Home / RACQ / Determination 924498

Determination 924498

Storm-related building and contents claims limited by policy exclusions (defective workmanship, earth movement, rust and mould)

FirmRACQ
Decided2024-02-13
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for storm-related damage to her home and contents across four claims, and the insurer partly accepted them but denied building damage attributed to non-compliant construction and pre-existing defects. AFCA decided the insurer was entitled to limit its liability and ordered $1,000 non-financial loss compensation.

Policy exclusions for defective or faulty workmanship, earth movement, and rust and mould apply to the building damage as shown by expert reports, while communication shortcomings warrant non-financial loss compensation.

Issues

Subjects and remedies

home or building damagemental healthnatural disasterpay non financial loss

Related

All RACQ determinations · Find similar determinations

Text of the determination

Determination Case number 924498 Financial firm RACQ Insurance Limited Determination | Case number: 924498 Page 2 of 13 Case number: 924498 11 December 2023 1 Determination overview 1.1 Complaint The complainant three storm related claims on her home and contents policy following storms on 7 December 2020, 30 November 2021, 25 February 2022 and 13 May 2022. The complainant is concerned there is ongoing storm related damage to the building including mould in the ceiling cavity, storm water damaged contents stored in the shed and damage to the building. The complainant believes the property is unliveable and that further temporary accommodation should have been provided. The insurer denied the building portion of the claim because the construction of the building is not compliant with the building code, which requires a structural step between the interior and exterior floor levels. 1.2 Issues and key findings Is the insurer entitled to limit its liability for the first claim (…. 26815) ? Yes. The insurer is entitled to limit its liability as set out in section 2.1 Is the insurer entitled to limit its liability for the second claim (….62557) ? Yes. The insurer is entitled to limit its liability as set out in section 2.2 Is the insurer entitled to limit its liability for the third claim? (…9510)? Yes. The panel accepts the third and fourth claims most likely relate to the same damage. The insurer is entitled to limit its liability as set out in section 2.3 Is the insurer required to pay compensation? Yes. The insurer is required to pay non-financial loss compensation of $1,000. Why is the outcome fair? The decision is fair because the insurer is entitled to rely upon the terms and conditions of the policy to assess its liability to the complainant regarding the loss and damage claimed. The panel is satisfied the insurer has fairly and reasonably paid the claims for temporary accommodation, contents, electricity costs, internal building repairs and counselling services. 1.3 Determination This determination is in favour of the insurer. Within 14 days of notification of the complainant accepting this determination the insurer is to:  pay the complainant $1,000 compensation for non-financial loss The insurer is otherwise entitled to limit its liability to the complainant under the terms and conditions of the policy and in accordance with the provisions of this determination. Determination | Case number: 924498 Page 3 of 13 2 Reasons for determination The complainant has lodged complaints relating to four separate flood related claims. The panel acknowledges there is an overlap in the claims given the claims all relate to water damage. Liability was not resolved until after the fourth claim had been lodged. However, as expert reports obtained cover damage related to each of the events, for ease of understanding the panel has dealt with each claim separately. 2.1 Is the insurer entitled to limit its liability for the first claim (…26815)? Yes. The insurer is entitled to limit its liability to the complainant Complainant has initial onus to prove claim falls within terms of policy It is accepted insurance law that the complainant carries the initial onus to establish on the balance of probabilities (that is more likely than not) that the loss or damage claimed falls within the terms the policy. Once established the onus shifts to the insurer to establish the application of a condition or an exclusion to limit its liability or to deny part of the claim. The complainant‟s Home and Contents Insurance policy provides coverage is an insured events policy that provides cover for a series of specified events including storm. Cover is subject to exclusions and conditions which are detailed within the policy documentation. This means that not all loss and damage is automatically covered. Rather, only loss and damage caused by an insured event during the period of insurance and subject to the conditions and exclusions, is covered. The full details of the policy coverage are contained within the Product Disclosure Statement (PDS) and the Certificate of Insurance (COI). There is no dispute that the complainant received the PDS and the COI and thus I am satisfied the insurer is entitled to rely upon the terms and conditions of the PDS and COI to assess its liability to the complainant regarding the claim. Insurer seeks to limit liability The insurer accepted the complainant‟s claim s but seeks to limit its liability in accordance with the terms and conditions of the policy. The PDS details that the policy provides coverage in the event of loss or damage caused by a storm. However, as stated, this coverage is subject to exclusions within the PDS. The insurer relies on exclusions relating to gradual deterioration, lack of maintenance, defective and faulty workmanship and erosion or earth movement. The relevant terms of the policy are set out in section 3.2 of this determination. Circumstances of the claim ( …. 26815) After a heavy rain event on 8 December 2020 the complainant lodged a claim after noticing a leak occurring all over the house, lounge, son‟s bedroom, five walls. On 9 August 2021 the complainant called the insurer to advise of mould throughout her property and on. Additionally, on 16 September 2021 the complainant notified the insurer of a termite infestation and requested cover for the damage. Determination | Case number: 924498 Page 4 of 13 The complainant says her roof leaks every time it rains, there is mould in the ceiling cavity and seeks the insurers trades to rectify the issues. The insurer partially accepted the claim and provided cash settlements as noted below:  $38,105.85 temporary accommodation including $6,105.85 ex-gratia temporary accommodation  $10,450 building repairs per the quotation provided by GR…. 5 July 2022  $1,467 contents settlement per approved schedule of loss…. 2 June 2022  $1,048 replacement mattress…. . 20 July 2022  $1,859 carpet replacement… . 2 June 2022  $1,672 reimbursement of estimated electricity costs to operate drying equipment  $1,500 Counselling services …. 5 July 2022 The complainant has submitted emails outlining her position however no supporting documentation of her own to support her issues with the insurers claims handling and settlements. Whilst the insurer has accepted part of the claim, it denies the balance on the basis that the cost of repairing the roof which is the source or the water ingress, has been identified as being caused by defective works not constructed to code. Expert reports identify defective and faulty workmanship On 24 March 2021 the insurer obtained a report from its expert builder C who say: The building has had additions over the years which do not comply and would have not been engineered and built to best practices. Water is now leaking through incorrect and poorly installed apron flashings. Where there is a change in roof pitch, the roof sheets do not align. Also, there has been roof patches where the overlaid roof sheet is poorly fitted. The expert is of the opinion that the water leaks have occurred because the attending trade, that carried out works on the roof, did not attempt to patch and or rectify the defects on the roof before painting the structure. Whilst it is accepted that the building has had unorthodox extensions/ additions, the entire roof structure is not to code, and any of the works to the roof over the years look to really be of a temporary nature. The report further concludes that incorrect sheet lapping, flashing installation and roofing material were the causation of the water ingress. The expert says the complainant had advised that they purchased the property in 2020 and „had some work done to the roof‟ . A pre-purchase report provided by DK following inspection of the property on 13 February 2020 identified amongst other things  Roof /Gutters / Downpipes ….. “a number of sections, the joins are not weather tight” , “flashings and hips are not properly fitted”, “there is water staining in a number of rooms inside”  Water staining is detected in multiple rooms  Roof – “joins not weather tight”  Floor – “floor not level” Determination | Case number: 924498 Page 5 of 13  General – “it looks as though the house has a dd- ons ……………………. the building works in areas are not built using best building practice” This would indicate the complainant had been reasonably aware of the maintenance issues identified for the roof. R attended to complete a make safe to the roof to prevent further water ingress. On 12 October 2021, C advised they had requested R to undertake a make safe to bedroom three to prevent the ceiling and wall lining from collapsing due to extensive termite damage. R further says that during its inspection, no event-related damage was found relating to termite damage, and the areas affected by live termites have been treated by the complainant's termite expert. On 2 November 2021, the insurer appointed a structural engineer CRD to provide a structural integrity report on the cracked concrete slab who report: 1.0 EXECUTIVE SUMMARY 1.1 This claim relates to the repair of movement damage to the concrete ground slab believed by the Member to have been caused by water ingress. 1.2 We are of the opinion that the movement in the ground slab is due to sequential construction of the floor with inadequate connection between individual portions, poor workmanship and uncontrolled variations in the moisture content of the underlying reactive clay soils. 1.3 Due to the poor standard of construction, persistent moisture and results of ground movement below the residence we do not consider repair of the existing slab on ground foundation to be practical or economically viable and therefore recommend that the slab is removed an d replaced”. The report's findings confirm, the damage to the ground slab is due to the sequential construction of the floor with inadequate connections between individual portions, poor workmanship, and uncontrolled variations in the moisture content of the underlying reactive clay soils. The insurer relies upon the above quoted exclusions within the policy, to deny this aspect of the complainant‟s claim. Ongoing mould no linked to insured event Mould remediation expert S was sent to the property on 16 September 2021 to undertake an inspection and carry out any necessary works. S says:  it did a thorough inspection of the rooms in concern (kitchen, lounge and dining room) and could not find any evidence of mould growth  its technician inspected the bedrooms where mould remediation has been completed and noticed that the concrete slab has visible wet patches  moisture readings were taken, and we recommend a builder inspection for possible rising damp or broken pipe under the slab  a dehumidifier and air scrubber running in the main bedroom and the RH is approx. 27% with this equipment running so there is no current risk of mould germinating from the present moisture in the slab. Determination | Case number: 924498 Page 6 of 13 On 15 November 2021, the insurer obtained a mould investigation report from PRE, a mould specialist who says:  moisture readings on building material was considered satisfactory except for small area of the master bedroom concrete slab  excessive historical dust, debris, cobweb were observed thorough out the property and consistent with a lack of routine house work  mould observed on tiles, however no mould observed an on previously remediated areas  poor standard of housekeeping observed through dining, kitchen and lounge areas In summary, PRE did not find the current mould and debris profile of the property is directly linked to a water ingress event through the roof. PRE did not recommend further remediation due to lingering mould directly attributable to the water ingress event. Conclusion On balance the expert's conclusions are thorough, logical, and compelling, and they are supported by photographs and the testing carried out by its mould remediation experts and engineers. The panel is satisfied that most likely the ongoing issues are related to faulty workmanship and defective design. The available information confirms the damage to the slab is attributed to poor construction and moisture content of the underlying reactive clay soils causing ground movement. The insurer has paid, in addition to the sum insured for temporary accommodation, a one-off $4800 ex-gratia payment to assist the complainant with temporary accommodation and delivering and renting two caravans to the insured home, noting the complainant wished to remain at the insured address to care for animals. Having reviewed all the available information, the panel is satisfied the insurer is entitled to rely upon the terms of the policy to limit its liability regarding this claim. The panel is satisfied the amount paid by the insurer for temporary accommodation, internal repairs, counselling services, contents, and electricity costs meets the insurer's obligations to the complainant regarding the claim. 2.2 Is the insurer entitled to limit its liability for the second claim (…62557) ? Yes. The insurer is entitled to limit its liability based on the information exchanged. Circumstances of the claim ( ……. 62557) On 6 December 2012 the complainant lodged a claim following the overflow of water during a storm event on 30 November 2021. The complainant was concerned as to possible damage to contents stored in the external shed while waiting for remediation on claim ….26815. The complainant advised that since moving these contents into storage shed, storm water runoff had affected the shed resulting in water damage to the stored items. The complainant further held concerns over mould growth in bedroom four, she further noted a crack present in the concrete slab like that in bedroom one of her previous claim. The complainant had placed fans within the shed to attempt to dry the area and minimise damage. She also attempted to create a drainage ditch to divert water away from the shed. Determination | Case number: 924498 Page 7 of 13 The insurer engaged C to assist with the assessment of the loss, R to determine causation and SOW and S to assist with restoration. The panel notes at the time the issues from claim …..26815 had not resolved. Insurer expert reports identify pre-existing damage to the shed The insurers expert R has attended the property and met with the insured to inspect and report on damages surrounding their claim. R reported: At the time of the inspection the insured advised who advised that during a recent storm event an overland flow drainage channel on the left-hand side of the shed overflowed with water which then entered under the shed walls. Soil levels around the shed are too high - in some areas soils is sitting against wall sheets - This could rust the wall sheets overtime and be a source of moisture. The roof and wall sheets of the shed have multiple holes allowing water to ingress in any rain event - Roof and wall sheets appear to be second hand/re-used form another roof. 1x Water Damaged FC wall linings on 2 x sections of shed walls - (Kitchenette side / LHS) Not related to any one single event 2x Water damaged FC wall linings a skirting on Right hand side of shed wall - Not related to any one single event. R building cannot warrant works due to poor construction of shed”. S confirmed that water ingress was not caused by a single weather event, but rather by external ground levels, unsealed penetrations, and holes in the external shed coverings, some of which were caused by rust over time. The insurer says, due to the overgrowth of vegetation surrounding the property; the drains were not effective. Mould growth and overgrown vegetation is widespread across the property and not localised to the affected areas Conclusion The insurer says the building portion of the claim cannot be accepted as it falls outside the cover provided under the policy under general exclusions on page 76 to 81 of the policy and further noted above. The insurer accepted liability for contents but denies the balance because the cost of repairing the source of water ingress, which is caused by the multiple holes in the shed roof and wall sheets, is excluded from coverage under the policy. The insurer experts have shown that water ingress has entered the shed through multiple holes in the shed roof and wall sheets roof as detailed by R. This is the result of maintenance issues, and the primary cause being a result of defect or structural fault of the shed. On 2 May 2022 the insurer asked the complainant to provide a schedule of loss (SOL) for the contents. The complainant provided a SOL on 10 May 2022 for a total loss of $4,227.79. The Determination | Case number: 924498 Page 8 of 13 insurer paid the contents claim on 2 June 2022. A further $357.70 was paid for electrical costs on 20 July 2022 based on an assessment from S. The complainant claimed for damaged carpet in bedroom four. The panel is satisfied this was allowed for in the payment of $1,859 .93 on 2 June 2022 in claim ….26815. The panel is satisfied the insurer has fairly assessment the claim for damage arising from the storm on 30 November 2021.The panel determines the insurer is entitled to rely upon policy exclusions to limit its liability to the complainant regarding the claim, to the amount paid. 2.3 Is the insurer entitled to limit its liability for the third claim (…9510) ? Yes. The insurer has met its liability for damage arising from the storm related event. Circumstances of the claim ….. 9510 and ….3972 On 25 February 2022, the complainant lodged a claim with the insurer for a weather event that flooded her property. She reported that water was seeping through the walls and under the door, and that the house was unliveable and required temporary accommodation. The complainant lodged a further claim (….3972) for loss said to have occurred on 13 May 2022. The complainant claimed water went under garage first and then entered mother‟s bedroom. The insurer engaged W to assist with determining causation. W considered the damage claimed had been present for two to five years most likely because the outside concrete sits at the same level as the inside of the house. The damage was due to design faults and maintenance issues and sort co ver for the same damage as ….9510. C identified there was little to no rain on the date of the claimed event. The complainant disputes this. The panel accepts that even if there was rain, the inundation of the property was most likely due to the design faults and lack of maintenance as highlighted by W. The insurer notes the damage claimed is the same as in claim ….9510 . No additional damage was identified, or contents loss proved. The insurer has proceeded to consider the claim under that event. The panel considers this fair given the nature of the claim. The insurer appointed R to assist in determining causation and S for restoration on claim ….9510 . The panel notes claim ….26815 and …..6 2557 were still open at this time. Expert Reports identify ongoing issues On 6 March 2022 S attended site and met with the complainant to discuss the circumstances surrounding the claim and noted the below: Technicians have advised there is extensive contents damage, as there are other ongoing claims for this property a large number of contents were stacked within the common living area which was impacted during the event. The Kitchen has sustained extensive damage with doors and kicks being swollen shut. Storage will need to be arranged for the Insureds contents in order to access a majority of the affected areas R reported on 20 April 2022 that overland surface water runoff caused damage to the property, entering through the wall frames due to the lack of a structural step between the interior and exterior floor levels. Determination | Case number: 924498 Page 9 of 13 Further internal inspection showed that the carpets were damaged, but the remainder of the property was considered restorable. The external weatherboard is sealed with silicone at the concrete junction as a form of weatherproofing, but this seal had deteriorated at the time of inspection. R noted the construction of the home was not compliant with relevant building standards. As the house floor level is the same as the external path it is very likely that water enters the property during rain events without flood. On R confirmed on 21 July 2022 that the building would experience water ingress regularly due to the way in which it has been constructed. There is no architectural step from the exterior concrete slab to the interior concrete slab, meaning that any water that contacts the external concrete has the capacity to enter the interior of the house. The complainant the insurers builders had damaged the kickboards in the kitchen. The builder responded that it had drilled holes in the kickboards to prevent water from seeping into the internal areas of the house. Missing contents The complainant has alleged contents were not totally reimbursed by the insurer and says there were two mini skips filled with flood damaged contents. The complainant further says that several contents were taken to be destroyed without their knowledge. Upon review of the available information the contents were assessed and removed by S who had asked the complainant to sign an authority to remove and dispose on 7 March 2022. The available information shows that the complainant had signed the authority and had given permission to dispose of items that were not restorable. The insurer has asked, that the complainant provide photos of the damaged items including replacement costs for their review to resolve the issue. In the absence of proof that restorable contents were incorrectly disposed of by the insurer the panel accepts the insurers offer is reasonable in the circumstances. Conclusion The complainant has raised the issue that her property should have been returned to its pre- flood condition. The available information shows that several defects are addressed in multiple reports that were attributed to the water ingress from these three weather events. There is no doubt that these weather events caused flooding, but the complainant had failed to adequately address defects on the property to migrate their risk. The insurer accepted resultant damage and have settled the complainants quotes and provided a cash settlement in a timely manner. The complainant says, the insurer promised to provide temporary accommodation for over six months to a year. The insurer says it has paid the complainant $46,600 in temporary accommodation benefits being the policy limit of $37,000 plus an ex gratia benefit of $9,600. In addition, on 5 July 2022 the insurer paid the complainant a further $1,500 for counselling fees and $992 to replace a mattress. There is no evidence of any other insured loss from claim ….9510 or …3972. The panel is satisfied the insurer has met its liability under the terms of the policy for these claims. Determination | Case number: 924498 Page 10 of 13 2.4 Is the insurer required to pay compensation? Yes. The insurer is required to pay non-financial loss compensation of $1,000. AFCA can award compensation for non-financial loss Under AFCA‟s Rules, we may award compensation (capped at $5,400) for non -financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. However, we adopt a conservative approach to the award of compensation for non-financial loss. We expect complainants to be moderately robust and bear the usual stress and inconvenience associated with an insurance claim. Claims handling has caused inconvenience The insurer agrees that some aspects of the claims handling, particularly regarding the communication with the complainant and the multiple property assessments, were not ideal and may have caused undue stress. The insurer has apologised for the experience and in recognition of the undue stress caused and, in an effort, to resolve this aspect of the dispute, has waved excesses and has further offered $1,000 as compensation for the non-financial loss. The panel have reviewed all the exchanged material and given the circumstances of the claim and the complaint, I satisfied the insurers offer of $1,000 non-financial loss adequately compensates the complainant as communication at times could have been more optimal from the insurer. 2.5 Why is the outcome fair? There is no dispute that the complainant‟s property has been inundated during at least three storm related events since 2020. The panel acknowledges the disappointment and stress this would place on the complainant in particular given the property was only purchased in September 2020. The available information however confirms the insurer has acted fairly and reasonably in assessing the damage and liability under the terms of the policy. The expert reports confirm the pre-existing condition of the property had a significant influence on the loss and application of the relevant exclusions. While the complainant says there are contents missing that were removed by the insurer, no evidence has been provided to support this. The insurer has offered to review this aspect of the claim subject to the complainant providing photographic proof of the items claimed. This is fair in the circumstances. There is no suggestion the insurer has misled the complainant. The exclusions relied upon are not unusual and in fact are contained in most policies. In the circumstances it is fair for the insurer to rely on the terms of the policy in assessing the extent of liability under the claims. Determination | Case number: 924498 Page 11 of 13 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive industry experience We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant policy terms The policy contains the following benefits: Temporary accommodation You are covered for: Determination | Case number: 924498 Page 12 of 13 The costs of temporary accommodation after an insured event happens that makes your home unfit to live in. These costs include: • short term accommodation costs for up to 14 days from when the insured event happened, • ongoing accommodation costs while your home is being rebuilt or repaired for up to 12 months from when the insured event happened until your home is fit to live in. We pay this benefit on top of your home sum insured. The costs of temporary accommodation. Accommodation costs up to the market rental value of your home prior to the insured event happening Counselling services YOU A RE COV E RE D FOR: You to receive counselling sessions with a registered practitioner after an insured event if:  we paid your claim for more than 10% of your home sum insured or more than 30% of your contents sum insured,  you begin the counselling sessions within 6 months from when the insured event happened, and  you give us invoices or receipts for the counselling sessions. GE NE RA L E X CL US IONS : THE POLICY CONTAINS THE FOLLOWING EXCLUSION: Defective or faulty wor kmanship YOU A RE NOT COVE RE D FOR: Loss or damage caused by any inherent or built-in or defective or faulty workmanship, design or manufacture. (But we do cover you if you can show that you or your tenant did not know or could not reasonably have been expected to know about the defect or defective or faulty workmanship, design or manufacture). Erosion and landslide YOU A RE NOT COVE RE D FOR: Loss or damage caused by erosion, landslide, subsidence, vibration, earth shrinkage or expansion or any other earth movement no matter how it is caused (but we do cover earthquake and we cover some landslide or subsidence that happens within 72 hours of the first loss or damage to your home or your contents caused by flood or water runoff – see page 32). Rust and mould YOU A RE NOT COVE RE D FOR: Rust, corrosion, rot, mould or gradual deterioration. Not Covered Determination | Case number: 924498 Page 13 of 13 (But we will cover mould damage to your home or your contents that happens within 21 days of the first loss or damage caused by the insured events of storm, storm surge, flood/water runoff, tsunami, or leaks).

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.