Home / Hollard / Determination 918443

Determination 918443

Dispute over cash settlement amount and scope of works for flood damage, temporary accommodation and claim handling delay

FirmHollard
Decided2023-11-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$112,707
Non-financial loss$5,400
Amount claimed—
SourceAFCA PDF

Summary

The complainant's flood claim was accepted but the settlement amount and scope of works were disputed. AFCA found the insurer's assessment unreasonable and required a cash settlement of $408,363.61, professional costs, temporary accommodation to 31 July 2024 and $5,400 compensation.

The insurer failed to settle the claim in a reasonable manner and timeframe, so the BBS and NP quotes with a 10% uplift were the fair measure of the cash settlement.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial loss

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 918443 Financial firm Hollard Insurance Partners Limited Determination | Case number: 918443 Page 1 of 7 Case number: 918443 17 November 2023 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (insurer). On 28 February 2022, the complainant lodged a claim for damage to her property following the floods in February 2022. The insurer accepted the claim on 4 April 2022, however a dispute has arisen about the settlement sum. The complainant has obtained a scope of works from her builder and seeks a cash settlement . The insurer says the complainant’s scope of works is unreasonable. The insurer has offered to pay the complainant $295,656.33. It also says the scope of works it has obtained is actionable and its builder is prepared to carry out the work and warrant repairs. The complainant seeks approval of the scope of works she has provided to the insurer, extension of accommodation costs and compensation for her claims experience. 1.2 Issues and key findings Is the insurer’s assessment of the claim reasonable? No. The insurer should cash settle the claim in accordance with the quotes from BBS and NP. The insurer should also pay the co mplainant’s professional costs and temporary accommodation until the repairs detailed in BBS’ quote are completed. Is the complainant entitled to compensation? Yes. The complainant is entitled to non-financial loss compensation for the delay, stress and i nconvenience caused by the insurer’s handling of the claim. I consider the insurer should pay the complainant $5,400 in compensation. Why is the outcome fair? The insurer has failed to settle the claim in a reasonable manner and timeframe. Accordingly, it is fair that the cash settlement be increased, the complainant reimbursed for her professional costs and further temporary accommodation costs and that the insurer pay compensation. 1.3 Determination This determination is in favour of the complainant. The insurer is required to:  within 10 days of the complainant’s acceptance of the determination, cash settle the complainant for the rectification works plus uplift, which total $408,363.61;  within 14 days of receiving copies of the tax invoices and confirmation of payment, pay the complainant’s professional costs of BUB and NP;  pay the complainant’s temporary accommodation costs until 31 July 2024; and  pay $5,400 compensation for non-financial loss. Determination | Case number: 918443 Page 2 of 7 Reasons for determination 2.1 Is the insurer’s assessment of the claim reasonable? No. The insurer should cash settle the claim in accordance with the quotes from BBS and NP. The insurer should also pay the complainant’s professional costs and temporar y accommodation until 31 July 2024. Policy sets out how claims are to be settled Page 61 of the PDS covers how claims are settled. It says in relation to Building, Contents and Portable Contents claims that if the insurer agrees to pay the claim, it will, in consultation with the customer:  repair your damaged property where it is practicable and economical to do so;  replace your lost or damaged property where it is not practicable and/or economical to repair it; or  pay you the value that fairly represents your loss, in the form of cash or a pre-paid store card*, up to the relevant sum insured stated on your current Certificate of Insurance. Parties disagree about the required scope of works and cost of works The insurer engaged a builder, QAT, to provide a scope of works. QAT has provided scopes of work dated 28 February 2022, 23 March 2022 and 30 May 2022. In June 2022, the insurer offered to pay the complainant $195,499.63 by way of a cash settlement and based on QAT’s quotation. The complainant rejected the cash settlement offer and said that a number of items were missing from QAT’s scope of works. She obtained her own scope of works from a builder, CI, in or about July 2022. The insurer accepted the quote in August 2022 but no cash settlement fact sheet was received. Sometime later, the insurer sent a builder to the property to obtain a scope of works. In October 2022, the complainant submitted a mould report from BUB to the insurer. She was concerned that mould had compromised the structural integrity of the building. BUB says:  the environment is contaminated with actual mould growth, associated spores and fungal fragments. Actual growth is active or dormant, visible or hidden and requires remediation;  the damage to the building is category 3. This is descried: water is grossly contaminated and can contain pathogenic, toxigenic, or other harmful agents and can cause significant adverse reactions to human if contacted or consumed. Examples of category 3 water can include but are not limited to: sewage; waste line backflows that originate from beyond any trap regardless of visible content or colour, all forms of flooding from sea water, rising water from rivers or streams; and other contaminated water entering or affecting the indoor environment. Category 3 water can carry trace levels of regulated or hazardous Determination | Case number: 918443 Page 3 of 7 materials such as pesticides or organic substances. is grossly contaminated and contains pathogenic, toxigenic or other harmful agents. Remediation is required, and contaminated materials need to be discarded. Consideration must be taken of hidden or concealed (not visible) mould growth and also the contamination arising from settled spores and fragment (not visible) that were dispersed from areas of actual growth.  there has been a delay in remediation. The severity of the damage escalates the longer the water sits and the building and contents stay wet. Time is of the essence; and  the building materials and concrete flooring should be dried before being replaced with new materials. The insurer carried out a further inspection of the property in response to BUB ’s report . QAT also provided a further scope of works dated 8 November 2022. The insurer obtained another scope of works from QAT for $211,193.08 dated 20 January 2023. Based on this, the insurer made an offer of $295,656.33 to the complainant. This comprised the value of the quote, plus a 25% uplift for rising costs of materials, labour and contingencies and a 15% uplift for the transfer of risk. This uplift totalled $84,473.23. In March 2023, the insurer engaged an engineer, CR, to report on the structural stability of the building. CR says:  the movement and cracking observed throughout the external wall in combination with the measured floor level, indicates a distinct settlement type deformation in the footing system trending from the rear-left corner to the front-right corner of the residence;  the primary cause of the footing movement is related to long-term issues and the inherent characteristics of the construction, reactive nature of the foundation material, effects of trees that were removed in the past and poor surface drainage;  as the top layer of clay swells and expands as it absorbs moisture, it compresses the soil and forms a plug that makes it difficult for the moisture to penetrate to lower depths. This means that the duration of the flooding was not sufficiently long to affect the founding soil in any significant way. Therefore, any effect would have been very minor;  no significant building movements have resulted from the flood event occurring around 28 February 2022. In the event saturation of the foundation soils had caused movement within the footing system, we would expect this movement to occur from swelling of the reactive foundation soils and subsequent heave (uplift) in the footing system. This type of damage has not occurred; and  the structural integrity of the footing has been compromised. As part of the complainant’s maintenance, the stabilisation of the footing system of the house needs to be undertaken by a structural engineer. CR’s report does not address the issue of mould at the property at all. As at March 2023, the insurer had agreed to the following payments:  $31,592.99 for restoration costs on or about 18 January 2023;  $36,000 for alternative accommodation for six months ($1,500 per week);  $1,680 for storage costs ($280 per month) The complainant subsequently obtained an updated scope of works from CI for $405,123.62 dated 4 May 2023. QAT reviewed the quote and said it did not believe it was fair and reasonable. Whilst QAT believe the dimensions used were comparable, a number of items appeared to be either overquoted or significantly upgraded and did not allow for a like for like manner in line with the insurance PDS. Determination | Case number: 918443 Page 4 of 7 The insurer paid the complainant $295,656.33 in accordance with QAT’s most recent quote and the uplifts on or about 12 September 2023. On 7 June 2023, QAT advised that it was confident its pricing was accurate and that it was willing to carry out the works. It estimated a repair duration of 4-5 months excluding any restoration works. It says its quotation is based on the original site attendance and variations may be required after the strip out works, restoration and specialist inspections. The insurer is also willing to instruct QAT to reattend and provide an opinion regarding additional damages in the garage, external cleaning and the pool pump. On 11 October 2023, the complainant obtained an actionable quote and scope of works from another builder, BBS. The quote totals $352,539.65 and comprises:  project budget: $260,208.19  builder’s margin: $52,041.64  levies, warranty and insurance: $8,240.76  GST: $32,049.06 The complainant notes that BBS is on the insurer’s panel and says the quote aligns with what the insurer originally approved in August 2022. Unfortunately, trades that have come through the property have advised that the slab is still wet. This is visible now as the floors have been removed. It is possible that flood water was trapped under the floors. Accordingly, the complainant has also obtained a moisture assessment report from NP. NP quoted $2,860 to perform the initial remediation services to dry the slab. It has also provided a further quote for $15,840 to clean, prepare and coat the slab with hydro epoxy and carry out necessary inspections. On balance, insurer should increase cash settlement offer The complainant does not consider the offer from the insurer to be reasonable and believes it does not factor ongoing inflation due to supply chain pressures and shortages. I also note that QAT says its ‘scope of works is based on [its] original site attendance and variations may be required after the strip out works, restoration and specialist inspections ’. I have carefully reviewed each of the quotes and the parties’ comments in relation to each of them. Based on the information exchanged, I consider that BB S’ offer is the most fair and reasonable in the circumstances. I note that it is an actionable quote and is comprehensive. I also note that it is one o f the insurer’s panel builders and was provided only last month. Therefore, it is an accurate reflection of current costs and labour. Further, the additional costs associated with drying and coating the slab are fair and reasonable . Therefore, in addition to BBS’ quote, the insurer is required to pay the complainant $18,700 ($2,860 plus $15,840). Therefore, the insurer is required to pay the complainant $371,239.65. The insurer is also required to pay an uplift for contingencies and the loss of a lifetime guarantee on repairs. Given BBS’ quote is recent and actionable, I consider a 10% uplift is sufficient. Accordingly, the insurer is required to pay the complainant $408.363.61 in total for the rectification works. Complainant’s expert report costs should be reimbursed The complainant obtained expert reports from NP and BUB. Under Rule D.5, AFCA may decide a financial firm contribute to the professional costs incurred by a complainant in the course of a complaint. These costs can be awarded if the Determination | Case number: 918443 Page 5 of 7 complainant needed an expert to understand or establish their claim. These costs are normally capped at $5,000 unless exceptional circumstances apply. The reports obtained from NP and BUB have assisted the complainant to establish her claim and the extent to which the property was impacted by the flood. Therefore, I am satisfied that the insurer should reimburse the complainant’s professional costs subject to the complain ant providing the insurer with these invoices and confirming payment has been made. Insurer to continue paying temporary accommodation costs The policy entitles the complainant for up to 52 weeks of reasonable accommodation costs during the period of repair where the property cannot be lived in. The insurer commenced paying temporary accommodation costs in March 2022 and has agreed to do so until at least 6 January 2024. I am satisfied that the insurer is liable for temporary accommodation costs beyond the limit of the policy. This is because of the significant delays in the insurer’s settlement of the claim following the claim being accepted in April 2022. QAT estimated the works would take 4-5 months. BBS estimate the works will take 12 weeks but have not indicated when the works can commence. I consider it is unlikely the works will commence this year. Further, taking into account the significant scope of works, a conservative approach should be adopted to the temporary accommodation period. Therefore, I consider the insurer should be liable to pay the complainant’s temporary accommodation costs until 31 July 2024. That is, a six month estimate from February 2024 (when most builders are likely to recommence after the end of year break). 2.2 Is the complainant entitled to compensation? Yes. The complainant is entitled to non-financial loss compensation for the delay, stress and inconvenience caused by the insurer’s handling of the claim. I consider the insurer should pay the complainant $5,400 in compensation. AFCA can award compensation for poor claim handling Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which causes:  an unusual degree of stress, delay, or inconvenience, and/or  interference with a person’s expectation of enjoyment and/or peace of mind. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. Complainant is entitled to non-financial loss compensation Compensation is warranted for a number of reasons. I accept the complainant says the claims process has caused a high level of stress and anxiety including concerns about not having a place to live at certain points in time. I acknowledge the complainant’s concerns and dissatisfaction as she has had to follow up the insurer on several occasions and that some of her questions still remain unanswered. I also note the complainant has not been able to live in her home for over two years (by the time the repairs are completed). The complainant’s house has remained unoccupied and unrepaired for almost two years. Determination | Case number: 918443 Page 6 of 7 The insurer failed to assist the complainant immediately after the flood. It initially agreed to do so but then cancelled its restoration contractors. It is not known why this occurred. The complainant had to remove all the contents from her home, as well as strip out the gyprock and floors herself. There have been difficulties in getting the insurer to agree to cover the temporary accommodation costs and it has only done so for certain periods of time. This has caused a lot of stress and frustration as the complainant was worried she would be homeless. The exchanged material confirms that on 4 August 2022, the insurer sent the complainant correspondence advising her scope of works had been approved. It said that a cash settlement fact sheet would be provided in the coming days. This did not occur and the insurer, instead, sent a builder to assess the property and provide a scope of works sometime later. To date, no explanation has been provided to the complainant as to why the insurer reneged on the original acceptance and quote. Had it not done so, the settlement would have been achieved over a year ago. Further, I consider the insurer took an unreasonable amount of time in obtaining its own scope of works and agreeing a cash settlement with the complainant. It has obtained five different scopes of work over a period of approximately 13 months. I also consider these delays have exacerbated the water damage at the property. The insurer has offered the complainant $5,400 in compensation. I am satisfied that this is fair and reasonable in the circumstances. 2.3 Why is the outcome fair? The insurer has failed to settle the claim in a reasonable manner and timeframe. Accordingly, it is fair that the cash settlement be increased, the complainant reimbursed for her professional costs and further temporary accommodation costs and that the insurer pay compensation. Determination | Case number: 918443 Page 7 of 7 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.