1 Determination overview
1.1 Complaint
The complainant holds a home building and contents policy underwritten by the financial firm
(insurer) covering her home address.
In February 2022, the property was damaged by a flood. A claim was lodged under the policy
for the damage sustained. The insurer accepted the claim. However, a dispute has arisen as
to the method of settlement and the way in which the insurer handled the claim.
1.2 Issues and key findings
Is the insurer entitled to cash settle the complainant?
No. The available information shows the insurer has not acted reasonably in seeking to cash
settle the claim. Therefore, the claim should proceed in the manner set out in section 2.1.
Is the insurer required to cover other losses?
No. The complainant has not substantiated her losses.
Is the complainant entitled to further compensation?
The insurer acknowledges its claims handling has been poor. The insurer should pay
compensation for non-financial loss in the sum of $3,000. The complainant is not entitled to
the other losses sought.
1.3 Determination
This determination is partially in favour of the complainant.
If the complainant accepts this determination, the insurer must:
proceed with the claim in the manner set out in section 2.1
pay the complainant $3,000 compensation for non-financial loss within 14 days of
receiving notice the complainant accepts this determination.
Determination | Case number: 919489 Page 2 of 9
2 Reasons for determination
2.1 Is the insurer entitled to cash settle the complainant?
Insurer wants to cash settle at least part of the repairs
There is no dispute the complainant ’s claim is covered by the policy. The insurer has offered
to either:
cash settl e the claim based on D’s scope of works in its entirety; or
cash settle part of the claim and authorise D to repair the remaining damage.
This is because the insurer says D cannot warrant the repairs due to the non-compliant
ceiling height in the bathroom/laundry.
The complainant says she would prefer the insurer to undertake all the necessary works.
Policy sets out how insurer may settle a claim
The PDS sets out how the insurer will settle a claim. The relevant provisions say:
How we settle building claims
We will aim to use a member of our supplier network to repair or rebuild the
damage to the building. Sometimes, this is not always possible e.g. if there is pre-
existing damage. This will determine how the building claim will be settled.
…
When a me mber of our supplier network is unable to complete the repair or
rebuild and you have a building sum insured
When your claim for loss or damage to the building is covered and a member of
our supplier network is unable to complete the repair or rebuild, we will ask you to
engage a builder to provide a scope of works and provide a quote on the cost to
repair or rebuild the building on a ‘new for old’ basis.
Once the scope of works and quote is provided to us, we will arrange for it to be
assessed. This will involve reviewing the quote to determine it is appropriate and
reasonable for the scope of works. This includes a consideration of the
appropriateness of materials, repair method, labour and material costs and overall
cost effectiveness.
If the quote is appropriate and reasonable for the scope of works, we will then pay
you the assessed amount. If it is not, the quote may be adjusted. This may
include, adjusting the scope of works or the quote. We will then pay you the
adjusted amount of the quote. If we pay you for the repair or rebuild, the Lifetime
guarantee on building repairs does not apply, see page 84.”
Determination | Case number: 919489 Page 3 of 9
As evident, the policy says the insurer will repair the damage with a member from its supplier
network unless the member is unable to do so. In this case, the insurer says D cannot repair
the damage due to the ceiling height in the bathroom/laundry.
Unclear why insurer cannot warrant works
There is no dispute the ceiling height is non-compliant with current standards. I note there is
no information to show it was non-compliant at the time of construction. The insurer says this
point is irrelevant.
It is not clear why D cannot warrant the repairs to the bathroom/laundry. It is possible D
cannot warrant the repairs without raising the ceiling height to current standards. If that is the
case, then this should be included in the cost of repairs.
In that regard, the insurer says the following exclusion would apply:
We don’t cover … The cost of: … upgrading undamaged parts, sections or
components, of the building to comply with current building regulations and laws.
I disagree. Under this section of the policy, it does cover the cost to:
to make the damaged building components comply with current home building
regulations and laws. We only pay these costs if the building components
complied with home building regulations and laws when they were built or when
construction, repairs, renovations or alterations were undertaken
The insurer’s scope of works includes extensive works to the bathroom. This includes
stripping the tiles, wall linings, fixtures and fittings. It also includes works to the ceiling.
This indicates the ceiling itself is part of the damage to be repaired. Therefore, if it is required
to be lifted, then it would fall within the ‘damaged building components’ that needs to comply
with current home building regulations and laws. Further, it would not fall within the exclusions
for ‘upgrading undamaged parts, sections or components’ given the ceiling is accepted
damage.
Therefore, there are several concerns with the insurer’s position:
the scope of works may be incomplete if the ceiling needs to be lifted, and
the insurer has not justified why it cannot complete the repairs.
Other concerns with insurer’s position
The complainant says she is not qualified to project manage and has no experience in
understanding the technicalities of rebuilding her home. Even if she were to consider the cash
settlement, she expressed concerns about the toll it (coordinating repairs) may have on her
mental health.
She also raised concerns with the insurer’s cash settlement. For instance, she submitted a
scope of works from an independent builder, J, for $70,798.20. In its report, J advised:
The costs provided are intended to capture the damage that has been caused by
the floods only, and where pre-existing structural issues or pre-existing related
maintenance issues are identified, these have not been allowed for in the cost
estimate.
Determination | Case number: 919489 Page 4 of 9
The insurer’s internal assessor reviewed this in November 2022 and said it was
unreasonable. Part of the reasons cited was because the assessor said J’s rates were too
high compared to the insurer’s suppliers.
However, as the insurer was considering cash settling the claim, the insurer should have
considered whether the more competitive rates referred to by the assessor were available to
the complainant. It is not clear from the asses sor’s report this is the case. It is therefore
unclear if the assessor’s rates are actionable.
Further, D’s report dated April 2022 said:
No allowance has been made for remediation sanitisation under the expectation
that this has been completed as a make safe by others. Should this be required
by [D], a variation will be submitted to cover the additional costs incurred.
NOTE:
Please be advised that [D] Constructions will not be responsible for any
unforeseen building damage to the property. Any additional damage discovered to
new or old areas will result in a variation to the quote.
Please be advised of the following possible variations below:
- Any unforeseen damage discovered once repairs commence.
- Any Plumbing, Electrical or Building damage that is discovered during repairs
that falls outside the scope of works.
- Additional costs required for Remediation Work/Cleaning outside the scope of
works.
- Any additional work required by the restorers that falls outside the scope of
works.
- Any additional areas of damage that the insured did not make [D] aware of at
time of inspection.
This indicates D’s scope of works may be incomplete in several regards. Whilst a contingency
has been included, it is unclear if it sufficiently accounts for all this.
Insurer must complete the repairs
Considering the above, I do not accept it is either fair or reasonable the insurer should cash
settle the claim. This is particularly due to the following factors:
the complainant’s vulnerability
the insurer has not substantiated why its repairers cannot warrant the works
the insurer’s scope of works has numerous uncertainties
it not clear the rates and costs the insurer is relying upon are available to the complainant.
In the circumstances, including the duty of utmost good faith each party owes to the other, I
am satisfied it is fair in all the circumstances the insurer arranges the repairs.
However, before it does so, a process should be undertaken to ensure the scope of works is
fair and reasonable given the concerns identified above. Therefore, the claim should be
processed in this way.
Determination | Case number: 919489 Page 5 of 9
Claim for building repairs to proceed in this way
The parties are to engage an independent building consultant or structural engineer (expert)
to inspect the property and provide a full scope of works to repair the claim related damage.
The scope of works should at least include the works the insurer has agreed to. The expert
should also consider whether:
any aspect of J’s scope of works which the insurer has not agreed to should be included,
and
if any compliance works are necessary in order to repair the claim related damage (e.g. if
the ceiling height needs to be raised).
The expert should be one agreed to by the parties. This is to be done by the insurer providing
a list of three experts that the complainant can choose one from. The expert should be
appropriately licenced and qualified to do this. The expert should be one who has not been
involved in the claim before.
The insurer must provide this list within 14 days of receiving notice the complainant accepts
this determination.
The expert’s costs are to be borne by the insurer. The expert should be engaged within 14
days of being chosen.
Within 21 days of receipt of the SOW, the insurer is to obtain at an actionable quotation
based upon the SOW.
Within 7 days of receipt of the SOW and associated quotation, the insurer must engage a
contractor to commence the necessary repairs and associated works. If, however, the parties
agree for the matter to be cash settled, the insurer can do so based on the actionable
quotation with a 20% contingency. This contingency is to factor in the risk of the works
passing to the complainant and the likely possibility that further works may be required
2.2 Is the insurer required to cover other losses?
Out of pocket expenses
The complainant provided several invoices in relation to out of pocket expenses she says she
incurred in organising her own flood clean up and make safe effort.
The insurer has assessed these invoices and accepted part of them. However, the insurer
sought further information for the remaining.
This determination will comment only for those invoices that remain in dispute. For those
already accepted, the insurer should arrange payment if it has not already done so.
JSF Designs
The complainant explained she had undertaken significant flood clean up due to the insurer’s
inaction.
The complainant provided six invoices. The insurer accepted three. However, it sought further
information on the remaining three.
Tax Invoice Description Date Amount Status
#1366 JSF Designs 5 March 2022 $170 accepted
September
Determination | Case number: 919489 Page 6 of 9
2023
#1387 JSF Designs 31 May 2022 $2,122 accepted
September
2023
#1392 JSF Designs 8 June 2022 $275 accepted
September
2023
#1409 JSF Designs 5 August 2022 $1,510 outstanding
#1423 JSF Designs 6 October 2022 $2,205.75 outstanding
#1427 JSF Designs 19 October
2022
$1,484 outstanding
The remaining three are fairly substantive price-wise. They were also issued numerous
months after the flood event and after the insurer did some works too. The screenshots
provided by the complainant give little information as to what works were done and how they
are related to the flood event. For instance:
Invoice #1409 says ‘sorry the bill is a whopper. there’s a few …’ before it is cut -off
Invoice $1423 says ‘Hi [K], please find attached invoice for the following invoice sorry it’s a
whopper …’ before it is cut off
Invoice #1427 says ‘Hey [K], sorry for another whopper of a bill. least this will be the last
one for a while!’
Given all this, I am not persuaded these costs were incurred as part of the clean-up.
Therefore, these are not payable.
XL Security & Blinds
The complainant provided a payment confirmation receipt for the sum of $6,325 for costs
associated with the blinds replacement. The insurer is unable to reconcile this amount citing
more information is required.
The complainant has not provided an invoice or quotation in support of this payment made.
I agree with the insurer there is insufficient information to pay for this. The insurer is not liable
for this.
Other issues
The complainant raised these additional issues during the course of the complaint.
Wood rot and pest infestation
In August 2023, the complainant reported wood rot and pest infestation. The complainant
advised she discovered this after she returned to her property for a brief period. It is not clear
why this was not discovered earlier given the numerous visits to the property previously.
The insurer relied on the photographs provided. The insurer said this did not occur from a
single flood event but rather several months or years. This is plausible. Rot is unlikely to be
associated with a single event.
Determination | Case number: 919489 Page 7 of 9
Based on this limited information, I am not persuaded this is claim related.
Removal of debris
In May 2023, the complainant advised there was still a large amount of debris yet to be
removed from her property. This included a pile of rotten wooden boards and picnic table.
The complainant provided photographs confirming this.
The insurer advised the policy only extends to the removal of debris that are damaged parts
of the building. The insurer’s assessor also said it issued $1,050 to the customer already for
removal of debris.
It is not clear why this was not removed from the clean- up done by the complainant’s
contractor and the insurer. It is also not clear why this was raised so late. The complainant
has not commented on the insurer’s assessor comment that a payment was already made.
Based on the limited information, I am not persuaded there is sufficient basis to include an
additional allowance for this.
2.3 Is the complainant entitled to further compensation?
It is fair the insurer pays non-financial loss compensation
AFCA will only award compensation for non-financial loss where there has been an unusual
amount of physical inconvenience, time taken to resolve a situation and/or interference with
the complainant’s reasonable expectations or peace of mind.
The complainant says the insurer failed to offer her assistance leading her to organise repairs
herself. Further, she says the insurer unreasonably delayed its assessment of the claim.
The insurer acknowledges its handling of the matter should have been better. It offered
$2,000 compensation for non-financial loss.
Having considered the circumstances and all the available evidence, I am persuaded the
insurer’s handling of the claim was less than ideal. I am satisfied the complainant underwent
considerable inconvenience and personal difficulty because of the flood damage. This could
have been prevented if the insurer had acted promptly in the given circumstances.
It is also worth noting the complainant’s vulnerability, which might reasonably have prompted
a more proactive and prioritised response by the insurer. In addition, I note the complainant
was compelled by the circumstances of the claim to arrange her own make safe and
assessment, which understandably heightened her stress.
The complainant seeks the maximum amount of $5,400. However, considering AFCA’s
conservative approach to such matters, the insurer must pay the complainant $3,000 in
compensation for non-financial loss due to the way it handled the claim.
The complainant is not entitled to other losses
In her submission, the complainant has sought reimbursement of these other losses:
Bunnings receipts
Petrol costs
Lost wages
Bunnings
Determination | Case number: 919489 Page 8 of 9
The complainant explained these costs were in relation to the flood clean-up and repair
supplies between 2 March to 9 December 2022.
The insurer sought further information, such as a breakdown of the amounts paid. The insurer
maintained that it is prepared to consider these costs under the claim if substantiated.
On review of the available information, I am satisfied that there is insufficient information to
compel the insurer in accepting these costs. The complainant has only provided amounts
paid to Bunnings with no detail of what was purchased.
Therefore, I consider the insurer’s position is fair. The insurer is not liable for these receipts
unless the complainant can provide the further information requested.
Fuel
The complainant explained she travelled from Port Macquarie to Tumbulgum to organise
things herself (e.g. trades). She has provided a handwritten record of all her trips and the cost
of fuel. She has substantiated the fuel cost through bank statements but not fuel receipts.
It is difficult to reconcile if all these fuel costs were incurred solely to do with the claim. For
instance, handwritten notes are not, of themselves, sufficient evidence that the fuel she
expended was solely to do with the claim.
It is also important to note the policy does not cover these costs. They would only potentially
be covered if it was a loss associated with the insurer’s unreas onable handling of the claim.
The limited information does not substantiate to what extent these costs are associated with
the claimed event compared to the insurer’s unreasonable handling of the claim .
Given all this, I am not satisfied there is sufficient basis to award any compensation for fuel.
Lost income, including future income
Such losses it not covered by the policy. They can only potentially be claimed if the
complainant can show:
the insurer breached the policy (e.g. its unreasonable handling of the claim)
these losses were caused by that breach (rather than the claimed event)
the losses were foreseeable when the contract was entered into
The complainant’s submission about the amount of income she lost is not supported by
employment or financial records. It is not supported by any other objective information, such
as medical reports or other information to confirm these losses were due to the insurer’s
unreasonable handling of the claim. Further, there is no way of differentiating any potential
lost income associated with the claimed event compared to the insurer’s unreasonable
handling of the claim.
Given all this, there is insufficient basis to make any award.
Determination | Case number: 919489 Page 9 of 9
3 Supporting Information
3.1 The AFCA process
AFCA’s approach is based on fairnes s
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.