Flood claim: foundation damage excluded, cash settlement amount, temporary accommodation and delay
Text of the determination
Determination
Case number 919144
Financial firm AAI Limited
Determination | Case number: 919144 Page 1 of 10
Case number: 919144 7 December 2023
1 Determination overview
1.1 Complaint
The complainants hold a home and contents policy with the financial firm (insurer). On 6
January 2022, they lodged a claim for flood damage to their home and contents.
The insurer partially accepted the claim. It says the foundation damage is not related to a
one-off storm event and is therefore excluded. Further, it says it cannot warrant the repairs
due to the pre-existing foundation damage and has sought to cash settle the claim.
The complainants say the insurer should cover the foundation damage as it was caused by
the flood event. The complainants seek that the insurer cover the costs of repairing the
foundation damage, complete all repairs to their home and pay compensation for the stress
and inconvenience suffered because of the insurer’s handling of the claim.
1.2 Issues and key findings
Is the insurer required to cover the foundation damage?
No. The insurer has established that the specific exclusion in the storm and flood events
cover applies. Therefore, it is not required to cover the foundation damage.
Is the insurer required to increase its cash settlement?
Yes. The cash settlement offer should be calculated based on an updated actionable quote, a
20% uplift for contingencies and an allowance for temporary accommodation (based on JL’s
estimate) for the time required to complete the repairs. The insurer is also required to pay the
temporary accommodation costs until the cash settlement is paid and legal fees up to $5,000.
Are the complainants entitled to compensation?
Yes. The complainants are entitled to $3,500 in non-financial loss compensation for the
stress and inconvenience caused by the insurer’s delay in remediating, assessing and cash
settling the claim. The panel does not consider the complainants are entitled to compensation
for indirect financial loss.
Why is the outcome fair?
The panel considers the outcome is consistent with the policy terms, law and the available
information. Therefore, the panel considers the outcome is fair in all the circumstances.
1.3 Determination
This determination is in favour of the complainant.
Within 14 days of being notified of the complainants’ acceptance of the determination, the
insurer is required to request an updated actionable quote from JL and pay $3,500 in non-
financial loss compensation. It must then cash settle the claim within 14 days of receiving the
updated quote from JL in accordance with section 2.2 of this determination.
Determination | Case number: 919144 Page 2 of 10
2 Reasons for determination
2.1 Is the insurer required to cover the foundation damage?
No. The insurer has established that the specific exclusion in the storm and flood events
cover applies. Therefore, it is not required to cover the foundation damage.
Onus on the complainants to establish a claimable loss
The complainants are required to show, on the balance of probabilities (that it is more likely
than not), that there is a claimable loss under the policy. This means the complainants must
prove the loss or damage was caused by a risk that is covered under the policy.
Once the complainants prove there is a claimable loss, the insurer is liable for the loss unless
it shows an exclusion or limiting condition applies. The insurer has the onus of proving, on the
balance of probabilities, that the exclusion or condition applies.
Policy covers insured events subject to exclusions
The insurer’s policy consists of the policy schedule and product disclosure statement (PDS).
It is not in dispute the insurer provided the policy documents to the complainant.
The policy is an ‘insured events’ policy. This means not all loss and damage is automatically
covered. Rather, only loss or damage caused by an insured event, and not subject to an
exclusion, is covered. The policy defines an insured event as a ‘single event, accident or
occurrence which you did not intend or expect to happen’ . A series of incidents attributable to
one source of originating cause is deemed to be the one incident.
The insured events are set out in the PDS and include storm and flood. However, the PDS
also says that cover for storm and flood do not include:
…loss or damage caused by erosion, vibration, subsidence, landslip, landslide,
mudslide, collapse, shrinkage or any other earth movement, but we will cover loss
or damage caused by a landslide or subsidence proved to have occurred within
72 hours of, and directly because of, [the storm or flood] and not because of
erosion, structural fault or design fault;
Under the general exclusions, the policy excludes loss or damage to, or caused by,
connected with or arising from:
Ground movement
erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage
or any other earth movement, but we will cover landslide or subsidence that is
specifically covered under the following insured events:
− ‘Storm’ page 42;
− ‘Storm surge’ page 43;
− ‘Escape of Liquid’ page 45;
− ‘Flood’ page 41;
− ‘Earthquake and Tsunami’ page 44;
− ‘Explosion’ page 48 …
Determination | Case number: 919144 Page 3 of 10
Parties disagree on cause of foundation damage
The insurer appointed a restorer, RS, to assess and remediate the property. RS says
remediation works included removing all vinyl, carpet and chipboard and plyboard flooring,
door trims and jambs and all wall linings to 1200mm. All timber framing and flooring was
abrasively cleaned and treated, and dehumidifiers and air movers were installed to assist with
drying.
There appear to have been delays in the remediation works. That is, RS did not complete the
works, including the strip out, until September 2022. This could have further contributed to the
damage. Nevertheless, it appears that the foundation damage is relatively minor. That is,
there is no significant damage, such as rotation of footings or significant movement of floor
levels outside acceptable ranges, bearing in mind the reactivity of the soil.
The insurer also obtained a report from a civil engineer, VC, dated 13 May 2022. Based on
this, the insurer says the foundation issues were not a result of landslide or subsidence
caused by a single storm event. It says the complainants have not provided any floor level
survey results to suggest the damage was localised or that the damage was not pre-existing
prior to the flood event.
The complainants engaged a structural engineer, EF, who provided a report dated 14 March
2023. They say they have established a claimable loss and the insurer has not established
that any exclusions apply. Therefore, the insurer should cover the foundation damage
component of the claim.
The complainants also say VC ’s assessment is flawed because it is based on the following
assumptions for which there is no reasonable basis. Therefore, the statements below are
mere assertions and not supported by evidence:
it assumes the floodwater inundation would have been for relatively short duration before
draining away;
it assumes due to the land’s topography that the sub-floor would be subject to regular
rain/runoff. However, there is no evidence of this;
it has not conducted any research or made any findings regarding the amount of water that
flooded the property; and
a soil report was not obtained.
Summaries of the reports from VC and EF are set out in section 3.2 of this determination.
On balance, complainants have established a claimable loss
The available evidence confirms that the property was inundated with flood water to
approximately 400mm above the internal floor level causing damage. The weather event was
significant and widely reported as a catastrophic event. Therefore, it is not in dispute that a
flood event did occur and that there was damage to the property. Accordingly, the panel is
satisfied the complainants have established a claimable loss.
However, the question to be considered is the extent of the flood related damage. The insurer
says the foundation damage has not been caused by a one-off storm event. Instead, it says
the earth movement damage has been occurring over a period of time and is therefore
excluded. The complainants disagree. They say that after the debris was cleaned up and the
carpet removed, they noticed movement in the master bedroom and that the skirting board
corners in the hallway have opened. They also rely on their expert evidence which shows the
timber joists and stumps have signs moisture ingress.
Determination | Case number: 919144 Page 4 of 10
On balance, foundation damage is excluded under the policy
The onus is on the insurer to establish that the foundation movement is excluded under the
policy.
The insurer refers to the report from VC. It relies on differential settlement of stumps since
restumping, poor site drainage and previous cosmetic repairs as its basis to conclude that the
foundation movement is ongoing. It acknowledges that the storm event may have
exacerbated the movement but says it was not the proximate cause.
Conversely, EF inspected the subfloor and says:
… there is separation in the timber floor and signs of deteriorating timber below
the studs in the living room and bedrooms with rotten timber floors in some areas.
There are signs of moisture ingress to the timber joists in the subfloor. There are
also water marks in the concrete stumps closer to the timber bearers’. Further, EF
says the ‘ storm event is the dominant cause that has created the possibility of
saturation and slumping in the reactive clay soils … which has contributed to the
movement and deterioration of the building elements.
The storm and flood insured event covers specifically exclude ‘loss or damage caused
by…earth movement [unl ess the] loss or damage [has been] caused by a landslide or
subsidence proved to have occurred within 72 hours of, and directly because of [the storm or
flood]’.
There is no evidence whatsoever from any of the experts that the foundation damage has
been caused by landslide or subsidence. Rather, the experts appear to agree that any
foundation movement was due to heave. Therefore, even if the proximate cause of the earth
movement is flood or storm, there is no cover for the foundation damage. This is because the
specific exclusion in the storm and flood events cover for earth movement will apply and there
is no evidence of a landslide or subsidence. Given this, it is not necessary to consider
whether the earth movement occurred within 72 hours of the storms/flood.
The above is the only plausible interpretation of the specific exclusion. Any alternate
interpretation would mean that the specific exclusion was of no effect. This type of wording
must also be distinguished from the general exclusions in the policy.
In the circumstances, the insurer has established the specific exclusion for earth movement in
the storm and flood event covers applies. Therefore, the insurer is entitled to decline cover for
the foundation damage.
2.2 Is the insurer required to increase its cash settlement?
Yes. The cash settlement offer should be calculated based on an updated actionable quote, a
20% uplift for contingencies and an allowance for temporary accommodation (based on JL’s
estimate) for the time required to complete the repairs. The insurer is also required to pay the
temporary accommodation costs until the cash settlement is paid and legal fees up to $5,000.
Insufficient information to show the claim is a total loss
The complainants building is insured for $339,900. The insurer has to date paid $15,180 for
the fence repairs and $22,377.85 to RS for remediation costs.
Determination | Case number: 919144 Page 5 of 10
The insurer also obtained a quote from JL for the accepted repairs to the property. JL’s quote
dated 6 October 2022 totalled $121,645.98 . This included a 15% builder’s margin. The
insurer offered to settle the complainants based on this quote plus a 15% uplift for
contingencies as it was unable to warrant repairs. Accordingly, the cash settlement offered for
the agreed repairs is $139,892,87.
The insurer says the total cost of repairs under the claim is $159,203.83 ($15,180 plus
$22,377.85 plus $121,645.98). Even if the 15% uplift is added to this, the total settlement is
well below the sum insured.
Given the above, and the fact that there is no cover for the foundation damage, the panel
does not consider the claim is a total loss.
Insurer can cash settle but must obtain an updated actionable quote
The policy allows the insurer to decide the way in which the claim is settled. In circumstances
where the insurer has stated it is unable to warrant the repairs, it is entitled to cash settle the
claim.
The JL quote is over 12 months old. In the circumstances, the insurer is required to obtain an
updated actionable quote from JL. The quote should also include an estimate of the time
required to complete the repair works. The quote should be actionable in the sense it should
be based on market rates available to the complainants.
Once an updated actionable quote is obtained from JL, the insurer must cash settle the
complainant with a 20% uplift for contingencies and the loss of a lifetime guarantee on
repairs. It is appropriate to increase the 15% uplift offered by the insurer to take into account
the higher chance of variances on a repair of this scale.
Insurer must pay further temporary accommodation costs
The insurer confirmed that it settled the complainants $33,990 for the temporary
accommodation costs. Given this, it says it would not be liable to cover any further
accommodation costs.
The complainants’ policy entitles them to temporary accommodation up to 10% of the sum
insured, or $33,990. The panel accepts this sum has been paid. However, the panel does not
consider this is a sufficient allowance for temporary accommodation in the circumstances.
The panel acknowledges there were several delays, particularly around the remediation
process, strip out and further assessment of the property. This greatly impacted the time
taken to respond to the claim. This meant the complainants remained in temporary
accommodation while waiting for the insurer to finalise the claim decision.
The insurer’s notes show that it had approved remediation in January 2022. However, the
strip out only commenced in June 2022 and the remediation works were not completed until
September 2022. The insurer’s IDR decision is also dated 10 August 2022, before the final
report from RS was received (which confirmed all remediation works had been completed).
Arguably, it was only after such time that a proper assessment of the claim should have been
conducted and a decision issued.
In the circumstances, the panel considers the insurer is liable to pay the complainants
temporary accommodation costs from the date the claim was lodged until time the cash
settlement is paid. The insurer should also include in its cash settlement, an allowance for
Determination | Case number: 919144 Page 6 of 10
temporary accommodation at a rate of $500 per week for the duration of the estimate
provided by JL.
Insurer not req uired to pay complainants’ professional costs
Under Rule D.5, AFCA may decide a financial firm contribute to the professional costs
incurred by a complainant in the course of a complaint. These costs can be awarded if the
complainant needed an expert to understand or establish their claim. These costs are
normally capped at $5,000 unless exceptional circumstances apply.
The complainants seek reimbursement for professional costs, specifically towards their legal
costs of $5,000. The panel is satisfied the matter was sufficiently complex that the
complainants needed help with managing the claim. This is particularly so in circumstances
where they are suffering adverse mental health issues because of the stress caused by the
claim. The panel considers it fair that the insurer pay the complainants up to $5,000 for their
legal costs subject to a copy of the invoice(s) and proof of payment being provided.
The report obtained from EF has not assisted the complainants to establish their claim.
Therefore, the panel is not satisfied that the insurer should have to reimburse the
complainants the cost of this report.
2.3 Are the complainants entitled to compensation?
Yes. The complainants are entitled to $3,500 in non-financial loss compensation for the
stress and inconvenience caused by the insurer’s delay in remediating, assessing and cash
settling the claim. The panel does not consider the complainants are entitled to compensation
for indirect financial loss.
Compensation is awarded conservatively
Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial
loss where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or peace of mind.
We take a conservative approach to compensation for non-financial loss. It is not awarded
when a person suffers the normal degree of inconvenience when a problem occurs.
Under paragraph D.2 of the AFCA Rules, we may also award compensation for indirect
financial loss (capped at $5,400).
Indirect loss may include the loss of use of a damaged item, the cost of renting a replacement
item or loss of income. However, the indirect loss claimed must be caused by the insurer’s
error or incorrect handling of the claim.
Complainants have suffered unreasonable stress and inconvenience
The insurer accepts the claim took longer to progress than expected. It has offered $1,000 in
non-financial loss compensation in recognition of this.
The complainants seek the maximum non- financial loss because of the insurer’s handling of
the claim. This is because one of the complainants was unable to continue working and
ceased her employment and both complainants have required counselling and medical
treatment. Furthermore, the complainants remain in temporary accommodation. Therefore,
Determination | Case number: 919144 Page 7 of 10
they are required to pay both their mortgage repayment and rent. This has had a further
negative impact on their mental health and financial circumstances.
The insurer says the claim involved large amount of damage. As a result, it required many
different suppliers and repairers to inspect and provide reports in relation to the cause of the
damage, confirm the remediation required and provide a scope of repair. The panel
acknowledges this. However, it considers the insurer’s handling was less than ideal,
particularly the length of time it took to remediate the property and the direct impact this has
had on the foundation.
Having considered the insurer’s notes, the panel is not persuaded that the available
information supports the insurer’s explanation. While it is not in dispute that the claim was
complex in nature, its correspondence was mainly with its panel builder, JL, and VC, its
engineer. There are no details of the supposed many different suppliers and/or repairers it
required.
The panel is satisfied that the complainants suffered an unusual degree of stress,
inconvenience and delay because the insurer ’s handling of the claim. The panel also notes
that the insurer did not pay the cash settlement to the complainants and, therefore, they could
not commence the repairs. It also notes the complainants will have been out of their home for
over two years by the time the repairs are completed. Given this, the insurer should pay the
complainants $3,500 in non-financial loss compensation.
Insurer not required to pay indirect financial loss
The complainants seek compensation for indirect financial loss. This is because they have
been unable to live in their house and continue to incur costs associated with alternative living
arrangements.
As discussed above, the insurer is to pay further temporary accommodation due to the delays
it has caused. The panel has also awarded the complainants compensation for the stress and
inconvenience caused. In the circumstances, the panel does not consider the complainants
are entitled to any compensation for indirect financial loss.
2.4 Why is the outcome fair?
The panel considers the outcome is consistent with the policy terms, law and the available
information. Therefore, the panel considers the outcome is fair in all the circumstances.
Determination | Case number: 919144 Page 8 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Engineering reports
VC says ‘subfloor observations was limited due to the access’. However, it considers the
foundation damage is an ongoing issue. The flood event may have exacerbated the damage,
however not to the extent of it being the dominant cause. VC says:
the foundation damage has likely occurred due to:
> differential settlement of stumps since restumping due to seasonal soil moisture
variations of moderately reactive founding soils;
Determination | Case number: 919144 Page 9 of 10
> poor external drainage which encourages runoff to flow towards and through the
subfloor;
> a likely history of excessive runoff/flood events inundating the subfloor stumps;
the land slopes naturally west to east and the subfloor had a mixture of dry and wet areas.
This indicates some areas of the subfloor were subject to surface runoff on an ongoing
basis and that the drainage around the property was poorly maintained. This is contributing
to the differential movement;
the foundation soil in the area is moderately reactive and seasonal changes in the
moisture contents of soil of this type can cause 20-40mm movement at the surface;
it acknowledges that no soil report has been obtained.;
the site level survey recorded a maximum difference of 30mm in the floor level across the
building. This was widespread and there was no pattern of localised movement;
when a leak occurs in a reactive soil, localised expansion occurs. Therefore, it is not
unreasonable to expect a certain level of heave in that location. The swelling of soil
creates an upward force on the footings of the building and, if the moistures level is
excessive, the bearing strength weakens causing the footings to settle. This is generally
limited to a localised influence zone depending on the amount of water released, the site
topography and the drying conditions;
it anticipates the flood water inundation would have been for a relatively short duration,
before draining away (given the apparent gradual slope across the site). Due to the slope,
it considers the sub-floor would have been subject to regular rainfall runoff;
in its opinion, the movement observed is more likely a result of the ongoing foundation
issues rather than a one-off flood event. It also observed previously patched cracks to the
interior of the dwelling which are typically caused by foundation movement/differential
settlement. This also indicates the foundation movement has been an ongoing issue; and
the external floors of the subfloor were higher than the subfloor in some areas. This may
serve to both encourage moisture into the subfloor and prevent moisture from leaving the
subfloor on an ongoing basis. With a significant rainfall event, this moisture ingress and
ponding is believed to contribute to the differential movement observed.
EF’s report dated 14 March 2023 says:
there is separation in the timber floor and signs of deteriorating timber below the studs in
the living room and bedrooms with rotten timber floors in some areas. There are signs of
moisture ingress to the timber joists in the subfloor. There are also water marks in the
concrete stumps closer to the timber bearers;
foundation movement is due to the one of the following factors - bearing failure, settlement
or reactivity;
no soil testing has been conducted to determine if the soils have experienced bearing
failure resulting in footing movement. If bearing failure was a contributing factor in
foundation movement, you would expect to see bouncy or squeaky floors, distress to
bearer and joist connections, stumps out of plumb, or deflection of the floor visible to the
naked eye. None of these indicators were noted during EF’s inspection;
no soil testing has been conducted to determine the nature of the soil profile to rule out a
long-term settlement of the building. However, EF considers long-term settlement is very
rare in the case of stumped houses and is more common for concrete slabs constructed
on fill soils. EF does not consider long-term settlement is a contributing factor in this case;
as settlement and bearing failure have been ruled out as probable contributing factors to
the current movement in the floor, it leaves reactive soil movement as the likely cause;
moisture meter readings were recorded at various locations of the property as follows -
16% in the living room, 15% in the hallway, 10.8% in the laundry, 6.6% in the bathroom,
9.4% in bedroom 3, 14.8% in bedroom 2, 10.9% in the wall corner near the doorway,
Determination | Case number: 919144 Page 10 of 10
24.1% in the other wall corner of bedroom 1 and 23.1% in the subfloor timber joist below
the bathroom floor;
according to the Australasian Timber and Flooring Association and Australian Standard
2796, the allowable moisture content range for timber flooring is between 9% and 14%.
The observed moisture levels indicate that some locations have slightly higher moisture
content, and the subfloor joist is still moist. This indicates that water has likely entered the
foundation;
a floor level survey showed a differential of 36mm across the property. This is consistent
with a central heave. Externally, there is poor drainage;
from the observed floor level contour pattern, the source of soil swelling is localised and
the proximate cause is the flood event;
the claimed storm event with severe rainfall for 3 consecutive days is considered as the
dominant cause of the swelling in this area. With the severe rainfall intensity noted and the
topography of the land observed it is unlikely that rainfall runoff was possible within the
short term;
poor site drainage allowing stormwater runoff to make its way under the house and a
natural low point where the overland flow can pool and allow water to soak into the
foundation soils are the other factors that have contributed to the soil swelling and some
weaknesses to develop previously; and
the storm event, however, is the dominant cause that has created the possibility of
saturation and slumping in the reactive clay soils (developing closer to a full soil wedge)
which has contributed to the movement and deterioration of the building elements.