Home / QBE / Determination 916287

Determination 916287

Insurer stopped fire damage repairs and offered a cash settlement; complainant wanted repairs completed and loss of rent paid beyond policy limits

FirmQBE
Decided2023-08-14
ProductGeneral Insurance · Landlord
OutcomeFor the complainant
Amount awarded—
Non-financial loss$5,400
Amount claimed—
SourceAFCA PDF

Summary

After a 2017 fire, the insurer abandoned repairs in 2022 citing an unstable foundation and offered a cash settlement. AFCA found the foundation stable and the cash settlement unfair, and ordered the insurer to complete repairs, pay loss of rent until completion, and pay $5,400 for non-financial loss.

The foundation was stable, so the insurer had not justified abandoning repairs; under the General Insurance Code of Practice duty to act fairly a cash settlement was unfair, and insurer-caused delays meant policy limits on loss of rent should not apply.

Issues

Subjects and remedies

home or building damagepay compensationpay non financial lossrepair or rectify

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 916287 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 916287 Page 1 of 10 Case number: 916287 10 August 2023 1 Determination overview 1.1 Complaint The complainant held a landlord insurance policy with the financial firm (the insurer). She lodged a claim after the insured property was damaged by fire in 2017. The insurer started repairing the property, but repairs were severely delayed. In 2022, the insurer stopped the repairs and refused to complete them. It says it cannot repair the property because the foundation is unstable. It has offered to settle the claim by paying the complainant the cost of demolishing and rebuilding the property. The complainant does not want the insurer to pay a cash settlement, which would leave her responsible for completing the repairs (or demolishing and rebuilding the property). She says the property’s foundation is stable, and the insurer should complete the repairs. 1.2 Issues and key findings Was the insurer right to stop repairs? No. The foundation moved between 2017 and 2019 (due to errors by the insurer’s contractors), but it was stabilised by underpinning in December 2019, and hasn’t moved since. The available information indicates the foundation is stable. The insurer’s decision to stop repairs was unreasonable. Is the insurer entitled to cash-settle the claim? No. The General Insurance Code of Practice requires insurers to act fairly to their customers. A cash settlement would be unfair to the complainant, because:  the insurer started repair work and left it incomplete  the insurer is able to complete and guarantee the work  the complainant may not be able to complete the work, because it would be difficult for her to find a builder willing to complete another builder’s work  the complainant may be forced to demolish and rebuild the house, which could take years longer than completing repairs  the complainant would be responsible for appointing and managing a builder, which would be more difficult for the complainant than it would be for the insurer  the complainant would lose the insurer’s guarantee on repairs. The insurer must complete the repairs. Is the insurer required to pay more for loss of rent? Yes. The insurer has already paid more than the policy limit for loss of rent. However, the complainant continues to lose rent because the insurer has caused unreasonable delays. The insurer should compensate the complainant for this additional loss of rent, even thoug h it is not covered under the policy. The insurer must pay for loss of rent from the date of the fire and continue to pay for loss of rent until repairs are complete and the complainant has had one month to find a tenant. Determination | Case number: 916287 Page 2 of 10 Is the complainant entitled to other compensation? Yes. AFCA can award up to $5,400 compensation for non-financial loss caused by an insurer mishandling a claim. The insurer has mishandled the claim, which has caused repairs to be delayed by about five years. This warrants compensation for non-financial loss in the sum of $5,400. 1.3 Determination This determination is in favour of the complainant. Within 14 days of being informed of the complainant’s acceptance of this determination, the insurer must:  appoint a suitably qualified expert or experts to complete repairs to the insured property, and give the complainant written notice of its plan to complete the repairs in a reasonable time  pay the complainant for loss of rent from the date of the fire, less any amounts it has already paid for loss of rent  pay the complainant $5,400 compensation for non-financial loss. The insurer must continue to pay the complainant for loss of rent until one month after it informs the complainant the repairs are complete. Determination | Case number: 916287 Page 3 of 10 2 Reasons for determination 2.1 Was the insurer right to stop repairs? No. The available information indicates the foundation is stable. The insurer ’s decision to stop repairs was unreasonable. Insurer says foundation is unstable On 1 October 2017, the complainant lodged a claim for fire damage to her property. The insurer appointed a builder (B1), who started repairs in March 2018. The complainant says B1:  decided to use the wrong kind of timber to repair the roof framing  appointed a building surveyor who approved the inappropriate roof framing repairs  forged her signature on a document saying she appointed the building surveyor. In July 2018, the insurer accepted the complainant’s concerns about the roof framing were justified. The insurer removed B1 and appointed a second builder (B2). In August 2018, B2 went into administration. In September 2018, the insurer appointed a third builder (B3). In January 2019, B3 started repairs. The complainant said she noticed new cracks in the building, and was concerned about its footings. In April 2019, the complai nant’s engineer (N) inspected the property. N said the footings had moved because:  water pooled on a tarpaulin on the roof (installed by the insurer as a temporary ‘make - safe’ measure, and left in place for more than a year)  gutters and downpipes were removed from the roof, and not replaced until March 2019 (o ne of the downpipes was still disconnected during N’s inspection )  due to the above issues, water from the roof fell next to the building (and entered the soil under the building) instead of flowing into stormwater drains. N recommended stabilising the soil with resin injection underpinning (injecting expanding resin into the soil), then waiting three months to resume repairs. In December 2019, the complainant’s builder injected resin into the soil. In 2020, the claim was delayed by several factors, including COVID-19. In April 2021, B3 prepared a new scope of works to complete repairs. The insurer authorised B3 to complete repairs in accordance with the scope. In March 2022, B3 resumed repairs. According to the insurer, B3 said they wanted to appoint an engineer to determine whether the foundation was stable enough for them to warrant repairs. The insurer says it appointed engineers who determined the foundation was unstable, and would continue to move. The insurer says ongoing foundation movement will cause further damage to the building, so it is futile to continue with repairs. In July 2022, the insurer said it would not complete the repairs. It said it would settle the claim by paying the complainant the cost of demolishing and rebuilding the building. Determination | Case number: 916287 Page 4 of 10 Foundation has been stable since December 2019 In April 2022, the insurer appointed an engineer (SS). SS said there was a ‘Category 3’ crack in the northeast corner of the building. SS appears to have assumed this occurred after the underpinning. SS concluded the underpinning had failed, and the footings would continue to move. SS did not give any reason for concluding the underpinning had failed, other than the existence of a single crack. The complainant said no cracks had appeared in the building since the underpinning in December 2019. She said what SS identified as a ‘Category 3’ crack was actually a gap left by B3 removing mortar in December 2019 (she confirmed this by providing photographs taken by B3 in December 2019; the photographs show gaps between bricks in the northeast corner of the building, and B3 captioned them ‘Removal of Mortar’ ). She asked the insurer to get a second opinion. In June 2022, the insurer appointed another engineer (EI). EI did not say whether any movement or cracking had occurred since the underpinning in December 2019. EI said the footings were ‘suitable for re - use’. The available information indicates no significant movement or cracking has occurred since the underpinning in December 2019. The available information indicates the building’s foundation is stable. Foundation movement possible for all buildings EI’s report recommended several measures to make the building less likely to crack in the future. EI’s report then gave the following disclaimer: Even with the measures above, we note that due to the reactive nature of the foundation material and history of movement related damage and repairs, we would expect further cracking defects will likely occur in the future, irrespective of repairs undertaken, as a result of general foundation movement from seasonal changes in the foundation moisture condition. Ongoing routine maintenance will be required. The insurer says EI’s disclaimer means repairs cannot be warranted, becau se the home will continue to crack no matter how it is repaired. The complainant says EI’s disclaimer ‘ applies to every single home ’. SS’ report includes the following quote from Australian Standard 2870: Residential slabs and footings : It is acknowledged that minor foundation movements occur on nearly all sites and that it is impracticable to design a footing system that will protect the building from movement under all circumstances. For most situations Category 0 or 1 cracks should be the limit; however, under adverse conditions, Category 2 cracks should be expected although such damage should be rare. EI said the insured building may crack after it is repaired. However, EI described the repair of these cracks as ‘routine maintenance’. This implies the expected cracking is normal wear and tear. Determination | Case number: 916287 Page 5 of 10 Insurer has not justified decision to stop repairs Every building is subject to damage from wear and tear, which includes cracking caused by ordinary ground movement. The possibility that a building will be damaged by wear and tear does not mean repairs cannot be warranted. If it did, no building repairs could ever be warranted. The available information indicates the insured building is no more susceptible to movement or cracking than is typical for buildings of its type. The risk of future cracking is not so severe that repairs cannot be warranted. The insurer has not justified its decision to stop repairing the building. 2.2 Is the insurer entitled to cash-settle the claim? No. A cash settlement would be unfair to the complainant. The insurer must complete the repairs. Complainant has not accepted insurer’s offer The insurer has offered to pay the complainant the cost of demolishing and rebuilding the house , plus one year’s loss of rent . The insurer’s offer is to settl e the claim by paying $585.675.92, being:  $482,079.93 (the amount quoted by B3 to demolish and rebuild the house)  $72,311.99 as a cost contingency (15% of the above amount)  $31,284 for one year’s loss of rent (in addition to $ 140,778 already paid for four and a half years’ loss of rent). The complainant has rejected the insurer’s offer. She says she wants the insurer to complete the repairs, because:  completing the repairs would be much quicker than demolishing and rebuilding the house. The foundations are stable. The framework has passed inspection. A kitchen and appliances are in storage and ready to be installed  there is an active building permit with B3 as the designated builder. The permit is due to lapse in December 2023, and cannot be renewed because it has already been renewed twice. If the insurer cash-settles the claim, she will have to obtain a new building permit, which will take months  it will be difficult for her to appoint a builder because the construction industry is overwhelmed with work. If she can find a builder, it will take at least six months for them to start. Some builders have told her it would take them 12 to 18 months to start, and many have told her they are too busy to take the job at all  many builders have told her they do not want to work on a property that has already had so much work done by other builders  the amount offered by the insurer may not be enough to demolish and rebuild the house (she has obtained a quote from another builder for this work totalling $826,444)  the amount offered by the insurer for loss of rent may not be enough to cover the time it will take to demolish and rebuild the house  she is caring for her mother, who is physically incapacitated, and supervising building work would take time away from her caring responsibilities. The insurer says the complainant could use the cash settlement to complete the repairs. However, the panel believes it would be difficult for the complainant to find a repairer willing to complete work started by the insurer’s builders (and such work would not come with a Determination | Case number: 916287 Page 6 of 10 warranty). If the insurer cash-settles the claim, the complainant may be forced to demolish and rebuild the house, which could take years longer than completing repairs. The General Insurance Code of Practice (to which the insurer subscribes) says that if an insurer ‘selected and directly authorised a repairer’, it must guarantee the quality of the repairs. If the insurer authorises its builders to complete repairs, it will be responsible for rectifying any fault in the repairs. If the insurer cash-settles the claim, the complainant will have to do the work of appointing and managing a builder, and will bear the risk of incurring rectification costs if the repairs are faulty. For the above reasons, the complainant will be significantly disadvantaged if the insurer leaves repairs unfinished, even if it pays the cost of demolishing and rebuilding the house. Cash settlement not fair to complainant The product disclosure statement for the complainant ’s policy says that if the insurer accepts a claim, it will pay the reasonable cost of repairing or rebuilding the building. It does not say the insurer will appoint a repairer. The General Insurance Code of Practice requires insurers to act fairly to their customers. When an insurer offers to cash-settle a claim rather than appointing a repairer, AFCA will consider whether the proposed settlement is fair. AFCA generally considers that if an insurer starts repairs, it should finish them. It is unsatisfactory to abandon repair work and leave the insured responsible for finishing it. An insurer may be left with no other option if it cannot complete repairs. However, in this case, the insurer has not shown it cannot complete and guarantee the repairs. The insurer has offered to pay the cost of demolishing and rebuilding the house. The amount it has offered is much more than the building sum insured ($335,000). Despite this, the panel believes a cash settlement would be unfair, because:  the insurer started repair work and left it incomplete  the insurer is able to complete and guarantee the work  the complainant may not be able to complete the work, because it would be difficult for her to find a builder willing to complete another builder’s work  the complainant may be forced to demolish and rebuild the house, which could take years longer than completing repairs  the complainant would be responsible for appointing and managing a builder, which would be more difficult for the complainant than it would be for the insurer  the complainant would lose the insurer’s guarantee on repairs. Within 14 days of being informed of the complainant’s acceptance of this determination, the insurer must appoint a suitably qualified expert or experts to complete the repairs, and give the complainant written notice of its plan to complete the repairs in a reasonable time. Insurer may only cash-settle if it is impossible to complete repairs The parties will need to work together to allow the insurer to complete repairs. Depending on both parties’ conduct, their relationship may deteriorate to the extent that it becomes impossible for them to work together, and the insurer will not be able to complete repairs. If it is impossible for the insurer to complete repairs, it may settle the claim by demolishing and rebuilding the house. If this is also impossible, it may settle the claim by paying the cost of demolishing and rebuilding the house. The insurer may not exercise these options unless it has made every reasonable attempt to complete repairs. If the insurer claims it is impossible Determination | Case number: 916287 Page 7 of 10 for it to complete repairs, and the complainant alleges otherwise, the complainant may lodge another AFCA complaint. If the insurer cash-settles the claim, it must pay the complainant an amount that will allow her to demolish and rebuild the house. It must also pay the complainant an amount that fairly compensates her for the disadvantages that come with a cash settlement, including the loss of the insurer’s guarantee and the difficulty of appointing a builder. If the parties cannot agree on a fair settlement sum, the complainant may lodge another AFCA complaint. 2.3 Is the insurer required to pay more for loss of rent? Yes. The insurer must continue to pay for loss of rent until repairs are complete and the complainant has had one month to find a tenant. Insurer not entitled to apply policy limits At the time of the fire, the building sum insured was $335,000, and the policy covered up to one year’s loss of rent. The insurer has offered to settle the claim by paying $5 54,391.92 for building work, and a total of five and a half years’ loss of rent. The cost of repairing or rebuilding the house and the complainant’s loss of rent will significantly exceed the policy limits. However, this has occurred because of lengthy delays in completing repairs, compounded by faulty make-safe work that directed water under the house. The delays and the faulty make-safe work were the insurer’s fault. If the insurer settled the claim in accordance with the policy terms within a reasonable time, the building probably would have been repaired for less than the building sum insured, and would have been ready to re-let within a year. The complainant’s losses have exceeded the policy limits because of the insurer’s errors. Therefore, it would not be fair for the insurer to apply the policy limits. Insurer must pay loss of rent until property is repaired The insurer has paid loss of rent at a rate of $31,284 per year. The complainant has not disputed this rate. The policy covers loss of rent for up to one year from the time of the damage. Therefore, the policy only covers loss of rent to October 2018. However, since October 2018, the insured property has been uninhabitable because of the insurer’s mishandling of the claim. Therefore, it is fair for the insurer to continue to pay for the complainant’s loss of rent. The insurer must pay loss of rent from 1 October 2017 (the date of the fire and the date of claim lodgement) to date, less any amount it has already paid. The insurer must continue to pay loss of rent until repairs are complete and the complainant has had one month to find a tenant. If the complainant unreasonably restricts or prevents the insurer from completing repairs, the insurer is not required to pay loss of rent for any resulting delay. Determination | Case number: 916287 Page 8 of 10 2.4 Is the complainant entitled to other compensation? Yes. The insurer mishandled the claim, causing repairs to be delayed by about five years. The insurer must pay $5,400 compensation for the resulting stress and inconvenience. AFCA can award compensation for non-financial loss Under the AFCA Rules, we can award up to $5,400 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim. We do not award compensation for the usual amount of inconvenience involved in making a claim. We do not award compensation for delays caused by the complainant, or other factors outside the insurer’s control. Insurer mishandled claim The insurer and its contractors mishandled the claim, because:  the first builder it appointed failed to properly repair the roof framing. This led to a significant delay in repairs. Repairs did not resume until January 2019, more than a year after the claim was lodged  the make-safe work it authorised was faulty, and damaged the house’s foundation . This led to further delays. Repairs did not resume until March 2022, about four and a half years after the claim was lodged  in July 2022, almost five years after starting repairs, the insurer decided to stop repairs and leave them incomplete. For the reasons set out above, this decision was unreasonable. The complainant was not at fault for the repair delays. She stopped repairs in 2018 due to concerns about the roof framing, and in 2019 due to concerns about the footings, but on both occasions, her concerns were justified. In 2020, the claim was delayed by several factors, including COVID-19. Restrictions related to COVID- 19 were outside the insurer’s control. However, if the insurer handled the claim correctly, it would have been settled well before 2020. Furthermore, the insurer continued to cause unreasonable delays after the restrictions were lifted. Insurer must pay compensation for non-financial loss The mishandling of the claim has caused the complainant to suffer an unusual degree of stress, inconvenience, and delay, because:  the house’s foundation was damaged . The complainant went to the trouble of appointing an engineer to confirm the foundation was damaged, and appointing a builder to stabilise it  the house became infested with mould, necessitating an extensive strip-out in March 2022  the house was left vulnerable to burglary. Keys to the house were left in a key safe on the front door. A plywood panel used as a side gate kept blowing over, and the complainant had to keep putting it back up. There were two attempted burglaries  B3 asked the complainant to buy fixtures and fittings in 2018, to be installed in 2019. The complainant bought the fixtures and fittings, and has been storing them on a neighbouring property (owned by a relative)  on many occasions, the complainant had to deal with new staff members being assigned to deal with her claim. Several of these staff members had conflicting ideas about how the property should be repaired, causing confusion and delay  the house, which should have been repaired in 2018, remains uninhabitable in August 2023. Determination | Case number: 916287 Page 9 of 10 The insurer’s mishandling of the claim has delayed its resolution by about five years. This has caused the complainant a great deal of stress and inconvenience. The complainant has spent an inordinate amount of time and effort dealing with the claim (far beyond the usual amount of inconvenience involved in making a claim). The panel believes this warrants compensation for non-financial loss in the sum of $5,400. Determination | Case number: 916287 Page 10 of 10 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with extensive experience in consumer and small business advocacy  a member with extensive experience in insurance.