Whether flooring damage was covered under the first claim or a new claim with a $25,000 excess, plus legal costs, temporary accommodation and delay compensation
Text of the determination
Amended Determination
Case number 920319
Financial firm Chubb Insurance Australia Limited
Amended Determination | Case number: 920319 Page 1 of 18
Case number: 920319 26 October 2023
1 Determination overview
1.1 Complaint
The complainant is a lot owner insured under a Strata Insurance Policy held by the Owners
Corporation with the financial firm (insurer). He lodged a claim on 10 July 2020 after
discovering water damage to his unit‟s bathroom ceiling.
The insurer accepted the claim, but dispute arose as to how the damage was to be repaired
and associated delays. In August 2022, while under repair, the unit was flooded following a
water leak. The complainant says the flooring was damaged due to the insurer‟s builder‟s
negligence and should be covered under the first claim. The insurer accepts liability but says
a faulty water valve caused the damage and this is a new claim with a $25,000 excess.
This dispute relates to whether the flooring is covered under the first or a new claim, the
complainant‟s legal costs incurred, temporary accommodation (TA) and compensation for the
numerous delays and associated financial loss.
1.2 Issues and key findings
Is the insurer liable to pay for the flooring damage under the first claim?
Yes. Most likely the timber flooring was damaged by the failure of the insurer‟s trades to seal
the bathroom water pipe. The insurer must pay the complainant $67,062.90 plus interest from
6 March 2023 under s.57 Insurance Contracts Act 1984 (Cth) (the Act).
Is the complainant entitled to compensation for professional costs incurred?
Yes. The policy does not cover a Lot owner‟s legal costs. Pursuant to AFCA Rule D.5.1 the
insurer must contribute $5,000 to the complainant‟s legal fees and $2,200 for IE‟s report fee.
Is the complainant entitled to further loss of rent/ TA?
Yes. The insurer should pay a further $2,263.68 plus any outstanding TA as per section 2.4
Is the insurer required to pay non-financial loss compensation?
Yes. The complainant is entitled to $4,000 non-financial loss compensation.
Why is the outcome fair?
The outcome is consistent with the available evidence and relevant policy terms.
1.3 Determination
This determination is in favour of the complainant. Within 14 days of notification of the
compla inant‟s acceptance of this determination the insurer is to pay the complainant:
$67,062.90 plus interest from 6 March 2023 pursuant to section 57 of the Act
$7,200 as legal and professional fees plus GM‟s report fee subject to proof of payment.
$2,263.68 plus any outstanding for temporary accommodation as per section 2.4
$4,000 non-financial loss compensation under AFCA rule D.3.3
Amended Determination | Case number: 920319 Page 2 of 18
2 Reasons for determination
Numerous submissions and attachments have been provided by the parties, in particular the
complainant. Various allegations have been made about the insure r‟ s conduct and, claims
handling.
The complainant says the insurer fabricated the „second claim‟ , used this to double the
premium payable and pressured the complainant to withdraw the claim. He says this conduct
impacted on his ability to sell the unit. The complainant also says the insurer engaged in
unlawful and or unreasonable conduct, deliberately misled AFCA and that adverse inferences
should be made.
While I acknowledge the complainant ‟ s comments, I am not satisfied the evidence shows any
deliberate attempt to, mislead, engage in unlawful or unreasonable conduct or fabricate the
„second‟ claim.
This determination is based on the information exchanged and focuses on the relevant issues
in dispute.
2.1 Is the insurer liable to pay for the flooring damage under
the first claim?
Yes. Most likely the cause of damage to the timber flooring of the unit was the failure of the
insurer‟s trades to seal the bathroom pipe. The insurer must pay the complainant $67 ,062.90
plus interest from 6 March 2023 under s. 57 Insurance Contracts Act 1984 (Cth) (the Act).
Complainant has initial onus to prove damage falls within terms of policy
It is established insurance law that an insured has the initial onus to prove, on the balance of
probabilities (that is more likely than not), that the loss or damage claimed falls within the
terms of the policy.
The complainant is a lot owner of a unit (unit 3) that is part of a strata unit development
insured by the Owners Corporation under a residential strata insurance policy. The policy
provides cover for physical loss or destruction of or damage to the insured property arising
from an event in the period of insurance.
An event is defined under the policy to be an occurrence or accident causing or resulting in
sudden and unforeseen, physical loss or destruction of or damage to the insured property.
Circumstances of claim
The original claim was lodged on 10 July 2020 after a tenant reported damage to the
bathroom ceiling. The insurer accepted liability for the damage caused by long term water
ingress from the bathroom in the unit (unit 6) above the complaint‟s unit.
Issues arose as to the method of repairs with further damage caused by the insurers builder
AA to the concrete ceiling slab. This caused considerable delays as noted in the chronology
in section 3.2 of this determination.
After various attempts and further delays appointing a structural engineer, the insurer
appointed AB to repair slab and bathroom damage in the complainant‟s unit. Work
commenced in May 2022, with slab rectification completed by July 2022. It was anticipated
Amended Determination | Case number: 920319 Page 3 of 18
bathroom repairs would be completed by December 2022, but the repairs were not completed
until February 2023.
In August 2022, during the repair process, a water leak occurred resulting in the flooding of
the complainant‟s unit. The wooden floor of the unit was damaged and required replaceme nt.
There is no dispute the damage to the flooring is covered under the policy. The dispute arises
as to whether it should be covered under the first claim or as a new claim under the
2022/2023 policy that would attract a $25,000 excess.
Parties dispute who is liable for the damage
The insurer says the proximate cause, that is the dominate or effective cause of the damage
was a shut off faulty valve. The water supply to unit 3 had to be isolated during bathroom
repair works. The valve that shut off the water failed, mainly due to its age and excessive
building water pressure. The insurer says the valve relied on a rubber washer to shut the
water off which had perished over time.
The insurer relied on AB‟s advice that the valve had failed. The insurer also obtained a report
from SR, a plumber, who confirmed a valve inside the property had failed, causing water
damage. It also said there was evidence the valve had previously been over-tightened and
was in poor condition prior to the flooding event.
The insurer t says this should be treated as a new claim under the terms of the policy
applicable from 1 May 2022 to 1 May 2023. Under this policy the applicable excess is
$25,000. It offered to settle the claim less the policy excess.
The complainant says the insurer should be liable for the flooring damage under the existing
claim as the damage was caused by AB‟s negligence. The complainant says the damage
would not have occurred if AB had engaged a licensed plumber to turn off the stop-tap and
seal the open end of a copper pipe in bathroom as required by the Victorian Plumbing
Regulations (the Regulations). He says it is unfair and unreasonable for the insurer to apply
the $25,000 excess in these circumstances.
Complainant provided persuasive evidence to support his position
The complainant‟s expert GM, a licensed plumber, provided a comprehensive report on 16
December 2022. Relevant particulars are set out under section 3.3 of this determination.
GM‟s key findings were:
AB was required to isolate the water supply to unit 3 by turning off the stop tap through
which mains water flows to the pipes in the unit. AB did not use a licensed plumber to do
this, which is a breach of the Regulations.
AB (also) punctured holes into a copper water pipe connected to the toilet when removing
bathroom tiles with a jackhammer in May 2022.
AB sealed off most of the pipes in the bathroom, as required by the Regulations. However,
the damaged copper pipe was left unsealed.
On 10 August 2022, an uncontrolled discharge flowed through the stop tap and discharged
from the unsealed pipe, flooding the complainant‟s unit .
Similar flooding occurred in the bathroom of unit 6, where AB had (also) failed to seal an
open pipe.
If the open end of these pipes were sealed as required, the escape of liquid would not
have occurred.
Amended Determination | Case number: 920319 Page 4 of 18
GM could not complete a forensic investigation on the stop-tap itself, as SR had
dismantled it despite the complainant‟s prior written instructions to leave it untouched (to
facilitate investigations).
In a supplementary report GM says that by failing to seal the open end of the copper pipe, AB
had relied solely on turning off the stop-tap to prevent a mains water leak into Unit 3. GM
considers this is reckless because stop-taps can often leak, even when turned off. Further,
the stop-tap was in the building‟s garage and anyone could have turned it on, or off.
Proximate cause of flooring damage is most likely unsealed pipes.
The escape of liquid occurred during the repair process. There is no dispute AB was required
to isolate the water supply.
Neither the insurer or its experts have responded to the specific points raised in GM‟s reports,
including alleged non-compliance with the Regulations. A review of the Regulations extract
provided by the complainant confirms a licensed plumber should have been used by AB to
isolate the water supply to unit 3 and seal all open pipes. The evidence indicates while the
stop tap was closed an unsealed pipe was left in the bathroom.
SP confirms the leak occurred from a valve inside the property, but it fails to consider the
possibility of a leak from the unsealed pipe inside the bathroom. SP did not address the need
to seal all pipes.
GM is a suitably qualified expert to comment on what caused the escape of liquid to occur.
GM‟s findings are logical, compelling and cons istent with the circumstances and evidence.
GM confirms that if AB had sealed all the unsealed water pipes as required the flooding would
not have occurred.
I am persuaded the leak would not have occurred if AB had isolated water supply to Unit 3 in
the manner required by the Regulations and confirmed by GM. I am satisfied the proximate
cause, that is the dominant or effective cause of the damage was the failure by AB to seal all
unsealed pipes. The damage is properly assessed under the original claim and does not
attract any excess.
Insurer to cash settle the cost of the flooring repairs
The flooring has been replaced by the complainant‟s contractor TKC with work completed and
invoiced on 6 March 2023 for $67,062. The complainant moved back into the unit on 29
March 2023.
The complainant paid TKC a deposit to commence repairs in January 2023, and the
remainder of the cost on completion of repairs in March 2023. The insurer accepts the cost
charged were reasonable. It is fair in the circumstances the insurer pays the complainant
$67,062 plus interest from 6 March 2023 under Section 57 of the Act until payment of the
claim.
It is also fair, if the insurer has not already done so, that it pays the complainant loss of rent
until 29 March 2023 when the complainant moved back into the unit.
Amended Determination | Case number: 920319 Page 5 of 18
2.2. Is the insurer liable for the complainant’s professional
costs?
Yes. While the policy does not include cover for a unit holder‟s legal costs, under AFCA‟s
Rule D.5.1 the insurer should contribute $5,000 to the complainants legal and reimburse the
complainant $2,200 for the expert report fee.
Complainant engaged lawyer to deal with claim while overseas
When the original claim was lodged in July 2020 the complainant was living and working
overseas. The building‟s insurance broker W arranged a quote from AA to remove a
damaged pipe inside the slab. The insurer ‟s agent L approved these works in July 2020.
The complainant insisted AA cease work after discovering it proceeded without his approval,
causing invasive damage to the slab and further damage to his bathroom from concrete
debris.
He notified the insurer‟s agent L that any work involving a concrete slab must be undertaken
by a specialist builder with experience in concrete works, under a structural engineer‟s
supervision. After L refused to appoint either as requested, the complainant says he engaged
a lawyer (U) to represent him until he returned to Australia and took over management of the
claim, and the subsequent complaint to AFCA. It is not clear whether he requested any
assistance from the owner‟s corporation to pursue these issues.
In total, the complainant incurred $54,574.14 in legal costs. He says he was compelled to
seek legal advice because the insurer authorised AA‟s work without ensuring the required
approvals were in place. Further he says the insurer and its agents were liable for multiple
delays in as sessing the claim and approving repairs. He says the insurer ignored U‟s
requests for over a year until it finally accepted cover for the additional damage AA caused.
He seeks cover for his legal expenses under section1, clause 4.1 or alternatively clause 9.2.
The relevant clauses are set out under section 3.2 of this determination. In the alternative the
complainant says the insurer has breached its duty of utmost good faith under section 13 of
the Act and should not be able to rely on the terms of the policy to limit its liability.
Insurer did not breach duty of utmost good faith
The statutory duty of utmost good faith requires an insurer to act consistently with commercial
standards of decency and fairness and with due regard to the interests of an insured. An
insurer is no entitled to rely on a provision of the policy if to do so would amount to a breach
of duty of utmost good faith.
The insurer acknowledges there were delays. However, it says these were largely outside its
control because:
the claim involved complex circumstances and repairs, which in turn required advice from
numerous experts and variations to the scope of works
it was not evident that an engineer was needed to assist with slab repairs, until (after) it
received the complainant‟s consulting engineer IM‟s report in October 2020
its builder AB could not start repairs until an engineering scope of works was prepared,
which was only available in June 2021 due to difficulties experienced by its structural
engineers
building permits could not be obtained until April 2022, which it blamed on industry-wide
disruption arising from the COVID-19 pandemic and government restrictions
Amended Determination | Case number: 920319 Page 6 of 18
it acknowledged its surveyor SP delayed this process throughout the latter part of 2021
and had to be replaced.
The insurer authorised the quote from AA, which led to additional damage. This may have
been avoided if the insurer took prudent steps to mitigate against such risk, by appointing a
structural engineer at the assessment stage. The failure to do so falls short of good industry
practice in the circumstances.
The available information confirms the repairs and scope of works required multiple experts
and revisions to the repair scope of work and methodology.
Despite the additional damage the insurer acted on i ts builder S‟s advice and did not appoint
a structural engineer. It is not unreasonable to have acted on S‟s advice in the absence of
other information.
On receiving the complainant‟s expert (IM), report in October 2020 the insurer acted
reasonably and ob tained a structural engineer‟s advice in December 2020, after reviewing
IM‟s report and accepting its findings.
There was then a further 3-month delay until the premises were inspected, given two of the
structural engineers the insurer appointed had to be replaced. After its engineering expert TG
inspected the premises in February 2021, it delayed providing the scope of works until June
2021. L described TG‟s conduct as “appalling”. In hindsight the insurer could have appointed
one of 3 structural engineers nominated by the complainant in November 2020. However, L
and its loss adjuster CL preferred to use their own, which ultimately caused further delay.
All this occurred during a period where there were significant restrictions imposed on
movement in metropolitan Melbourne during Covid – 19 closures. This impacted on the
availability of trades and assessment of claims.
I accept that taking more than 30 months to repair the damage is an exceedingly long time
and some circumstances might be considered a breach of duty of utmost good faith. While I
accept the claims handling did not meet industry standards I do not accept, in the
circumstances of this case, this amounted to a breach of duty of utmost good faith.
The issues did not involve acceptance of liability but decisions as to repair methodology and
proximate cause. Numerous experts were contracted and no doubt the unusual
circumstances in place during the repair period due to Covid-19 restrictions would have
significantly contributed to the delays.
I am not satisfied the circumstances establish a breach of duty of utmost good faith. I accept
the insurer is entitled to rely on the terms of the policy in determining liability for the legal
costs incurred.
Policy does not cover Lot owner’s legal or pro fessional expenses in pursuing
claim.
While the complainant has relied on Section 1, clauses 4.1 and 9.2 neither clause applies to
legal costs incurred by Lot owners.
The policy defines You / Your / Insured as the Owners Corporation, Strata Corporation,
Community Title, Body Corporate or like entity stated in the Policy Schedule. Lot owners are
only included as You/Your or Insured in respect of additional benefits 5.10, 5.16 and 6.8; and
optional Covers 7.1 and 7.2. under Section 1.
Amended Determination | Case number: 920319 Page 7 of 18
Clause 4.1 refers to legal and professional fees necessarily and reasonably incurred in the
reinstatement or replacement of Your insured property (emphasis added). While I
understand the complainant‟s submission that the legal costs were necessarily and
reasonably incurred, clause 4.1 extends to costs reasonably and necessarily incurred by the
body corporate, not to the Lot owners.
Clause 9.2 refers to expenses for preparation of claims that You (emphasis added)
reasonably and necessarily incur with Our consent and which are not otherwise recoverable
under this Policy. Again, under this clause cover is provided to the body corporate not the Lot
owners.
There is no suggestion the costs were incurred by the complainant on behalf of the body
corporate. I can find no other section in the policy that extends to provide cover for a Lot
owners professional costs incurred in pursuing the claim.
AFCA can require Insurer contributes to professional costs reasonably
incurred.
Under AFCA rule D.5.1 AFCA can determine an insurer contributes to a complainant‟s legal
or professional costs incurred during the course of a complaint. Unless special circumstances
apply, the compensation payable is limited to $5,000.
There is no automatic right to payment of legal or professional costs. In determining whether
costs should be awarded we will consider the complexity of the complaint and whether the
complainant needed to incur the costs to understand or establish the claim.
Legal costs incurred as complainant
The complainant says he appointed his solicitor (U) after L refused to appoint a structural
engineer following the additional damage caused by AA. He appointed U as he was living
overseas.
He claims U‟s services were regularly required to negotiate issues, deal with ongoing delays
and settle the scope of works. U was required to regularly follow up on loss of rent, given
there was no regular arrangement in place for payment and in certain instances, the insurer
either missed payment or directed payment to the incorrect parties. He says U was also
required to step in after AB and the insurer refused to accept liability for the flooring damage.
I note the complainants brother, in his statement, confirmed he had on numerous occasions
attended the unit after July 2021 to discuss the unit and slab rectification works. He had met
with the site inspectors. This seems to be in addition to U‟s representation.
The issues in dispute essentially involve decisions as to how to complete the repairs (and
liability for the second event). The issues do not involve complex legal issues. I would not
normally require an insurer to contribute to legal costs in these circumstances.
However, while the complainant appears to have had assistance from his brother, the
complainant was overseas and covid-19 had resulted in numerous lockdowns and restrictions
on travel. It was not unreasonable in these circumstances for the complainant to obtain legal
support in dealing with the claim.
I am satisfied the complainant reasonably required the assistance of U while overseas during
the claim process. I consider it fair the insurer contributes $5,000 to the legal fees incurred
pursuant to AFCA rule D5.1.
Amended Determination | Case number: 920319 Page 8 of 18
Insurer should contribute to c omplainant’s report fees
The complainant is also seeking to recover $2,200 paid to his engineer IE.
The insurer acknowledges this was an assessment of the structural integrity of the slab above
the bathroom in unit 3. The insurer accepted the repair scope of work and methodology the
complainant was seeking after reviewing IE‟s recommendations and findings. It is reasonable
for the insurer to agree to cover the report fee.
I am also satisfied the insurer should pay the report fees, if any, incurred in obtaining the
plumbers report from GM. This report was required to respond to the insurer and has been
relied upon in determining this complaint.
Given this, I am satisfied this cost the insurer should reimburse the complainant $2,200 for
IE‟s report a nd costs incurred from GM, subject to the complainant providing a copy of the
relevant invoicing or proof of payment.
2.3 Should the insurer pay non-financial loss compensation?
Yes. The complainant is entitled to $4,000 non-financial loss compensation.
AFCA can award compensation for non-financial loss
Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial
loss where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or peace of mind.
We take a conservative approach to compensation for non-financial loss. It is not awarded
when a person suffers the normal degree of inconvenience when a problem occurs.
Complainant entitled to compensation for non-financial loss
The insurer could have and should have dealt with the claim in a more timely manner. It
should have given some explanation for the delays and the need to change its appointed
experts.
Not all delays can be attributed to the insurer‟s claims handling given the Melbourne
metropolitan Covid-19 orders that existed during the claim and repair process. However, the
repairs took nearly three years to complete with completion dates regularly missed. I am
satisfied the insurer and its agents mishandled the claim at different stages, and this has
contributed to the delays in completion of the repairs.
The insurer ‟ s communication with the complainant was at times poor and often required
further follow up through the complainant‟s legal representative. It failed to ensure the
complainant received regular and consistent payments for loss of rental income.
I am satisfied the complainant suffered significant stress and inconvenience, including
psychological distress because of the insurers claims handling. I am satisfied this entitles the
complainant to compensation at the higher level. In the circumstances I consider it fair that
the insurer pays the complainant $4,000 non-financial loss compensation.
Amended Determination | Case number: 920319 Page 9 of 18
2.4 Is the complainant entitled to further loss of rent/
temporary accommodation?
Yes, the insurer should pay the complainant an additional $2,263.68 for temporary
accommodation plus any outstanding temporary accommodation benefit from 4 January 2023
until 29 March 2023 as set out below.
Complainant says he suffered indirect financial loss
The complainant is seeking cover for the following loss:
the difference between his monthly loss of rent reimbursement and his rent in Tokyo,
Japan between August 2021 and October 2022 ($28,560), on the basis the repairs should
have been complete within a year, and he was compelled to delay his return to Australia
the difference between his monthly loss of rent and his alternative accommodation in
Melbourne following his return to Australia in September 2022.
No evidence complainant forced to stay overseas
Although the complainant says he incurred additional expenses as he was required to stay
overseas due to the delay in the repairs there is no evidence to support this.
There is no claim related reason why the complainant could not have returned to Australia
and sought rental accommodation (as he eventually did) while waiting for the repairs to be
completed.
The insurer was paying loss of rent during this period and I am satisfied this met the insurers
obligations at the time.
Policy provides for calculation of loss of rent/ temporary accommoda tion.
Under the terms of the policy loss rent is payable is an amount of money for lost rent calculated
based on the Annual Rentable Value that applied immediately prior to the event . The complainant‟s
loss of rental income was calculated at a daily rate of $66.79 based on that rent payable.
The complainant claimed temporary accommodation costs from 19 September 2022 after his
return to Australia. Temporary Accommodation costs are calculated as the amount of money for
temporary accommodation based on similar accommodation located in the vicinity of the location.
Although payment was at times not regular, there no dispute that payment was to be made up
to 29 March 2023. The complainant says the no payment has been received to date for the
84 days from 4 January 2023 until 29 March 2023. The insurer advised on 13 April 2023 that
the rent will be paid until 29 March 2023.
If it has not already done so, then the insurer should pay the outstanding rent for the 84 days
plus interest on the outstanding amount from 29 March 2023 pursuant to section 57 of the Act
until payment is made. Payment should be calculated at the rate of $66.79 per day for 84
days being a total of $5,610.36.
The temporary accommodation obtained when he returned to Melbourne on 19 September
2022 was not similar accommodation located within the vicinity of the location. It was not a
unit but a house. The insurer continued to pay the temporary accommodation at the rate of
$66.79 per day. There is no evidence the insurer assessed this rate based on similar
accommodation in the vicinity of the unit.
The insurer argues the temporary accommodation is not comparable to the unit. I do not
accept this is a reasonable position. The complainant returned to Melbourne during the rental
Amended Determination | Case number: 920319 Page 10 of 18
crisis. There is no evidence to indicate the temporary accommodation facilities are excessive
or unreasonable.
The complainant‟s alternate accom modation monthly rate was $2,390 (daily rate of $78.58).
Given this, I am satisfied it is fair that the insurer should also pay the complainant an
additional $2,263.68 being the excess temporary accommodation cost ($11.79 a day), from
19 September 2022 until 29 March 2023 (192 days).
2.5 Is the outcome fair?
Outcome is fair in all the circumstances
I have considered all the information exchanged and recognise the issues that have been
raised. While numerous issues have been raised the determination covers the relevant
issues. In reaching this determination I have carefully considered the terms of the policy,
good industry practice, relevant codes of practice and what is fair in all the circumstances.
Amended Determination | Case number: 920319 Page 11 of 18
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Relevant policy terms
4 Additional Benefits A
Following loss, destruction or damage covered under this Section 1 of the Policy and provided the
Sum Insured is not otherwise exhausted, We will also pay the following costs and expenses incurred
in consequence of the loss, destruction or damage:
4.1 Architects and Other Fees
Architects‟, surveyors‟, consulting engineers‟, legal and other professional fees, clerk of works salaries
and bank imposed charges as necessarily and reasonably incurred in the reinstatement or
replacement of loss, destruction or damage to Your Insured Property.
These fees include legal fees incurred in making submissions or applications to any public or statutory
authority, licensing board or court.
Amended Determination | Case number: 920319 Page 12 of 18
9 Conditions Applying To This S ection
9.2 Claims Preparation Fees
We will pay up to $50,000 or any higher amount shown in the Policy Schedule for professional fees
and other expenses for preparation of claims that You reasonably and necessarily incur with Our
consent and which are not otherwise recoverable under this Policy.
3.3 Event Chronology
Date Item
June 2020 Complainant‟s paint er discovered damage in his unit‟s bathroom
(Unit 3).
A leak detection undertaken by S, an insuranc e panel builder
uncovered water damage to the concrete slab bet ween the
bathroom‟s ceiling and a bathroom above (belonging to a separate
unit, Unit 6).
Complainant notified the building‟s strata insurance broker W.
July 20 20 W lodged a claim with L, who act on behalf of the insurer on a binder
authority. On 22 July 2020, L accepted a quot e from AA, organised
by W, to remove and replac e a damaged pipe inside the concret e
slab.
AA started work in July 2022, and broke a hole (30cm wide) through
the concrete slab between Unit 3 and the unit above (Unit 6), leading
to furt her damage inside Unit 3‟s bathroom from falling debris.
AA stopped work after the complainant insisted the insurer engage a
structural engineer to consult on the repair, and a specialist builder
to complete repairs.
August 2020 L acted on S‟s advice, wh o said an engineer was not required.
L advised W the r esultant damage from the pipe inside the concrete
was c overed, as well as loss of rent.
The complainant appoint ed a consulting structural engineer IM to
inspect the slab.
October 2020 The complainant engaged a lawyer (U) to liaise with L and the other
agents acting for the insurer. U wrote to L and advised the slab was
at risk of collapse, required urgent removal and replac ement, and a
structural engineer to consult on the repair methodology (including
whet her a partial or full replacement was required) .
Amended Determination | Case number: 920319 Page 13 of 18
November 2020 CL, a loss adjuster appointed by L, confirmed indemnity had been
granted for the building damage inside unit 3.
U asked CL and L to confirm if this extended to the additional
damage caus ed by AA, and if repairs would be undertaken in
accordance with IM‟s recommendations.
December 2020 The complainant offered 3 structural engineers he said were readily
available to inspect the damage. This offer was rejected, and CL
appointed its preferred structural engineer CR.
CR were removed by CL, who appointed another structural engineer
MF.
January 2021 CL removed MF and appointed another structural engineer, TG
February 2021 TG inspected the unit and undertook to provide a report and scope
of works . It accepted AA‟s work had further compromised the slab‟s
integrity, and that the slab needed to be replaced.
June 2021 U complained to L about the delay in progre ssing repairs, given TG
was yet to provide its slab design and scope of works for the
required repairs.
L wrote to U and acknowledged TG‟s service was “appalling”. TG‟s
scope of works was received shortly after.
July 2021 L appointed its panel builder AB to provide repa ir quot e/scope of
works, and a surveyor SP to prepare and manage the building
permit process .
Further to U‟s efforts, L (also) agreed to instruct AB to amend the
quote to include the resultant damage to the bathroom caused by
AA‟s repai r work.
August 2021 AB advised it was considering a partial slab replacement. U
recommended the complainant‟s consent was obtained as this was
contrary to TG‟s advice.
September 2021 L obtained further advice from another structural engineer, FS which
s upported AB‟s repair methodology
October 2021 The complainant communic ated his agreement to AB and FS‟s
proposal through U.
L advised AB was arranging building permits .
February 2022 L replaced SP with another survey or, IB .
March 2022 In response to U‟s complaint, AB advised it was yet to receive the
required building permits and highlighted the significant disruption to
the construction industry arising from the COVID - 19 pandemic and
Amended Determination | Case number: 920319 Page 14 of 18
government restrictions .
April 2022 Building permits received .
May 2022 Slab rectification works started .
June 2022 CL estimated repairs would be completed by December 2022 .
July 2022 In accordance with advice from another structural engineer, FS, a
half slab removal and replacement were completed by July 2022. FS
agreed with IM‟s advice that AA further compromised the slab, and
that its work was very poor building practice.
August 2022 While bathroom rectification work was ongoing, water had flooded
the unit and the timber floor had been damaged.
U wrote to L seeking it accept liability for the timber floor damage.
This was rejected, L advised it was the complainant‟s responsibility
to attend to these repairs, and a new complaint could be lodged if
the claim cost exceeded the $25,000 excess.
Dece mber 2022 AB completed bathroom reinstatement works. After the
complainant‟s inspection uncovered inc omplet e works, AB agreed to
complete this.
February 2023 AB completed all bathroom reinstatement works. The insurer agreed
to cover loss of rent up unti l the date of completion.
March 2023 The complainant‟s builder TK complet ed all flooring reinstatement
work, at the cost of $67,062.90.
The insurer offered to consider this as a separate insurance claim,
subject to the $25,000 water damage excess, and loss of rent up to
the date the flooring works were completed.
3.4 Report Extracts
Record Key points
Amended Determination | Case number: 920319 Page 15 of 18
Record Key points
SR Report
25.08. 2022
During repair works, a valve within the property has failed causing
water damage. I have been asked to attend the property
inspected valve and report.
I inspected the valve in question and noticed that the original
handle had been broken off, indicating this valve has had to have
been tightened excessively to prevent water from continually on -
running.
……..
Given an excessively high - water pressure, valves that I would
estimate to be 50 years old and evidence that the valve has been
over tightened (prior to it being used to isolate the water to an
apartment before the valve failed), I can confirm that the valve
was in poor condition prior t o the flooding event.
With the excessively high - water pressure additionally contributing,
water entry has occurred to an apartment under construction.
………
GM Report
16 - 12 - 2022
I have attached a pictorial which visually illustrates the plumbing
issues subject to my opinion, namely the locations of the mains
water supply, the isolation valve (also referred to as a “stop - tap” and
the water supply pipes whic h carry water from the ma ins water
supply through to the water outlets within Units 3 and 6.
With the mains water supply to Unit 3 shut off, in mid - May 2022, AB
then commenced removing bat hroom wall tiles from Unit 3 with a
jackhammer. With the jackhammer, AB accidentally punctur ed holes
into a copper water pipe connected to the toilet cistern. AB did not
repair the holes and left the damaged water pipe in situ for the next
3 months leading up to the flooding emergency in August 2022.
Once tapware attached to the ends of water pi pes were removed,
AB was required to seal off their "open" ends with caps in
accordance with applicable Plumbing Regulations. In Unit 6, AB did
this in relation to all water pipes except one, which AB left unsealed
and "open" for the next 3 months leading up to the flooding
emergency. In Unit 3, AB did this in relation to all wat er pipes
except, as noted above, the damaged copper wat er pipe which AB
left unsealed and "open".
Leaving these two water pipes "open" was in breach of the Plumbing
Regulations whi ch require water popes to be sealed during these
works. This also left Unit 3 badly exposed to the risk of an
uncontrolled discharge of water.
……..
The failure by AB to seal the two "open" water pipes means that,
over a period of months, AB had relied so lely upon the turned OFF
Amended Determination | Case number: 920319 Page 16 of 18
Record Key points
stop - tap to prevent mains water from entering Unit 3. AB's sole
reliance upon the stop - tap breached the Performance Requirement
to avoid an uncontrolled discharge of water int o Unit 3 by exposing
Unit 3 to a high risk of flooding. This is becaus e:
it is well - known that stop - taps (in the OFF position) often leak;
and such relianc e was reckless given the location of the stop - tap
meant that, for 3 months
It is also irrelevant to proximat e cause as to why mains water
passed through the stop - tap in August 2022. This is because had
AB's licensed plumber duly sealed off the two "open" water pipes in
the Units in May 2022 as required by the Plumbing Regulations,
then any water that passed through the stop - tap in August 2022
would have be en prevented from flooding out Unit 3, regardless of
the reason such water was able to pass through the stop - tap at that
time.
After the flooding emergency, AB engaged a plumber Stewart Rose
Plumbing) (SR) who ins pected and pulled apart the stop - tap and
p repared a report on the cause of the flooding. This prevented the
parties from having the stop - tap forensically examined by an
independent third - party plumbing failure specialist which is the
normal practice in severe flooding inci dents such as the present
case. Rose Report concludes that the cause of the flooding was the
sudden failure of the stop - tap ( due to "overtightening") to hold back
the mains water notwithstanding that the stop - tap had been turned
OFF by AB from May 2022 until the floo ding emergency .
Significantly, Rose Report does not mention the two water pipes that
AB had left "open" from which the flood waters discharged. I do not
believe that the Rose Report can sensibly reach a conclusion about
the proximate cause of the flooding without consid ering the two
"open" water pipes.
As explained in paragraph 61 below, even if there had been
"overtightening" of the stop-tap and/or high mains water pressure
which damaged the stop - tap as suggested in the Rose Report
(whic h I consider to be implausible), and these factors had caused
flooding to Unit 3 (again, I consider this implausible), this does not
change my conclusion as to the proximate cause of the flooding.
This is because had the two "open" water pipes wit hin the Units
been duly sealed off by AB in May 2022 as was required by the
Plumbing Regulations, then any water that would have flowed
through the stop - tap in August 2022 due to such hypot hetical
"overtightening" and/or high mains water pressure would have been
blocked from entering into Unit 3, thus preventing any flooding of
Unit 3.
Amended Determination | Case number: 920319 Page 17 of 18
Record Key points
GM Supplementary Report
03 - 04 - 23
At the top of page 2 of the Rose Report, there is a photograph of the
dismantled stop - tap (the " Rose Report Photo") with the not ation
"The rubber section of the washer was completely missing".
Whilst the Rose Report does not state it, I am instructed that Mr.
John Riske of AB says that the washer within this stop - tap must
have been perished and "washed away" up the water pipe on or
around 10 August 2022, thus allowing the mains wat er to flow past
the stop - tap.
There is no was her visible in the Rose Report Photo. The washer
within this stop - tap would have been positioned between the nut
visible at the t op of the stop - tap in the Ros e Report Photo, and the
circular brass seat immediately underneath it.
In my first report, I concluded that, for various reasons, the evidence
points to the stop - tap in this case being in good working order at all
material times and that it had no role in the ca use of the flooding
incident. It therefore follows that there would have been a washer
present within the stop - tap at all material times, including during the
time the mains water passed through the stop - tap to then d ischarge
from the "open" water pipes within Units 3 and 6, causing flooding.
In addition, even if hypothetically there had been "overtightening" of
the stop - tap and/ or high mains water pressure which damaged the
stop - tap as suggested in the Rose Report (w hich I consider
implausible for reaso ns set out in my first report), or even if the
washer was very old, I consider it implausible that the washer would
have "was hed away" up the wat er pipe and gone "missing". This is
because wash ers are made of tough mate rials and are lodged tightly
between two precision - machined brass seats within the enveloping
brass body of the stop - tap assembly.
VBA Advice
24 - 05 - 23
“What you have described sounds like an element or part of a
building or structure that carries or tr ansfers a load between
intermediate floors in addition to its own weight.
Pri or to any building work being undertaken I can confirm that any
proposed modifications, alterations and any repairs to [this] would
require an application for a building permit t o be submitted to a
registered building surveyor. The building surveyor will then assess
the compliance requirements and guide you through the process…”.
VBA Advice
19 - 05 - 2023
“Based on your description I would recommend contacting a
registered endorsed structural engineer to undert ake a site
Amended Determination | Case number: 920319 Page 18 of 18
Record Key points
inspection to check whether the concrete floor between your unit
and the one above requires remedial work due to the water
ingress…
I can confirm that before any remedial works are undertaken, if the
work r elates to a structural alternation or repair for instance, this type
of work would require a building permit to be issued by a registered
building surveyor prior to any building work”.
FES Engineering Report
27 - 09 - 21
FES understands renovations were carr ied out to the unit 6
bathroom in July 2020.
During these works, a section of concrete fell f om the underside of
the second floor slab into unit 3 bathroom, with a void / hole being
formed in the suspended slab. This loss of concrete occurred in the
vici nity where the new PVC pipe was connected into the retained
original discharge pipe which is located within the external (eastern)
wall.
It appears that the contractor for this work did not engage a
structural engineer, prior to the works being carried out. It is
unknown if a Building Permit was obtained for the works. FES has
not been provided with any evidenc e showing that a structural
engineer specified, or inspected the works carried out to the
reinforcement during the unit 6 bat hroom refurbishment w orks.
It is recommended, however, that AAA Above Group be requested
to provide evidence in relation to a building permit, including building
surveying related documents.