Home / Allianz Australia / Determination 914983

Determination 914983

Unreasonable delay in repairs following accepted fence damage claim

FirmAllianz Australia
Decided2023-03-03
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

The complainant's landlord insurer accepted a claim for fence damage caused by a vehicle, but repairs were delayed about five weeks while the scope of works was finalised and by poor contact with the contractor. AFCA found the insurer unreasonably delayed the repairs and ordered $500 non-financial loss compensation; quality of repairs was not considered.

The insurer unreasonably delayed finalising the scope of works and failed to respond to the complainant, causing unusual stress and inconvenience warranting non-financial loss compensation.

Issues

Subjects and remedies

home or building damagemotor vehicle collisionpay non financial loss

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 914983 Financial firm Allianz Australia Insurance Limited Determination | Case number: 914983 Page 1 of 6 Case number: 914983 2 March 2023 1 Determination overview 1.1 Complaint The complainant holds a landlord insurance policy with the financial firm (insurer), covering his investment property (property). On 14 July 2022, the complainant lodged a claim after a vehicle impacted the front fence of the property (damage). The insurer accepted the claim. On 14 September 2022, the complainant lodged this complaint with the Australian Financial Complaints Authority (AFCA). He said the insurer was delaying the claim. As a resolution, he wanted the insurer to expedite the completion of the repairs. On 18 October 2022, the insurer says it completed the repairs. The complainant disagrees. He says the repairs were completed to a level below the Australian standard. Therefore, he considers the repairs are still incomplete. As discussed with the parties, this complaint is solely about whether the insurer unreasonably delayed the repairs. The complainant will need to lodge a new AFCA complaint regarding any concerns he has about the quality of the repairs. 1.2 Issues and key findings Did the insurer unreasonably delay the repairs? Yes. There were delays finalising the scope of works. This delayed the repairs for about five weeks. There were also periods where the insurer delayed or failed to respond to the complainant. The insurer should compensate the complainant $500 for his non-financial loss. Why is the outcome fair? The insurer commits to providing a high standard of service. I am satisfied the insurer did not meet the standard in this case. It is fair for the insurer to compensate the complainant for this. However, it would not be fair to consider the quality of repairs for the reasons outlined below. 1.3 Determination This determination is substantially in favour of the insurer. Within 14 days of the complainant accepting this determination, the insurer should pay $500 into an account of the complainant’s choice as compensation for his non -financial loss. If the complainant does not accept this determination, no action is required. Determination | Case number: 914983 Page 2 of 6 2 Reasons for determination 2.1 Did the insurer unreasonably delay the repairs? Yes. There were delays finalising the scope of works. This delayed the repairs for about five weeks. There were also periods where the insurer delayed or failed to respond to the complainant. The insurer should compensate the complainant $500 for his non-financial loss. There were delays finalising the scope of works On 20 July 2022, the insurer appointed a builder, RC, to manage the repairs of the damage. On 29 July 2022, a site inspection was completed at the property. On this date, work was also completed to ensure the area was safe and the remaining fence was secure. On 17 August 2022, the insurer sent RC’s scope of works (SOW) to the complainant. The complainant highlighted several concerns with the SOW. On 23 August 2022, the insurer confirmed there was no excess payable and it was awaiting the updated SOW from RC. On 30 August 2022, the complainant followed up with the insurer. On the same date, the insurer sent the complainant the ‘site report’ dated 1 8 August 2022. The complainant said this is the damage report, not the SOW. The insurer asked RC to contact the complainant. On 8 September 2022, the complainant said he was still waiting for the SOW from RC. On this date, RC said someone from a different company, WC, is meeting the complainant on site tomorrow. The complainant had not heard about this meeting and was unable to attend. On 9 September 2022, the complainant asked the insurer for an update and to provide the SOW by 14 September 2022 or he would refer the claim to AFCA. On 12 September 2022, the insurer said it had spoken with RC and it will contact the complainant tomorrow. On 13 September 2022, the complainant said he had again not heard from RC. By close of business the next day, 14 September 2022, the insurer and RC had still not contacted the complainant. Therefore, the complainant lodged this AFCA complaint. The insurer escalated the issue with RC. It said RC was supposed to contact the complainant on 1 September 2022 and 13 September 2022 which did not occur. On 19 September 2022, the insurer spoke with RC and it agreed the SOW it provided was insufficient. On 20 September 2022, RC sent the new SOW to the complainant. However, it did not have a start date or completion date. The complainant highlighted this to RC. RC then entered an estimated start date of 7 October 2022 and an estimated completion date of 29 October 2022. The complainant wanted the repairs to start and finish sooner. RC amended the estimated start date to 22 September 2022 and the estimated completion date to 19 October 2022. On 21 September 2022, the complainant signed and returned the SOW. Complainant is entitled to some compensation for non-financial loss I accept the complainant was not required to sign and accept the SOW until the information was true and correct. Therefore, I am satisfied the issues with finalising the SOW delayed the start of the repairs by about five weeks (17 August 2022 to 21 September 2022). I am also satisfied that there were delays with the insurer and/or RC contacting or responding to the complainant. The insurer accepts that RC said it would contact the complainant on 1 September 2022 and 13 September 2022 but failed to do so. Determination | Case number: 914983 Page 3 of 6 AFCA has the power to award compensation for non-financial loss. Non-financial loss includes claims for stress or inconvenience caused by an error of the financial firm. I have outline more information about our approach to awarding compensation in section 3.1 below. In this case, I accept the delays starting repairs and the lack of communication caused the complainant unusual stress and inconvenience. Therefore, if he accepts this determination, the insurer should compensate the complainant $500 for his non-financial loss. Repairs were completed before the agreed estimated completion date The complainant says the insurer and its appointed contractors treated the claim as a ‘ low priority ’ and a ‘fill in job’. H e says the contractors attended the property in between other jobs on weekends, public holidays and during inclement weather to save money. On 12 October 2022, the complainant emailed the insurer and said the repairs had stalled and no work had been done since 22 September 2022. He said RC could not use the weather as an excuse because there were several days of ideal weather to complete the work. On 14 October 2022, RC said rendering work will start today and be finished by Monday. It said painting will be completed on Tuesday, 18 October 2022. The complainant was unhappy the renderer did not turn up on this date as advised. They arrived the next day, a Saturday. However, although there is a dispute about quality (discussed further below), RC completed the repairs on 18 October 2022. This was the day before the estimated completion date on the SOW. Therefore, I do not consider there were any further delays once the repairs started. Complainant raised several concerns regarding the quality of repairs The complainant raised several concerns regarding the quality of the repairs. For example, he says the contractors used an extremely porous, second hand or repurposed brick with green algae growth. He also says the fence was rendered and painted while the bricks were wet. He took readings on a hydrometer of the fence two hours before it was painted which he says shows there was 100% relative moisture content. He says the render and paint will deteriorate rapidly. On 24 November 2022, the insurer said it had asked RC to attend the property to certify that the repairs were completed in accordance with Australian standards. On 30 November 2022, RC received an email from the complainant which said: Hi [RC], No date will be acceptable as I do not want anyone from [RC] near my property again after the negligent way that you carried out the repairs. I have the evidence in photos and moisture tests carried out during your rectification works and will use those as evidence when required. On 9 December 2022, the insurer engaged a structural engineer, AG, to inspect the fence. On the same date, the complainant sent a text message to AG which said: Hi [AG] There is nothing structurally wrong with the fence, it’s defective rendering and painting which I do not believe you have the expertise to assess so I won’t be providing access. You are welcome to look from the street but please do not bother the tenants or enter the property. Be aware that there are security cameras at the property. Determination | Case number: 914983 Page 4 of 6 On 13 December 2022, the insurer advised the complainant that it cannot assess any repair issues without inspecting the completed repairs. It asked the complainant to provide information showing poor workmanship or engage his own contractor to complete a report. In response, the complainant says he refused to allow RC to return to the property because it was the ‘ offending contractor ’ and it cannot assess its own work. He also says AG is a structural engineer and the defects with the fence are not structural. The complainant can lodge a new complaint regarding quality of repairs The complainant says the time for inspecting and assessing the fence was before the render and paint was applied, when he identified the defects. He says RC deliberately covered the standard of the repairs. He has offered to provide a building defect report if requested. In response, the insurer says there is no evidence that any rectification is required. However, it says the repairs are warranted. Therefore, if any issues arise regarding the repairs in the future, the insurer says they will be assessed and rectified. The insurer also says RC advised the complainant its works are warranted. The insurer says if there are any obvious spot rust marks, render detaching, blemishes or run marks that would be considered defective from a normal view point, RC would rectify these. As outlined previously to the parties, this complaint is about whether the insurer unreasonably delayed the repairs. I have addressed this issue above. However, I have not addressed any further issues regarding the quality of the repairs. If the complainant remains unhappy with the repairs, he can provide further information to the insurer in support of his position. The complainant should also take reasonable steps to allow the insurer to obtain its own report of the repairs if required. The parties should work together to resolve any further complaint. However, if they are unable to do so, or the complainant is unhappy with the response he receives from the insurer, he is entitled to lodge a new AFCA complaint. Determination | Case number: 914983 Page 5 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. AFCA approach to awarding compensation for non-financial loss Non-financial loss includes claims for stress or inconvenience caused by an error of the financial firm. The maximum amount we can award for non-financial loss is $5,400 for each claim (for complaints lodged after 1 January 2021). We recognise that making a claim can be stressful and time-consuming, even if the insurer handles the claim correctly. We will not award compensation for the ordinary degree of inconvenience that comes with making a claim. We take a conservative approach to awarding compensation for non-financial loss. Compensation for non-financial loss is only provided where the complainant has suffered from an unusual amount of physical inconvenience or the time taken to resolve the situation has been unusually long. We do not award non-financial loss compensation merely because the complainant has suffered some inconvenience and anxiety. We expect complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. Determination | Case number: 914983 Page 6 of 6 If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.