged material, I am satisfied the insurer should increase it compensation from $2,500 to $4,000. The complainant ’ s dispute about the ferns that were removed by the tenants has recently been resolved. The complainant accepted the insurer’s settlement offer of $1,200. 2.3 Why is the outcome fair? Outcome is fair The outcome is fair because whilst both parties contributed to the delays, the insurer should have done more to promptly resolve the claim. The insurer’s claim settlement was fair, but the property remained uninhabitable until repairs were reasonably completed by its builder. The insurer should pay compensation for its claim handling. Determination | Case number: 924836 Page 8 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.