Cyclone storm damage claim partly declined for pre-existing damage, termites, rust and wear and tear; dispute over scope of works and cash settlement amount
Text of the determination
Determination
Case number 914518
Financial firm Hollard Insurance Partners Limited
Determination | Case number: 914518 Page 1 of 7
Case number: 914518 22 February 2023
1 Determination overview
1.1 Complaint
The complainant holds a home building and contents insurance policy with the financial firm
(insurer) and lodged a claim in Aril 2021 for damage to his property following a cyclone event
that occurred on 11 April 2021.
The insurer accepted damage to the property. However, it declined damage to the carport
timbers/steel framing and the subfloor stumps on the basis that damage to these areas is due
to termites, rust, lack of maintenance, wear and tear, which the policy excludes.
A dispute has arisen about the scope of works (SOW) necessary to repair the damages to an
appropriate standard, the reasonable cost of repairs and the way in which the insurer handled
the claim overall.
The complainant seeks the insurer to cash settle the claim based on his repair quotation of
$226,724.30 from his builder, RSA.
1.2 Issues and key findings
Is the insurer required to increase the cash settlement?
The evidence does not establish the complainant’s quotes most accurately reflect the
reasonable cost of repairs. The insurer’s quote for $ 105,405.87 is an appropriate starting
point to determine a fair cash settlement, since it reasonably reflects the scope of works.
However, the insurer’s cash settlement offer should be increased by a further 25% to allow for
unforeseen variations and the additional risks assumed by the complainant in undertaking the
work directly (since he loses the benefit of the insurer’s lifetime guarantee on repairs).
1.3 Determination
This determination is partially in favour of the insurer. Within 14 days of the parties’
acceptance of this determination, the insurer is to:
cash settle the balance of the claim for building repairs for $44,028.50
pay the complainant $6,000 for the handling of the asbestos and clean up and
reimburse any costs incurred by the complainant in obtaining the report and quotation from
RSA.
The insurer is required to pay statutory interest on the settlement sum from 1 March 2022
until the date of payment.
Determination | Case number: 914518 Page 2 of 7
2 Reasons for determination
Due to the nature of the issues involved we have considered it appropriate to expedite this
complaint in accordance with the Operational Guidelines to the AFCA Rules. Accordingly, this
complaint has not been the subject of a preliminary assessment and has proceeded directly
to determination.
There has been a full exchange of all material information relied on for this determination and
each party has had the opportunity to address any issues raised by the other. All material
provided by the parties has been reviewed and considered.
The determination follows review of all relevant material. It is based on what is fair in all the
circumstances having regard to the relevant legal principles, terms of the policy, good
industry practice including codes of practice and prior determinations where applicable.
While the parties have raised numerous issues in their submissions, for the purposes of this
determination, commentary has been restricted to those issues considered directly relevant to
the outcome only
2.1 Is the insurer required to increase the cash settlement?
The evidence does not establish t he complainant’s quotes most accurately reflect the
reasonable cost of repairs. The insurer’s quote for $ 105,405.87 is an appropriate starting
point to determine a fair cash settlement, since it reasonably reflects the scope of works.
However, the insurer ’s cash settlement offer should be increased by a further 25% to allow for
unforeseen variations and the additional risks assumed by the complainant in undertaking the
work directly (since he loses the benefit of the insurer’s lifetime guarantee on repairs ).
Complainant has the onus to establish claim falls within terms of policy
It is established insurance law that an insured has the initial onus to establish on the balance
of probabilities (that is more likely than not) a claim that falls within the terms of the policy.
The complainant’s policy is an insured events policy that provides cover for several insured
events including storm damage, subject to conditions and exclusions.
The complainant lodged the claim on 16 April 2021 and says his building has sustained
severe damage due to the cyclone event that occurred on 11 April 2021.
The insurer partially accepted the claim for building damage resulting from the claimed event
but denied damage that is related to pre-existing, deterioration, wear and tear.
The complainant denies any pre-existing maintenance issues with the building. The dispute
relates to the extent the damage is due to the cyclone or is pre-existing damage.
Reports indicate pre-existing maintenance issues contributed to building
damage.
In support of the claim, the complainant provided an inspection report and scope of works
from consulting engineers RSA. The report provided a quote for repairs of $226,724.30. The
building repair scope is for a total home renovation, on the basis that the property is not in
compliance with the current relevant building codes and standards and needs to be renovated
to comply with the current standard, it also includes damaged items and various upgrades
that are not insured event related.
Determination | Case number: 914518 Page 3 of 7
The report from RSA identified insured event damage, as well as damage due to pre-existing
maintenance, defects and poor construction.
The insurer accepted liability for damages that were caused by the cyclone. However, it says
it is not response for damage to the carport timbers/steel framing and the subfloor stumps on
the basis that damage to these areas is due to termites, rust, lack of maintenance, wear and
tear, which the policy excludes.
The insurer relies on a report from its appointed building consultant, SBC, who attended the
site on 19 January 2022 and noted damage to the building due to the cyclone event and pre-
existing maintenance.
SBC ’s report concludes:
Our summary of the above opinions is as follows:
6.1. I was unable to determine the extent of the damage to the main roof tiles as
they were covered by a tarpaulin and not visual at the time of the inspection
6.2. The visual inspection within the roof area has identified a number of cracked
and broken tiles, in various locations over the whole property.
6.3. The damage to the roof tiles on the northern elevation eaves overhang, is
typical damage for this storm event.
6.4. The damage to the eastern elevation attached garage roof sheeting and the
associated flashing is typical damage for this storm event.
6.5. The metal roof sheeting over bedroom 3 was uplifted and peeled back which
is typical damage for this type of storm event.
6.6. The boundary fencing is a mixture of asbestos and fibre cement sheeting with
evidence that the majority of the fencing was in a damaged and deteriorates state
prior to the storm event.
The complainant disagrees with the SBC ’s report and says he had regularly maintained the
building and treated the termites issue under the subfloor before the cyclone event. He denies
that maintenance issues contributed to the damage.
The complainant provided a supplementary commentary from RSA, which details:
Items that have not been affected from TC Seroja event.
Item 10 – The end grains of the roof beams have been affected from dry rot over
time. This damage would not affect the structural capacity of the timber members
at the time of the cyclonic event and will only affect approximately 100mm of the
ends of the timber beams.
Determination | Case number: 914518 Page 4 of 7
Item 15 & 45 – Surface corrosion to steel portal frames was present, however,
RSA did not witness any significant section losses due to the corrosion. This
damage would not affect the structural capacity of the steel members at the time
of the cyclonic event.
Item 22, 23 & 24 – Some external stumps had signs of termite attack at some
stage prior to the cyclonic event. All signs of termite attack were minor in nature
and the damage was limited to insignificant surface pitting and some mud tubes.
In relation to the carport and subfloor we make the following comments.
The carport timber purlins had no sign of termite attack at the time of the
structural inspection. The structure did show signs of high loading which is likely
to have been sustained from TC Seroja. The timber purlins have creeped over
time, which is a natural occurrence when green hardwoods have been used in the
initial construction of the roof.
The steel sections that make up the carport structure did show signs of surface
corrosion at the time of the inspection, however as noted above in point 2, no
significant section loss was witnessed and would not affect the structural capacity
of the steel portals.
The sub floor stumps did have signs of minor termite attack; however, all stumps
were intact and no local failures were observed. If the termite attacks were
significant then we would expect to see some stumps fail due to section loss. The
issue we see the stumps have faced is the significant shunting of the whole house
(lateral force from high winds). The significant loading has moved the house from
their supports and are positioned offset from their initial design locations. When
stumps have high loads and significant wetting from the storm coupled with offset
bearing locations we would expect the stumps to begin to settle as shown in our
inspection report.
The house has wi thstood an Ultimate Limit State event within its’ life.
It is highly unlikely the structure would respond in the same manner if another
high wind event were to batter the house again without major remedial actions
noted in our report and scope of works documents.
Having carefully reviewed the parties’ experts’ reports, I am satisfied both reports establish
the building has significant pre-existing damage and maintenance issues.
The complainant’s arguments do not advance his position
The complainant says the building needs to be brought up to compliance with current building
standards and codes. He says the amount the insurer has offered is inadequate to address
the repairs required. I am not persuaded that the need for the property to be brought up to
comp liance with current building standards and codes is the insurer’s responsibility.
Determination | Case number: 914518 Page 5 of 7
Further, the complainant says he is a 71-year-old pensioner, who has been a loyal customer
and has held his policy with the insurer for about 10 years. It is his view that the insurer
should settle the claim based on this repair quote from RSA. In addition, the complainant says
he treated the termites at the time and there have not been any further issues to the subfloor.
However, I note there is no evidence of the termites’ treatment at the time.
While I acknowledge the complainant’s age and being a loyal customer of the insurer, these
on its own should not be a basis for the insurer’s assessment of the claim. Both experts’
reports establish that not all the identified damage to the building was caused by the cyclone
event as claimed.
It is fair the insurer increases its cash settlement
Having reviewed al l the information, I am satisfied the insurer’s quotes are fair and
reasonable. The information available shows the poor and deteriorated condition of the
building prior to the cyclone event. All experts’ report s confirmed pre-existing damage to the
building, including pre-existing damage to the carport timbers/steel framing and the subfloor
stumps, which required maintenance by the complainant.
In my view, the building has extensive pre-existing damage. The building has evidence of
gradual deterioration, noting the maintenance related issues such as roof beams dry rot,
surface corrosion to steel portal frames and signs of termites’ attack to the stumps.
I accept the insurer is not liable for re-stumping of the subfloor, not liable for the replacement
of the carport timber/steel frames and other damages not directly related to the cyclone event
of April 2021. The photographs provided support this observation. Further, I accept the policy
does not cover a betterment of the building.
Based on the available information, I consider the insurer’s quote for $105,405.87 represents
a reasonable starting point for determining an appropriate cash settlement.
I also acknowledge that in cash settling the claim, the complainant gives up the lifetime
guarantee on repairs provided under the policy. Furthermore, a cash settlement transfers all
the risk from the insurer to the complainant of any unforeseen damage and any additional
work required once repairs commence.
I consider it fair in the circumstances to allow a further 25%, on top of the insurer’s quote to
account for the transfer of the risk to the complainant and the potential increase in costs of
labour and materials since the quote was drafted. Therefore, the insurer is to settle the claim
for $131,757.33. I note the insurer has already cash settled the complainant $87,728.83.
In addition, the insurer has offered $2,500 to cover the cost for asbestos testing and clean up.
I note the insurer has not provided any quote to support this offer nor has it provided any
other information to show the amount offered will cover the cost for testing the asbestos and
clean up.
However, I note the complainant’s quote from RSA included $6,000 for asbestos removal and
disposal. Therefore, I consider it appropriate the insurer pay $6,000 for the handling of the
asbestos.
In summary, within 14 days of the parties’ acceptance of this determination, the insurer is to:
cash settle the balance of the claim for building repairs for $44,028.50
pay the complainant $6,000 for the handling of the asbestos and clean up
The insurer is required to pay statutory interest on the settlement sum from 1 March 2022
until the date of payment.
Determination | Case number: 914518 Page 6 of 7
I found the report from RSA to be useful in reaching my determination.
I am satisfied it is fair that the insurer is to reimburse the complainant that costs he incurred in
engaging RSA.
The complainant is to provide the insurer with copy receipts and invoices.
Non-Financial loss compensation
Under AFCA’s Rules, we may award compensation (capped at $5,400) for non -financial loss
where a complainant has suffered an unusual degree or extent of physical inconvenience,
time taken to resolve the situation or interference with their expectation of enjoyment or peace
of mind.
However, we adopt a conservative approach to the award of compensation for non-financial
loss. We expect complainants to be moderately robust and bear the usual stress and
inconvenience associated with an insurance claim.
The onus is on the complainant to establish he has suffered a loss because the insurer
mishandled the claim.
Having reviewed all the exchanged material, I am not satisfied that the complainant has
established the insurer mishandled the claim, so as to warrant non-financial loss
compensation.
Outcome is fair in the circumstances
The outcome is fair as it recognises the extent of the contribution to the loss or damage by
the cyclone event and the pre-existing damage.
The complainant’ s circumstances are unfortunate, and I understand he has suffered a loss.
However, the information shows there were other causes of damage to the building that are
excluded under the policy and it is fair to apportion that loss.
Determination | Case number: 914518 Page 7 of 7
3 Supporting information
3.1 The AFCA processes
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.