Home / Suncorp Group / Determination 923154

Determination 923154

Storm damage claim: adequacy of cash settlement for internal and roof repairs, accommodation, maintenance warning, fraud allegation and non-financial loss

FirmSuncorp Group
Decided2023-11-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,500
Amount claimed—
SourceAFCA PDF

Summary

Homeowners disputed the insurer's partial cash settlement of a storm claim, roof cover, maintenance warning and handling. AFCA found the roof fastening damage was storm related, required updated market-rate settlement including accommodation, rejected the fraud allegation and awarded $2,500 non-financial loss.

Weight of expert evidence showed storm winds lifted roof fastenings and sheets, so the damage is covered and settlement must reflect current market quotes, while fraud was not proven and claim handling delays justified $2,500.

Issues

Subjects and remedies

health or medicalhome or building damagenatural disasterpay claimpay non financial lossreassess claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 923154 Financial firm AAI Limited Determination | Case number: 923154 Page 1 of 17 Case number: 923154 22 August 2023 1 Determination overview 1.1 Complaint The complainants hold a general insurance policy with the financial firm (insurer) covering their home building. The insured home sustained storm damage on 26 February 2022 and a claim was made on 27 February 2022. The insurer offered a partial settlement of the claim. The complainants lodged a complaint with AFCA stating the following:  the insurer should cover the replacement cost of the roof  the insurer failed to make the roof safe which caused ongoing water ingress and the incorrect mould treatment caused additional damage  delays in claims handling meant living with mould, ongoing water damage and no heating and cooling due to storm damage to those building components  The scope of works and/or settlement offered for internal repairs may be inadequate  the insurer provided fraudulent and/or misleading reports  the insurer provided a warning that ongoing cover would not continue if maintenance issues with the roof were not addressed (these issues being part of ongoing water ingress)  The offered sum of $1,000 for non-financial loss does not recognise the issues caused by claims handling. The insurer‟s position is that the roof was not damaged by the storm. It has increased its cash settlement for internal repairs to $23,560.52 to allow a 15% uplift for contingencies. Further, the insurer is prepared to consider temporary accommodation for the period of internal works and has offered $1,000 in non-financial loss for delays in claims handling. 1.2 Issues and key findings Has the insurer offered a reasonable cash settlement? No. The insurer‟s settlement figure for internal repairs requires updating for current market rates. Further, the insurer‟s reports identified popped rivets which lifted due to strong winds during the storm and issues with the lapping of the sheets which is why silicone was applied in make safe repairs. These issues are caused by storm damage and should be settled. The accommodation costs will need to be calculated on the basis of the number of days during which the property will be unliveable during the repair work to be covered by the insurer. Can the insurer refuse ongoing insurance due to maintenance issues? No. The insurer has not established there are outstanding maintenance issues to the insured building. Did the insurer behave fraudulently? No. There is no evidence of fraudulent or misleading behaviour to the standard of proof required. It is common for experts to have different opinions and such differences do not establish fraudulent or misleading behaviour. Determination | Case number: 923154 Page 2 of 17 Are the complainants entitled to additional non-financial loss compensation? Yes. The complainants are entitled to additional non-financial loss due to the duration and impact of the poor claims handling process on them. A total figure of $2,500 is appropriate. Why is the outcome fair? The outcome is fair because it results in appropriate settlement of the claim in accordance with the policy and expert evidence. Further, the non-financial loss component reasonably addresses the impact of the delays in claims handling. 1.3 Determination This determination is partially in favour of the complainants. After accepting this determination, the complainants will provide to the insurer:  three current market rate quotations for the internal repairs together with number of days the repairs will take and the number of days the insured property will be unliveable. If the complainants‟ repair quotation s differ from the A (AB) scope of works identified in this determination, then the complainants need to provide evidence from the quoting party to establish these works are reasonably necessary to effect repairs required due to the storm water damage.  three quotations for repairs to the popped rivets and resultant loose roof sheeting only together with confirmation as to the number of days to complete the works and, if relevant, the number of days the property may be unliveable during the period of the works.  an updated accommodation quotation based on the updated scope of works and number of days the property will be unliveable for internal repairs and the roof repairs. The number of days for accommodation will be calculated on the number of days the property will be unliveable. Within 14 days of receiving the updated quotations from the complainants, the insurer will settle the internal works, roof repair works and accommodation costs on the basis of the average of the market rate costs provided in the quotations from the complainants plus a 15% contingency allowance to allow for unexpected variations to the repair works. The insurer will also make payment of non-financial loss in the sum of $2,500. Determination | Case number: 923154 Page 3 of 17 2 Reasons for determination 2.1 Has the insurer offered a reasonable cash settlement? No. The insurer‟s settlement figure for internal repairs requires updating for current market rates. Further, the insurer‟s reports identified popped rivets which lifted due to strong winds during the storm. This is storm damage and should be settled. The accommodation costs will need to be calculated on the basis of the number of days during which the property will be unliveable during the repair work to be covered by the insurer. There is no dispute that an insured event caused damage to an insured building The parties generally agree that an insured event of storm occurred which caused damage to the insured building. Based on the submissions from the complainants and the insurer, the following items or settlement amounts are in dispute:  internal damage to plaster and paintwork through the home  damage to the roof  accommodation costs whilst repairs are conducted. I also note that the original insurance claim from the complainants included items such as heating and cooling units. The insurer‟s assessment reports have acknowledged these units are required to be replaced and AFCA has not received submissions suggesting these units or any other items are currently disputed. 2.1.1 Internal repairs The parties agree that internal repairs are covered The parties agree that storm water damage occurred to the insured home building creating damage to the painted plaster ceilings throughout the home. The original complaint form to AFCA suggested that the amount of $20,487.42 was insufficient and did not allow for contingency fees. The insurer has increased the offered settlement sum for internal repairs to $23,560.52 based on an allowance of 15% for contingencies. The complainants raise concerns about internal repair costing The complainants have stated in email dated 17 July 2023 that: We accept and always have accepted the internal settlement (current. completed. costed scope of works required - note the insurer has never offered to undertake this work, it is only fair that if we are expected to source tradespeople we will need to spend time also attaining multiple quotes, and we should have a valid current full set of costings/scope of works to ensure that we can sufficiently complete this work and that the settled totals are reasonable based on received quotations. Accordingly, whilst the items for repair are agreed, it appears there is concern that the proposed settlement amount is insufficient based on a scope of works or costing of same. Determination | Case number: 923154 Page 4 of 17 The settlement should be based on updated market quotes The only scope of works and costings provided for the internal repairs has been provided by the insurer, in the A (AB) report dated 26 September 2022. The complainants have not provided any alternative quotations for the current scope of works or market rate repair costs. It is clear however that the insurer is not proceeding to undertake works itself. Accordingly, the cash settlement must reflect the market rate to complete the internal repairs. Whilst AB has provided a cost calculation for the work, nearly a year has passed since that scope of works and costing was provided. This is problematic as there has been ongoing damage to the plaster ceilings and continued mould growth. It is not known if the plaster sheeting is salvageable and can be adequately prepared for painting. The insurer has allowed for a 15% contingency for variations to the scope of works which is appropriate if the plasterboard can be adequately prepared for painting. However, this amount may be insufficient if new plasterboard is required as this will likely exceed the 15% contingency allowance made by the insurer. It is also unknown if the quote from AB is still reflective of current pricing. I consider it unlikely given the current impacts of inflation and the rising costs for materials in the building industry on market rates for building repairs. The complainants will need to obtain three updated quotations based on the A Scope of Works outlining the Internal Works to establish the current market rate for settlement of those internal works together with an estimate of the number of days the repairs will take and the number of days the property will be unliveable. If the plasterboard requires replacement, then the complainants need to produce adequate evidence from each of the repairers they obtain quotations from in relation to the internal works of the necessity for such works. If the complainants can establish the plasterboard should be replaced, then this cost will need to be incorporated into the scope of works for the internal repairs. 2.1.2 Damage to the Roof The roof can only be covered if it was damaged due to the insured event of storm The policy of insurance will only extend to cover loss or damage caused by a storm. A storm is defined in the policy as: …a storm, cyclone or sever e atmospheric disturbance. It can be accompanied by strong winds, rain, lightning, hail, snow or dust. Accordingly, if the roof has been damaged by the insured event of storm, then the complainants could seek cover for the roof only to the extent of the damage caused by the insured event. The evidence demonstrates the roof sustained damaged from the storm event There are multiple reports provided by the parties regarding the cause of loss and the condition of the roof. After reviewing each of the reports provided, I note that only one of the reports suggests the roof had sustained hail damage to 70% of the roofing sheets due to a hail storm on 3 March Determination | Case number: 923154 Page 5 of 17 2022. The date of the hail storm occurs after the original claimed date of loss for this claim which was 26 February 2022. However, a different report provider who attended for an inspection on 4 March 2022 did not report finding any hail stone marks on the roof. This was close in time to the noted hail storm. An examination of every other report recording the roof condition or cause of loss fails to provide any suggestion of visible hail stone damage, this includes the complainants ‟ own second report. I would have expected this to be recorded in the complainants‟ report if the expert had noted hail stone damage to the roof. I further note that the report recording hail damage also records the roof sheets are loose to walk along, which supports the other roof reports of the roof sheets being uplifted during the storm. On balance, the weight of the expert evidence, with the one noted exception, appears unanimous in identifying the roof sheets as having lifted due to high winds which allowed water ingress into the property. Interestingly, several of these reports suggest the fastenings for the roof sheets had also lifted. There are two main reasons given for this:  there are aged roof screws that are non-compliant roof penetrations above the areas of damage. Various other roof screws were lifted due to age wear and tear  after 3-4 days of torrential rain and high coastal winds, the roof has likely lifted and/or caused damage to some rivets and rivet points enabling the water to enter the property. The opinion suggesting the aged roof screws are non-compliant is unclear as to whether, at the time the roof screws were installed, the screws were compliant or were always deemed to be non-compliant. This is an important distinction as the policy does not cover any component of the home that has been built or repaired if it was not in compliance with relevant building laws at the time the work was undertaken. Currently, there is no submission from the insurer suggesting this is the case or adequate expert evidence to support such a submission. I consider the screws were more likely lifted as a result of the storm based on:  the nature of the event being a substantial storm event over a period of several days with high winds and rain  the lack of prior water damage noted in any of the reports  the sudden failure of the roof during the storm and ongoing issues with the roof despite application of silicone in make safe repairs. The make safe repairs appear to me to be evidence that there was storm damage to the roof requiring repairs, noting that silicone is only a temporary repair  the roofing reports closest in time to the claimed event state the sheets have lifted but do not record issues of rusted screws which would have been in situ at the time of inspec tions  The later reports which are generated 5-6 months after the storm event record rust on the screws. They do not address or preclude the potential for that rust to have occurred due to the period of time elapsed between storm event and inspection. This is particularly notable given the coastal region of the insured building. Given these factors, I consider that the evidence supports a conclusion the roof screws and fastenings were damaged by high storm winds sufficiently to allow wind to lift the roof sheeting. This is a storm created opening to the roof, or storm created roof damage, which allowed water ingress. This damage is covered by the insurance policy. The cost of repairing this damage to the roof should be accounted for in any settlement provided by the insurer. It is unclear to me from the information provided whether new fastenings could be provided or if the sheets themselves would need to be replaced. An appropriate market value quotation for the storm damage to the roof, being the areas where Determination | Case number: 923154 Page 6 of 17 the rivets and sheets lifted only, should be provided to the insurer by the complainants. The quotation for repairs to the roof should also list the number of days likely to be required to undertake the works and, if the works render the property unliveable, the number of days the property will be unliveable. 2.1.3 Accommodation costs The accommodation costs will not be fully known until the scope of works for internal repairs and roof repairs are known, as it is unclear how many days the property may be unliveable. Prior agreement to accommodation costs A review of the submissions from the parties suggests a general agreement that accommodation costs are required and form part of any claim settlement. One of the complainants suffers from asthma and due to this condition, the painting of the internal repairs will likely cause a health issue and render it unliveable for him. I note the assessor in the Internal Assessment report dated 8 November 2022 has indicated the circumstances make it appropriate for the insurer to make an allowance for accommodation for the internal repairs. I agree that the complainants will need accommodation for the duration of the painting required as part of the internal repairs as already agreed. Accommodation costs will need to be updated It is unclear yet whether the roof repairs will also require the complainants to vacate the insured property. This may increase the days that alternative accommodation may be required. It would also be appropriate to update the accommodation quotation after the complainants have received confirmation of how many days the internal repairs will take. 2.2 Can the insurer refuse ongoing insurance due to maintenance issues? No. The insurer has not established there are maintenance issues required to be undertaken to the insured building. The insurer wrote to the complainants requiring roof maintenance On 10 November 2022, the insurer wrote to one of the complainants explaining that there were maintenance issues identified at the insured property. The insurer particularly noted that: Under the terms and conditions of your policy, you are responsible for keeping your home well maintained and in good condition. You are responsible for carrying out general maintenance repairs at your property. Failure to do so may impact our decision to accept future claims, offer you renewal of your policy and it may also lead us to cancel your policy. The insurer and the covering email refer to a report, but it is not clear which report was attached to the correspondence. The correspondence between the parties appears to Determination | Case number: 923154 Page 7 of 17 suggest the maintenance issues refer to the roof and to the application of silicone being a temporary repair. The policy of insurance does not cover maintenance items It should be noted that the policy of insurance between the complainants and the insurer does not provide cover to maintain the home for items that degrade over time. The policy states it does not cover: Loss or damage to, or caused by, connected with or arising from, or liability caused by, connected with or arising from: wear, tear and gradual deterioration. Further, the policy requires an insured to take certain steps such as: keep the home structurally sound, watertight, secure and well maintained (e.g. remove mould, fix any holes in floors, walls and ceilings, fix loose, missing or rusted steps, gutters, flooring); The insurer has not established maintenance is required to insured building Based on my findings above, the roof has storm damage which is required to be settled by the insurer. The identified issues with the roof should not be deemed as maintenance issues by the insurer which would allow the declinature of the claim if the maintenance works were not completed. I have noted that there are a substantive number of assessment and roofing reports in relation to the insured building which do not particularly identify or refer to any maintenance issues which required attending to by the complainants. Further, the report dated 26 April 2023 from the complainants‟ experts recorded that the roof had been sealed and painted in August 2018, which suggests that the complainants were maintaining the roof. The insurer has not identified any outstanding maintenance issues which are required to be undertaken to the insured building. 2.3 Did the insurer behave fraudulently? No. There is no evidence of fraudulent or misleading behaviour to the standard of proof required. It is common for experts to have different opinions and such differences do not establish fraudulent or misleading behaviour. The complainants have made a serious allegation of fraud The complainants have alleged the insurer has acted fraudulently by providing misleading information in its expert reports. The basis for the allegation appears to be largely due to the changing description of the roof ‟s condition between reports from the same or other providers. Determination | Case number: 923154 Page 8 of 17 Serious allegations require a particular standard of proof An allegation of fraud is a serious allegation which requires a certain standard of proof to establish the allegation. A serious allegation requires clear and cogent evidence to establish the matter alleged and cannot be reasonably established with inexact proofs, indefinite testimony or indirect inferences. 1 It must also be considered whether the inference the complainants has drawn, namely fraud or misconduct, is more likely than a competing inference. 2 The complainants have not provided sufficient evidence to establish fraud The complainants have alleged the changes of opinion for „fair‟ and „good‟ in terms of describing the condition of the roof are misleading and/or fraudulent in nature. I note that there are references within the correspondence which refer to the inability of one of the roofers to attend because they no longer worked with the company. This suggests that for at least one of the companies, there were different individuals attending. Further, the reports are all generated from different companies which means a variety of individuals gave their opinions on the condition of the roof and cause of the loss. In the context of insurance, fraud would best be defined as a dishonest act or omission by the insured or the insurer designed to obtain a material advantage over the other party. This would require the complainants to provide evidence that the insurer or their expert has deliberately changed their opinion in order to disadvantage the complainants. However, the complainants have not ruled out the probability that the changes in the report are simply caused by a difference of opinion regarding what the individual expert deemed to be fair or good condition. I have not been referred to an objective standard of what may be considered „good‟ or „fair‟ for the roof which should have provided a standardising of the opinion by objective measures. Given this, there is no basis to suggest the experts have not fairly or honestly provided their opinion. This is particularly given it is common for expert opinion to vary. In this case, the roof has been damaged by storm and is being viewed by experts at different times after the event when further damage may have occurred. This likely led the experts to form different conclusions. The complainants have not established the insurer has conducted itself in a misleading or fraudulent manner. 2.4 Are the complainants entitled to additional non-financial loss compensation? Yes. The complainants are entitled to additional non-financial loss due to the duration and impact of the poor claims handling process on them. A total figure of $2,500 is appropriate. 1 Briginshaw v Briginshaw 60 CLR 336 at p 362 per Dixon 2 Australian Associated Motor Insurers Ltd v Elmore Haulage Pty Ltd [2013] VSCA 54 at p 61 per Kaye Determination | Case number: 923154 Page 9 of 17 The insurer has offered $1,000 in compensation to the complainants The complainants have been offered $1,000 in non-financial loss compensation from the insurer. The insurer has indicated this sum was for stress caused by its delays in handling the claim. The complainants have indicated such a sum does not adequately represent the claims handling delays and the impact it has had. AFCA’s app roach to non-financial loss compensation When deciding whether to award compensation for non-financial loss, AFCA looks at the severity and duration of the impact of the financial firm‟s conduct on the complainant. AFCA takes a conservative approach to assessing compensation for non-financial loss. The maximum award for non-financial loss is $5,400. In deciding whether to award compensation, AFCA expects complainants to be moderately robust, to bear the normal degree of inconvenience experienced when a problem occurs and take reasonable steps to manage the situation. AFCA will only award compensation for non-financial loss where there has been an unusual amount of:  physical inconvenience  time taken to resolve a situation  i nterference with the complainant‟s expectation of enjoyment or peace of mind AFCA will look at the time frames and the type of inconvenience or hardship caused to the complainants to determine any appropriate award. A short duration is likely to be only minutes, hours or days. Medium duration is likely to be from a few weeks to a few months. Long duration is likely to be more than six months. Very low impact may include mild frustration, inconvenience and annoyance. Low impact may include more significant frustration, inconvenience and annoyance. Medium impact may include high levels of inconvenience, distress and some financial hardship. High impact may include more severe distress and hardship. Severe impact may include distress requiring medical treatment, physical injury, very severe financial hardship, and homelessness. AFCA may also consider whether the complainant has contributed to their loss arising from the financial firm‟s conduct. If so, it may be appropriate for the financial firm and the complainant to share responsibility for the loss. Additional non-financial loss is appropriate in these circumstances A review of this matter suggests the following general chronology:  the complainants lodged their claim on 27 February 2022  The insurer arranged for an inspection of the roof to determine cause of loss and attempted several make safe repairs. The earliest reports are dated 4 March 2022 and 2 April 2022 and these reports address the cause of loss and make safe works completed  There are no further reports provided until July 2022 which involve a make safe report and a desktop assessment. The desk top assessment is dated 29 July 2022  The bulk of the expert reports on the cause of water ingress through the roof cavity are dated September 2022 Determination | Case number: 923154 Page 10 of 17 I note that a 4-month time frame for handling claims applies under the General Insurance Code of Practice (Code). This time frame extends to 12 months in the event of an extraordinary catastrophe declaration by the Insurance Council of Australia. The Insurance Council of Australia declared an „Insurance Catastrophe‟ but not an Extraordinary Catastrophe under the Code. The time frames in the code are a general guide, there will be times when it is appropriate for the claim to take longer – particularly if there are complex matters for investigation and resolution. The dates of the reports suggest a delay of approximately 6-7 months before the generation of relevant expert reports on which the insurer seeks to rely. This is despite circumstances where the insurer already had a report confirming the cause of loss was lifted roof sheets. Given that the roof sheets had loosened in the weather, it is not clear why there was no information regarding the repairs required to rectify same. Further, there does not appear to have been an appropriate offer of settlement for internal repairs until the complainants lodged a complaint, some 8 months after the event. This was after the insurer had received several reports indicating the roof sheets had lifted during the storm allowing water ingress. In addition to the above, the complainants also dealt with a continuously leaking roof and mould which can create respiratory issues. It is noted that the insurer attempted to address this issue but given the mould recurred (likely due to ongoing leaks), this would have created ongoing stress. A further concern is that the complainants submit that they have been without heating or cooling since the date of the storm as the storm water damaged their units. It is unknown whether the insurer has attempted any partial settlement of these items which appeared to be agreed between the parties. Due to the length of time to handle the claim and the stress and inconvenience of living in a home with continual leaks and mould, I accept that the impact and duration of the claims handling process on the complainants would have been substantive. In the circumstances, I consider an award of $2,500 is appropriate. 2.5 Why is the outcome fair? The outcome is fair because it results in appropriate settlement of the claim in accordance with the policy and expert evidence. Further, the non-financial loss component reasonably addresses the impact of the delays in claims handling. Determination | Case number: 923154 Page 11 of 17 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 923154 Page 12 of 17 3.2 Assessment Reports and Quotations Record Key points Insurer ARC Report Make Safe 4 March 2022  Resulting damage is listed as water ingress most of ceiling due to wind driven rain penetrating bet ween sheet laps. Insurer ARC Assessment Report 2 April 2022  A physical inspection of the roof on 1 April 2022 revealed the roofing material pre - event was fair with consideration to the age of the products.  Prior to ARC attendanc e, a make safe occurred which sealed the sheet joins to prevent further ingress.  No fu rther maintenance required  Given this advic e, ARC confirm that upon inspection to the insured's property we have identified the point of water entry where the substantial wind and rain that occurred has uplifted the asbestos sheeting, causing large gaps Insurer ARC Make Safe Report 18 July 2022  ARC trades attended and noted previously applied silicone is still in good condition. Some roof nails have rel eased and rais ed possibly due to previous water ingress.  To mitigate f urther damage trades applied sili cone to fill in any gaps and make safe Determination | Case number: 923154 Page 13 of 17 Record Key points Insurer Assessment Report 29 July 2022  The assessment report was based on a virtual review.  Roof leaking causing internal ceiling and wall damage to plaster and paint, and causing mould formation. After 3 - 4 days of t orrential rain and high coastal winds the roof has likely lifted and/or caused damage to some rivets and rivet points enabling water to enter the property in multiple rooms and locations.  ARC provided an original scope of works in the sum of $19,567.48 (GST incl) at a minimum. Mould growth may cause an increase in the scope of works and the report suggested further remediation. However, the assessor notes there is a concern that ARC did not address causation.  Asbestos testing requested and roof report may locate additional areas of damage that have not been confirmed to be event related.  All internal damage will be for acceptance under the listed event of storm with only the portions that h ave sustained damage generally being covered for repair under the policy. Internal damage listed open plan living room, dining and kitchen area, all four bedrooms, toilet, laundry and bathroom.  The report notes that cash settlement for the roof would be p ermitted if the damage to the roof is less than 20%. If the damage is 20 - 50% then roof sheet certification for such repair would need to be obtained and settled if suitable. Anything over 50% damage to the roof sheets would require total roof replacement.  If the roof sheets are as bestos material then temporary accommodation would be required during removal. Insurer Envirohealth laboratory Results 11 August 2022  The roof sheeting sample taken from dining room and rear bedroom ceiling detected asbestos  The ceiling of the kitchen, loungeroom, bedroom, laundry and bathroom ceilings was plasterboard. Insurer Asbestos Roof Report 17 August 2022 T B Plumbing  The roof leaked from the roof line  Damage to lounge room, hallway, 4 bedrooms, toilet, kitchen, dining room and laundry.  The report states there was storm relat ed damage to the roof but then the report states cause of the damage as wear and tear.  An inspection of the roof identified recent make safes to the roof overlaps, aged roof screws and non co mpliant roof penetrations above the areas of damage. Various other roof screws were lifted due to age wear and tear. Determination | Case number: 923154 Page 14 of 17 Record Key points Insurer ARC Report 5 September 2022  The ARC report states there was no storm damage present to the roof and maintenance issues were identified to the roof.  On inspection to the roof identified recent make safes to the roof overlaps, aged roof screws and non - compliant roof penetrations above the areas of damage. It was also not ed that various other roof screws were lifted due to the age wear and tear. Complainants’ Quotation Roof Repairs 7 September 2022  The quotation is for the removal and replacement of the entire roof sheets including asb estos removal and building approvals.  The cost of replacement is $34, 997.60 (GST incl) Insurer A Air conditioning report 8 September 2022  Damage inspected showed backed up storm water flooded aircon units.  Given the amount of water through both outdoor units, it is deemed both units require replacement. Flood water and debris through unit will cause damage to the compressor and heat pump system.  It was recommended to replace both units as excessive amounts of water and debris have entered through the bot tom of the units. Complainant’s Quotation Accommodation 23 October 2022  Quotation is for local accommodation for 4 nights  6 February 2023 to 10 February 2023  The cost of accommodation is $743.60 excl GST Complainants’ Report Hail Impact Damage Assessment 15 September 202 2  The report confirmed there was hail impact damage but lists damage and causation as “70%”. The report later confirms that 70% of the roof was impacted.  The asbestos sheeting felt loose, and this was possible from high winds. Th e damage was consistent with that experienced in a storm with high winds and hail.  There was no maint enance issues contributing to the resultant damage Insurer A Builder‟s assessment report 20 September 2022  From Monday 21st February through to Monday 28th February 2022 the east coast of Australia has been impacted by severe thunderstorms and intense rain, leading to severe flooding from Bundaberg to Lismore. A surface and upper trough combined with a humid airmass to produce a very slow moving airmass that stalled several times over Gympie (Tuesday 22nd - Saturday 26th), the Sunshine Coast (Wednesday 23rd - Sunday 27t h), Brisbane (Thursday 24th - Monday 28th) and the Gold Coast (Saturday 26t h – Monday 28th).Daily falls in these areas ex ceeded several hundr ed millimet r e s in a day and have caused water entry to properties through backed up gutters, overflowing valleys and flooding. The Bureau of Meteorology advis ed SEQ is in the midst of its worst flooding for 30 years and parts of Bris bane have had more than one month‟s worth of rain in one day. The Brisbane River (and associated river systems) are experiencing some of the worst flooding since 2011 with inundation caused to Determination | Case number: 923154 Page 15 of 17 Record Key points thousands of properties.  A Building estimator has completed a comprehensive assessment of the dwelling and the damages that we have observed are consistent with a one off storm event. The water damages to the ceilings are consistent with wind drive n rain during the event. A Building require a roof report to det ermine the owner maintenance r equired to the roof and if there is any storm rela ted damages to the roof. A Building recommend the claim to be cash settled to the insured due to paint delaminating in the laundry and hallway, this is consistent with poor paint adhesion and not related to storm damages. The cornices throughout the dwelling have been painted with a gloss paint which is not typical building practice and we are unable to apply ceiling pai nt over the gloss paint. A are unable to warrant these repairs.26. 09.22 A  A Building esti mator has reviewed the roof report completed by specialist trade  Roof inspection: No evidenc e of damage to the roof. Roof is in good condition, it appears that the owner has just done roof maintenance - sealing all the roof sheet joins with silicone. It i s possible that mould is in the ceiling from condensation due to the low pitch and small roof cavity.  In our professional opinion the internal damages are the result of wind driven rain under the laps in the roof sheets during heavy rain event which has be en rectified by the insured applying silicone to the sheet joins. It should be noted that silicone is a temporary repair measure and not a long term repair. As confirmed in the roof report there is no storm related damages to the roof.  The roof is in good condition and the roof has been painted which is in good condition. No owner maintenance required. Insurer A Roof Report 21 September 2022  Caus ation and resulting damage is listed as Storm back in February. Resulting in mould throughout internal ceiling.  Internal inspection suggested most of the house is mould affected throughout the ceiling - bedroom 1, 2, 3, 4, living room, dining room, hallway, bathroom, kitchen. Except ensuite ceiling and the office ceiling.  Roof inspection found no evidence of damage to the roof. Roof is in good condition. It appears that the owner has just done roof maintenance - sealing all the roof sheet joins with silicone. It is possible that mould is in the ceiling from condensation du e to the low pitch and small roof cavity. “A has requested to do tarping to prevent more damage to the internal ceiling. But this morning while we were on site , C called J from A Building to advise that there is no damage to the roof.”  The general conditi on of the roof is considered good. The asbestos containing „Super 6‟ roof has been paint ed in the past and is in good condition. A small area of the roof is displaying Determination | Case number: 923154 Page 16 of 17 Record Key points paint bubbling most likely from poor preparation prior to paint application, and exposur e to the elements for an extended period.  The roof penetration flashings are in good condition and no signs of potential water ingress were noticed.  These „Super 6‟ type roofs with extremely low pitch are likely to let water ingress during high levels of rainfall in conjunction with high level wind. The water can travel under the roof sheet overlaps and into the ceiling cavity. The addition of silicon to the sheet joins and overlaps should remedy this problem.  Asbest os Contamination in roof cavity. Asbes tos contamination is most likely due to the asbestos containing roof material. We recommend restricting access to asbestos licensed personnel only. Insurer A Scope of Works (SOW) 26 September 2022  The scope of works includes internal repairs to the livi ng room, four bedrooms, laundry, kitchen, dining room, hallway and laundry plaster and paint.  The scope of works also included external repairs to the right side elevation being the supply of a new split system air - conditioner.  The total cost of works was $20,487.41 (GST Incl) Insurer Assessment Report 8 November 2022  The report records that all ceilings damaged except bathroom by leaking roof.  Further investigation is not required to progress the claim.  Assessor comments then state there are t wo roof reports stating no event related damage and with the rain event in February there was no slope for the water to flow away quickly.  The assessor records the complainant as stating the roof sheet lifted and it was not for hail damage.  Assessor records he advised the insured no visible damage to the bathroom and that variation for internal works could commence after roof is replaced. The hallway and laundry ceilings are in latest scope of works and due to compl ainants‟ asthma issues temporary accommodation can be considered but roof is not covered.  No need for tarping as roof is in good condition and there was no evidence of hail damage or hail on the date of loss when claim was lodged. The complaints advised r oof still leaking.  Complainants Updated Roof Report 26 April 2023  The asbestos sheeting felt loose when walked on, possibly from high winds.  The damage is consistent with that experienced in a storm of high winds and hail.  The roof impacts are flaking consistent with hail damage. These flakes occur when high impact ice stones crack the pain to a super 6 roof.  The holes within the lower corrugations have begun mould spots Determination | Case number: 923154 Page 17 of 17 Record Key points and the holes on the higher corrugations have freshly exposed fibres which shows the impacts are rec ent and water is going to ingress in the lower corrugations first.  Recent events relative to the claim include Landsborough storm – extreme hail storm event in the area on 3 March 2022.  There is no evidence o f wind driven rain.  The paint coating has been removed exposing asbestos fibres. The hail appears to have consistently arisen ac ross recent paint work on the roofing.  When walked on the roof feels like some wind uplift has occurred on the roof sheets by the creaking sound consistent with loosened sheet fixings.  The report suggests the roof has 70% hail damage and recommendations include removal and replac ement of the roof. Complainant Roofing Report 2 May 2023  Due to roof likely containing asbestos, only a visual inspection was performed.  There are no visible holes in the sheeting.  Evidence of previous make safe works are visible where silicone was applied to where sheets are lapped.  The sheets could not be lifted to check for water ingress.  We can only assume that water ingress in occurring between the lapped sheets due to them lifting. Insurer Email from A 2 May 2023 and 5 May 2023  There was no hail damage to the identified roof at the time of inspection.  Their opinion is that the roof was not impacted by hail event.  The images of paint peeling from the asbestos roof is related to long term deterioration and not the result of a one off storm event.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.