Home / IAG / Determination 923672

Determination 923672

Dispute over claim settlement amount for cyclone-damaged building BH, with insurer delays increasing repair costs

FirmIAG
Decided2023-05-09
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$22,500
Non-financial loss—
Amount claimed$39,000
SourceAFCA PDF

Summary

The complainant disputed the insurer's cash settlement for a cyclone-damaged farm building, arguing delays inflated repair costs. AFCA partly upheld the complaint, ordering a further $19,500 plus about $3,000 pest control costs and interest, and found the insurer's $10,800 compensation offer reasonable.

Insurer delays and poor communication contributed to higher repair costs but were not the sole cause, so a 50% contribution to the $39,000 sought was fair, and the ex-gratia offer exceeded what AFCA could award.

Issues

Subjects and remedies

home or building damagenatural disastersmall businesspay claimpay compensationpay interest

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 923672 Financial firm Insurance Australia Limited Determination | Case number: 923672 Page 1 of 9 Case number: 923672 27 April 2023 1 Determination overview 1.1 Complaint The complainant held multiple covers of insurance for the various components of her farm property (farm buildings, farm vehicles, livestock etc) bundled together under a Rural Farm Policy (the policy) underwritten by the financial firm (insurer). On 21 April 2021, a claim was lodged under the farm property damage section of the policy for damage to several structures on the farm due to Cyclone Saroja on 11 April 2021. The insurer has accepted the claim. However, the complainant is not satisfied with the insurer’s settlement offer for damage to one of the homes ‘BH’ on the property. The complainant says due to the insurer’s unreasonable delays and poor communication, the cost to repair BH now exceeds its sum insured, while it had originally been quoted for a lower amount. The insurer says, given BH’s cost of repairs, it is a total loss for the purpose of the policy. It has offered the maximum the complainant is entitled to, based on the policy benefits including the $40,000 Additional working costs benefit and $10,000 removal of debris. In addition, the insurer has offered ex-gratia payment of $10,800 ($5,400 indirect financial loss compensation and $5,400 in non-financial loss compensation) as well as interest on the settlement payment. 1.2 Issues and key findings Is the insurer’s final claim settlement offer fair in the circumstances? No. The insurer’s overall management of the claim and poor communication has caused unreasonable delays, which more likely than not has contributed to an increase in repair costs. However, it would not fair to accept the insurer’s failures are the sole cause for the repair costs increasing since the initial assessment and associated scope of works and quote. Accordingly, the insurer is to increase its claim settlement payments as set out in section 2.1 which represents a fair contribution towards the increase in the cost to repair BH. Is the complainant entitled to additional compensation?? No. The insurer has made an ex-gratia offer to pay the complainant $10,800 in compensation relating to his experience under the claim. The offer is reasonable and exceeds what AFCA would have awarded and/or could award for such compensation under its Rules. Why is the outcome fair? The determination is fair because it accepts both parties to this complaint have raised reasonable positions regarding the issues in dispute. Based on the available information, although it is fair that the insurer increases its final settlement, it would be unfair to require the insurer to pay the full extent of loss being claimed by the complainant. Further, the insurer’s offer to pay $10,800 in compensation is reasonable. Determination | Case number: 923672 Page 2 of 9 1.3 Determination This determination is partially in favour of the complainant. The insurer is to increase its final settlement payment to the complainant in line with section 2.1 of this determination. The insurer is to pay interest on the additional payment towards repairs to BH in line with section 57 of the Insurance Contracts Act 1984 (the Act), from 28 January 2022 to the date on which the additional payment is issued under the claim. The insurer’s offer to pay the complainant $10,800 in compensation for its poor management and communication over the life of the claim is reasonable. Determination | Case number: 923672 Page 3 of 9 2 Reasons for determination I have considered all the information provided by the parties. There is no dispute a significant weather event caused extensive damage to several structures at the insured property. Further, that the claim has been accepted with the insurer having assessed, investigated and accepted to cover loss or damage covered under the policy. The issues in contention under this complaint are limited to the damage to and associated cover for BH as well as the insurer’s overall management of the claim. Consideration of this determination will be limited to the issues that remain in contention. 2.1 Is the insurer’s final claim settlement offer fair? No. Considering what is fair in the circumstances and in line with the available information, the insurer is to increase its final claim settlement for the damage to BH but not to the extent claimed by the complainant. Cover under the policy is subject to conditions, limitations and exclusions The insurer provided the complainant with the relevant policy documentation including the product disclosure statement (PDS) and certificate of insurance (COI). Therefore, I accept the insurer is entitled to rely on the policy provisions to assess its liability under the claim. The policy covers farm buildings against loss or damage caused by one or more of the listed insured events, including ‘Wind, rain, hail, snow or escape of liquid’ . The policy also covers accidental loss or damage, where such damage is not due to one of the listed insured events. Cover under these benefits is subject to the conditions, limitations and exclusions specified in the PDS. The complainant has established loss or damage to which the policy responds There is no dispute multiple farm buildings have been significantly damaged due to a cyclone event, which triggers cover under the policy. The insurer has accepted the claim and offered to cover loss or damage it has assessed to be consistent with the insured event , subject to the policy provisions which include specified sum insured amounts for the various structures. There is no dispute BH was one of the farm buildings that was significantly damaged by the cyclone and which has been accepted under the claim. The dispute between the parties relates to the insurer’s assessment of and associated cash settlement offer for the damage to BH. The insurer says it has accepted and paid the complainant’s maximum entitlements allowed under the policy for loss or damage to BH. Given there is no dispute the damage to BH triggers cover under the policy, the onus rests with the insurer to show an entitlement to limit its liability under the complainant ’s claim for the damage to BH in line with the policy. Relevant information not in dispute between the parties I have carefully considered all the information from the parties including multiple consultants’ reports, communications between the parties, claim file notes and the provisions of the policy. I am satisfied, relevant to this complaint, the available information establishes:  on 11 April 2021, Cyclone Saroja caused significant damage to farm property insured under the policy including BH. At the time of the damage, BH was covered for a total sum insured amount of $200,000 Determination | Case number: 923672 Page 4 of 9  the insurer’s appointed building consultants ‘M’ assessed the damage to BH and provided a repair quote which fell below the sum insured amount of $200,000. The insurer authorised repairs to M  M requested the insurer to appoint an engineer to review the damage and provide drawings for the repairs to be completed to BH. These were needed to provide to the Council and its approval for the works to take place  the complainant, arising from concerns regarding extended delays, arranged for a scope for works and quote from her preferred repairer ‘N’  the insurer appointed engineers ‘S’ who provided the requested information and drawings. M and N were requested to provide fresh quotes based on the information received from S  both M and N increased the scope of work and associated cost of repairs to $269,100.65 (M) and $230,633.95 (N), both of which exceed the policy sum insured $200,000  the insurer given the above, elected to cash settle the complainant for the damage to BH based on the sum insured of $200,000. The insurer also paid the complainant $50,000 under the additional working costs and removal of debris benefits  the complainant was not satisfied with the above and says the insurer should cash settle her based on N’s quote of $230, 633.95, given the delays experienced under the claim  the complainant says she has suffered further financial loss in having to set up alternative accommodation for farm workers, repair further damage to BH due to the delays and in arranging necessary pest control  the insurer acknowledges the level of service provided did not meet the complainant’s expectation and has offered to pay her $10,800 in IFL and NFL. However, the complainant declined and sought further payment of $39,000 under the claim, which the insurer has declined. Delays and poor communication were experienced under the claim I am satisfied the available information supports the complainant’s position that the insurer’s management of the claim and poor communication did result in unreasonable delays. The claim file notes and documentation provided by the parties show there occurred various extended periods of delays and/or inaction by the insurer or its appointed representatives. Some examples of delays and poor communication by the insurer are:  it took close to four months from lodgement of the claim for M to provide its original quote for repairs  it was not until six months into the claim that M requested appointment of an engineer so necessary plans could be drawn and provided to the Council. It is not unreasonable to accept M would or should have been aware of the Council requirements from the start, given the significant scope of the damage and associated repairs  this delay led to an additional delay of three months (9 months into the claim) before M re- attended the insured property to provide a revised scope of works and q uote based on S’s information  after receiving M’s revised scope of works (SOW) and quote, it took the insurer a further six months before it arranged its cash settlement to the complainant (this being 15 months since claim lodgement)  during this six months the available information shows the insurer remained unclear about what section of the policy BH would be covered under as well as whether it was going to arrange the repairs or cash settle the claim. This is despite it being clear six months prior that the cost of repairs would exceed BH’s sum insured of $200.000  there was poor to no communication with the complainant regarding these issues and a revised quote from N was not requested until 6 months after the insured had received M’s revised quote Determination | Case number: 923672 Page 5 of 9  once the insurer decided it was going to cash settle the claim, it did not communicate this to the complainant. The insurer proceeded to arrange the cash settlement without any explanation as to why it had changed its decision to arrange the repairs or how it had calculated the settlement payment amount. I note in the insurer’s claim file notes there is an acknowledgement of the fact there ha d occurred significant increases in cost of labour and materials in Western Australia over the relevant period. The increase in SOW and repair costs not solely due to delays I am of the view it is was not only the delays caused by the insurer that resulted in the revised SOW and quotes from M and N being much higher than the original estimates. The available information shows that the SOW ’s were first increased based on S’s assessment and recommendations to the insurer. I accept, as engineering consultants, S are the more qualified consultants. I am satisfied it was necessary for the insurer to act on S’s information and request M to provide a revised SOW and quote considering S’s findings and recommendations . Similarly, it was fair that the insurer also requested N to provide a comparative revised SOW and quote taking into consideration the information from S. These revised quotes from both M and N are higher that their original estimates. I accept both these revised quotes exceeded BH’s sum insured and render it a total loss under the policy . Given this, I am not satisfied it would be fair to hold the insurer solely responsible for the increase in the costs to repair BH. Th e available information shows it was S’s assessment that identified the need to increase the SOW (and therefore the cost of repairs). As discussed above, I accept the insurer’s poor management and communication will have had an impact on the repair costs due to the significant increase in the cost of labour and materials. However, I am also satisfied the insurer was obliged to accept an increase in the SOW based on the engineers’ assessment and failure to do so would not only be contrary to its obligations under the policy but a failure to act with the utmost good faith. Therefore, I am satisfied the insurer’s poor manageme nt and associated delays are not the only reason for the increase BH’s repair costs. Insurer to increase final claim settlement for BH under the claim The complainant believes the insurer should be required to pay an additional $39,000 given its failures and the impact this has had on BH’s total repair costs. She is also seeking cover for expenses incurred in having to arrange pest control services due to the extended time the property has remained unoccupied. The insurer says it has paid the complainant her maximum entitlements under the claim. The insurer says it is not required to cover consequential loss, as this is excluded under the policy. I acknowledge the policy excludes consequential loss, however, this would reasonably apply to such loss that may arise or is related to circumstances experienced in the normal processing of a claim. I do not believe this exclusion applies to circumstances where such loss arises from the insurer’s errors or failures. I am satisfied, subject to the complainant providing the insurer with proof of payment, it is fair that the insurer reimburses the complainant for the reasonable claimed pest control expenses (estimated to be around $3,000). Determination | Case number: 923672 Page 6 of 9 The available information shows it is more likely than not the cost to repair BH would have exceeded the sum insured amount of $200,000 regardless of the insurer’s poor communication and delay. In saying that, I accept it is also fair to accept that the delays and poor communication by the insurer did contribute to the increased repair costs. Had the insurer and its appointed consultants managed the assessment process to expected standards, it is more likely that the cost to repair BH would have been lower than where they eventually ended up. Given this, and considering what is fair in the circumstances, I believe it is reasonable to require the insurer to contribute a further $19,500 towards the cost of repairs (in addition to the pest control expenses). This is based on a 50% contribution towards the $39,000 being sought by the complainant. The insurer is to include this additional settlement into its calculation and offer to pay interest in line with section 57 of the Act, to be calculate from 28 January 2022 to dates these payments were/are issued under the claim. For clarity, interest on BH’s sum insured of $200,000 is to be calculated to 27 July 2022, which is when the payment was issued under the claim. The insurer is to arrange the above awarded payments 14 days from receiving notice of the complainant’s acceptance of this determination. 2.2 Is the complainant entitled to additional compensation? No. The insurer’s offer to pay the complainant $10,800 in compensation under the claim is reasonable in the circumstances. The AFCA Rules allow for an award of NFL The AFCA Rules (Rule D 3.3) allows for an award of up to $5,400 for non-financial loss compensation, if the insurer caused the complainant to suffer an unusual degree or extent of inconvenience, delay or interference. AFCA takes a conservative approach when considering any award of compensation. The insurer’s offer to pay IFL and NFL is reasonable I acknowledge the complainant’s various concerns regarding her experience under the claim given the insurer ’s poor management and communication over the life of the claim. I accept the insurer ’s failures contributed to the increase in costs the complainant will incur in repairing BH, which has been considered in section 2.1 above. In addition to financial prejudice, I accept the insurer’s failures cause d the complainant to experience unreasonable levels of stress, anxiety and inconvenience. This would usually result in the consideration of an award of compensation to the complainant under the AFCA Rules. However, in this instance, the insurer has acknowledged is failures and as a result offered to pay the complainant $10,800 in compensation. This offer represents an amount greater than what AFCA would have otherwise offered and/or the limits provided in Rules. Accordingly, I am not in a position to require the insurer to pay any further compensation under the claim. 2.3 Why is the outcome fair? The determination is fair because it accepts both parties to this complaint have raised reasonable positions regarding the issues in dispute. Based on the available information, Determination | Case number: 923672 Page 7 of 9 although it is fair that the insurer increases its final settlement, it would be unfair to require the insurer to pay the full extent of loss being claimed by the complainant. Further, the insurer’s offer to pay $10,800 in compensation is reasonable. Determination | Case number: 923672 Page 8 of 9 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. W e have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant policy provisions What We pay if property is damaged or destroyed’, Replacement This is what We pay if ‘Replacement’ is shown on the Certificate of Insurance for the Farm Building or Other Property … We only pay up to the sum insured shown on the Certificate of Insurance for the Farm Building and Other Property damaged or destroyed for all claims arising out of the one event. Determination | Case number: 923672 Page 9 of 9 … Additional working costs We pay up to the greater of $10,000 or the amount shown on the Certificate of Insurance, towards the reasonable costs You incur to maintain a farming or grazing activity at the Farm Premises as a consequence of physical damage to a Farm Building… … We do not pay for a cost You incur more than 12 months after the date of the damage. … General exclusions applying to all policies’, 2 Consequential loss  consequential loss of any kind or description whatsoever. This exclusion does not apply to: … - the extent that an additional or optional benefit in a policy in this Plan expressly extends to cover consequential loss. 3.3 AFCA Rules D.3.3 An AFCA Decision Maker may decide that the Financial Firm is to compensate the Complainant for non-financial loss: a) for a complaint r elating to an individual’s privacy rights - injury has occurred to the Complainant’s feelings or humiliation has been suffered by the Complainant; or b) for other complaints – an unusual degree or extent of physical inconvenience, time taken to resolve th e situation or interference with the Complainant’s expectation of enjoyment or peace of mind has occurred.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.