Determination 918443
Dispute over cash settlement amount and scope of works for flood damage, temporary accommodation and claim handling delay
Summary
The complainant's flood claim was accepted but the settlement amount and scope of works were disputed. AFCA found the insurer's assessment unreasonable and required a cash settlement of $408,363.61, professional costs, temporary accommodation to 31 July 2024 and $5,400 compensation.
The insurer failed to settle the claim in a reasonable manner and timeframe, so the BBS and NP quotes with a 10% uplift were the fair measure of the cash settlement.
Issues
- Claim amount dispute primary · upheld“The insurer should cash settle the claim in accordance with the quotes from BBS and NP; rectification works plus uplift total $408,363.61.”
- Poor claim handling secondary · upheld“insurer reneged on the original acceptance and quote; failed to assist immediately after the flood.”
- Inadequate claim investigation secondary · upheld“CR's report does not address the issue of mould at the property at all.”
- Delay secondary · upheld“insurer took an unreasonable amount of time in obtaining its own scope of works; five different scopes over approximately 13 months.”
- Poor communication secondary · upheld“cash settlement fact sheet not provided; no explanation given; some questions remain unanswered.”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay non financial loss
Related
Text of the determination
Determination
Case number 918443
Financial firm Hollard Insurance Partners Limited
Determination | Case number: 918443 Page 1 of 7
Case number: 918443 17 November 2023
Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm (insurer).
On 28 February 2022, the complainant lodged a claim for damage to her property following
the floods in February 2022.
The insurer accepted the claim on 4 April 2022, however a dispute has arisen about the
settlement sum. The complainant has obtained a scope of works from her builder and seeks a
cash settlement . The insurer says the complainant’s scope of works is unreasonable. The
insurer has offered to pay the complainant $295,656.33. It also says the scope of works it has
obtained is actionable and its builder is prepared to carry out the work and warrant repairs.
The complainant seeks approval of the scope of works she has provided to the insurer,
extension of accommodation costs and compensation for her claims experience.
1.2 Issues and key findings
Is the insurer’s assessment of the claim reasonable?
No. The insurer should cash settle the claim in accordance with the quotes from BBS and NP.
The insurer should also pay the co mplainant’s professional costs and temporary
accommodation until the repairs detailed in BBS’ quote are completed.
Is the complainant entitled to compensation?
Yes. The complainant is entitled to non-financial loss compensation for the delay, stress and
i nconvenience caused by the insurer’s handling of the claim. I consider the insurer should pay
the complainant $5,400 in compensation.
Why is the outcome fair?
The insurer has failed to settle the claim in a reasonable manner and timeframe. Accordingly,
it is fair that the cash settlement be increased, the complainant reimbursed for her
professional costs and further temporary accommodation costs and that the insurer pay
compensation.
1.3 Determination
This determination is in favour of the complainant. The insurer is required to:
within 10 days of the complainant’s acceptance of the determination, cash settle the
complainant for the rectification works plus uplift, which total $408,363.61;
within 14 days of receiving copies of the tax invoices and confirmation of payment, pay the
complainant’s professional costs of BUB and NP;
pay the complainant’s temporary accommodation costs until 31 July 2024; and
pay $5,400 compensation for non-financial loss.
Determination | Case number: 918443 Page 2 of 7
Reasons for determination
2.1 Is the insurer’s assessment of the claim reasonable?
No. The insurer should cash settle the claim in accordance with the quotes from BBS and NP.
The insurer should also pay the complainant’s professional costs and temporar y
accommodation until 31 July 2024.
Policy sets out how claims are to be settled
Page 61 of the PDS covers how claims are settled. It says in relation to Building, Contents
and Portable Contents claims that if the insurer agrees to pay the claim, it will, in consultation
with the customer:
repair your damaged property where it is practicable and economical to do
so;
replace your lost or damaged property where it is not practicable and/or
economical to repair it; or
pay you the value that fairly represents your loss, in the form of cash or a
pre-paid store card*, up to the relevant sum insured stated on your current
Certificate of Insurance.
Parties disagree about the required scope of works and cost of works
The insurer engaged a builder, QAT, to provide a scope of works. QAT has provided scopes
of work dated 28 February 2022, 23 March 2022 and 30 May 2022. In June 2022, the insurer
offered to pay the complainant $195,499.63 by way of a cash settlement and based on QAT’s
quotation.
The complainant rejected the cash settlement offer and said that a number of items were
missing from QAT’s scope of works. She obtained her own scope of works from a builder, CI,
in or about July 2022. The insurer accepted the quote in August 2022 but no cash settlement
fact sheet was received.
Sometime later, the insurer sent a builder to the property to obtain a scope of works.
In October 2022, the complainant submitted a mould report from BUB to the insurer. She was
concerned that mould had compromised the structural integrity of the building. BUB says:
the environment is contaminated with actual mould growth, associated spores and fungal
fragments. Actual growth is active or dormant, visible or hidden and requires remediation;
the damage to the building is category 3. This is descried:
water is grossly contaminated and can contain pathogenic, toxigenic, or other
harmful agents and can cause significant adverse reactions to human if contacted
or consumed. Examples of category 3 water can include but are not limited to:
sewage; waste line backflows that originate from beyond any trap regardless of
visible content or colour, all forms of flooding from sea water, rising water from
rivers or streams; and other contaminated water entering or affecting the indoor
environment. Category 3 water can carry trace levels of regulated or hazardous
Determination | Case number: 918443 Page 3 of 7
materials such as pesticides or organic substances. is grossly contaminated and
contains pathogenic, toxigenic or other harmful agents. Remediation is required,
and contaminated materials need to be discarded. Consideration must be taken of
hidden or concealed (not visible) mould growth and also the contamination arising
from settled spores and fragment (not visible) that were dispersed from areas of
actual growth.
there has been a delay in remediation. The severity of the damage escalates the longer
the water sits and the building and contents stay wet. Time is of the essence; and
the building materials and concrete flooring should be dried before being replaced with
new materials.
The insurer carried out a further inspection of the property in response to BUB ’s report . QAT
also provided a further scope of works dated 8 November 2022.
The insurer obtained another scope of works from QAT for $211,193.08 dated 20 January
2023. Based on this, the insurer made an offer of $295,656.33 to the complainant. This
comprised the value of the quote, plus a 25% uplift for rising costs of materials, labour and
contingencies and a 15% uplift for the transfer of risk. This uplift totalled $84,473.23.
In March 2023, the insurer engaged an engineer, CR, to report on the structural stability of
the building. CR says:
the movement and cracking observed throughout the external wall in combination with the
measured floor level, indicates a distinct settlement type deformation in the footing system
trending from the rear-left corner to the front-right corner of the residence;
the primary cause of the footing movement is related to long-term issues and the inherent
characteristics of the construction, reactive nature of the foundation material, effects of
trees that were removed in the past and poor surface drainage;
as the top layer of clay swells and expands as it absorbs moisture, it compresses the soil
and forms a plug that makes it difficult for the moisture to penetrate to lower depths. This
means that the duration of the flooding was not sufficiently long to affect the founding soil
in any significant way. Therefore, any effect would have been very minor;
no significant building movements have resulted from the flood event occurring around 28
February 2022. In the event saturation of the foundation soils had caused movement within
the footing system, we would expect this movement to occur from swelling of the reactive
foundation soils and subsequent heave (uplift) in the footing system. This type of damage
has not occurred; and
the structural integrity of the footing has been compromised. As part of the complainant’s
maintenance, the stabilisation of the footing system of the house needs to be undertaken
by a structural engineer.
CR’s report does not address the issue of mould at the property at all.
As at March 2023, the insurer had agreed to the following payments:
$31,592.99 for restoration costs on or about 18 January 2023;
$36,000 for alternative accommodation for six months ($1,500 per week);
$1,680 for storage costs ($280 per month)
The complainant subsequently obtained an updated scope of works from CI for $405,123.62
dated 4 May 2023. QAT reviewed the quote and said it did not believe it was fair and
reasonable. Whilst QAT believe the dimensions used were comparable, a number of items
appeared to be either overquoted or significantly upgraded and did not allow for a like for like
manner in line with the insurance PDS.
Determination | Case number: 918443 Page 4 of 7
The insurer paid the complainant $295,656.33 in accordance with QAT’s most recent quote
and the uplifts on or about 12 September 2023.
On 7 June 2023, QAT advised that it was confident its pricing was accurate and that it was
willing to carry out the works. It estimated a repair duration of 4-5 months excluding any
restoration works. It says its quotation is based on the original site attendance and variations
may be required after the strip out works, restoration and specialist inspections.
The insurer is also willing to instruct QAT to reattend and provide an opinion regarding
additional damages in the garage, external cleaning and the pool pump.
On 11 October 2023, the complainant obtained an actionable quote and scope of works from
another builder, BBS. The quote totals $352,539.65 and comprises:
project budget: $260,208.19
builder’s margin: $52,041.64
levies, warranty and insurance: $8,240.76
GST: $32,049.06
The complainant notes that BBS is on the insurer’s panel and says the quote aligns with what
the insurer originally approved in August 2022. Unfortunately, trades that have come through
the property have advised that the slab is still wet. This is visible now as the floors have been
removed. It is possible that flood water was trapped under the floors. Accordingly, the
complainant has also obtained a moisture assessment report from NP. NP quoted $2,860 to
perform the initial remediation services to dry the slab. It has also provided a further quote for
$15,840 to clean, prepare and coat the slab with hydro epoxy and carry out necessary
inspections.
On balance, insurer should increase cash settlement offer
The complainant does not consider the offer from the insurer to be reasonable and believes it
does not factor ongoing inflation due to supply chain pressures and shortages. I also note that
QAT says its ‘scope of works is based on [its] original site attendance and variations may be
required after the strip out works, restoration and specialist inspections ’.
I have carefully reviewed each of the quotes and the parties’ comments in relation to each of
them. Based on the information exchanged, I consider that BB S’ offer is the most fair and
reasonable in the circumstances. I note that it is an actionable quote and is comprehensive. I
also note that it is one o f the insurer’s panel builders and was provided only last month.
Therefore, it is an accurate reflection of current costs and labour.
Further, the additional costs associated with drying and coating the slab are fair and
reasonable . Therefore, in addition to BBS’ quote, the insurer is required to pay the
complainant $18,700 ($2,860 plus $15,840).
Therefore, the insurer is required to pay the complainant $371,239.65. The insurer is also
required to pay an uplift for contingencies and the loss of a lifetime guarantee on repairs.
Given BBS’ quote is recent and actionable, I consider a 10% uplift is sufficient. Accordingly,
the insurer is required to pay the complainant $408.363.61 in total for the rectification works.
Complainant’s expert report costs should be reimbursed
The complainant obtained expert reports from NP and BUB.
Under Rule D.5, AFCA may decide a financial firm contribute to the professional costs
incurred by a complainant in the course of a complaint. These costs can be awarded if the
Determination | Case number: 918443 Page 5 of 7
complainant needed an expert to understand or establish their claim. These costs are
normally capped at $5,000 unless exceptional circumstances apply.
The reports obtained from NP and BUB have assisted the complainant to establish her claim
and the extent to which the property was impacted by the flood. Therefore, I am satisfied that
the insurer should reimburse the complainant’s professional costs subject to the complain ant
providing the insurer with these invoices and confirming payment has been made.
Insurer to continue paying temporary accommodation costs
The policy entitles the complainant for up to 52 weeks of reasonable accommodation costs
during the period of repair where the property cannot be lived in.
The insurer commenced paying temporary accommodation costs in March 2022 and has
agreed to do so until at least 6 January 2024. I am satisfied that the insurer is liable for
temporary accommodation costs beyond the limit of the policy. This is because of the
significant delays in the insurer’s settlement of the claim following the claim being accepted in
April 2022.
QAT estimated the works would take 4-5 months. BBS estimate the works will take 12 weeks
but have not indicated when the works can commence. I consider it is unlikely the works will
commence this year. Further, taking into account the significant scope of works, a
conservative approach should be adopted to the temporary accommodation period.
Therefore, I consider the insurer should be liable to pay the complainant’s temporary
accommodation costs until 31 July 2024. That is, a six month estimate from February 2024
(when most builders are likely to recommence after the end of year break).
2.2 Is the complainant entitled to compensation?
Yes. The complainant is entitled to non-financial loss compensation for the delay, stress and
inconvenience caused by the insurer’s handling of the claim. I consider the insurer should pay
the complainant $5,400 in compensation.
AFCA can award compensation for poor claim handling
Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This
must relate to poor claims handling or other actions of the insurer which causes:
an unusual degree of stress, delay, or inconvenience, and/or
interference with a person’s expectation of enjoyment and/or peace of mind.
We expect complainants to be moderately robust, and we will not award compensation for the
ordinary degree of inconvenience involved in making a claim.
Complainant is entitled to non-financial loss compensation
Compensation is warranted for a number of reasons.
I accept the complainant says the claims process has caused a high level of stress and
anxiety including concerns about not having a place to live at certain points in time. I
acknowledge the complainant’s concerns and dissatisfaction as she has had to follow up the
insurer on several occasions and that some of her questions still remain unanswered. I also
note the complainant has not been able to live in her home for over two years (by the time the
repairs are completed).
The complainant’s house has remained unoccupied and unrepaired for almost two years.
Determination | Case number: 918443 Page 6 of 7
The insurer failed to assist the complainant immediately after the flood. It initially agreed to do
so but then cancelled its restoration contractors. It is not known why this occurred. The
complainant had to remove all the contents from her home, as well as strip out the gyprock
and floors herself.
There have been difficulties in getting the insurer to agree to cover the temporary
accommodation costs and it has only done so for certain periods of time. This has caused a
lot of stress and frustration as the complainant was worried she would be homeless.
The exchanged material confirms that on 4 August 2022, the insurer sent the complainant
correspondence advising her scope of works had been approved. It said that a cash
settlement fact sheet would be provided in the coming days. This did not occur and the
insurer, instead, sent a builder to assess the property and provide a scope of works sometime
later. To date, no explanation has been provided to the complainant as to why the insurer
reneged on the original acceptance and quote. Had it not done so, the settlement would have
been achieved over a year ago.
Further, I consider the insurer took an unreasonable amount of time in obtaining its own
scope of works and agreeing a cash settlement with the complainant. It has obtained five
different scopes of work over a period of approximately 13 months. I also consider these
delays have exacerbated the water damage at the property.
The insurer has offered the complainant $5,400 in compensation. I am satisfied that this is fair
and reasonable in the circumstances.
2.3 Why is the outcome fair?
The insurer has failed to settle the claim in a reasonable manner and timeframe. Accordingly,
it is fair that the cash settlement be increased, the complainant reimbursed for her
professional costs and further temporary accommodation costs and that the insurer pay
compensation.
Determination | Case number: 918443 Page 7 of 7
Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.