Partial denial of flood building claim (piers and stumps) and cash settlement amount dispute
Text of the determination
Determination
Case number 912215
Financial firm Auto & General Services Pty Ltd
Determination | Case number: 912215 Page 1 of 7
Case number: 912215 31 July 2023
1 Determination overview
1.1 Complaint
The complainant holds home building and contents insurance issued by the financial firm
(insurer). On 1 March 2022, she lodged claims after a flood event caused damage to her
home and contents. The contents claim has been resolved.
The insurer partially accepted the building claim but denied liability for the home’s piers and
stumps on the basis the damage was pre-existing and from excluded causes. The insurer has
made several cash settlement offers, culminating in a $233,006.83 offer inclusive of a 30%
contingencies uplift. It has also paid $20,000 in temporary accommodation (TA) costs.
The complainant says the insurer’s cash settlement offer is insufficient and under-priced,
including because the pier and stump repairs should be included in the scope of works
(SOW). She seeks a much higher cash settlement amount, additional TA costs, and non-
financial loss compensation.
1.2 Issues and key findings
Are investigations still required to enable cash settlement?
Yes. The claim related repairs include the piers and stumps. The insurer is to obtain from an
expert not previously involved in the claim an actionable retail quote based on an adequate
SOW. The cash settlement is to include a TA allowance based on the expert’s estimate of
how long the property will be unliveable during repairs. A 20% uplift is to be applied.
Is non-financial loss compensation payable?
Yes. The insurer’s poor claim handling and delays have caused the complainant unnecessary
stress and inconvenience. It is required to pay her $2,000 in non-financial loss compensation.
Why is the outcome fair?
The insurer’s cash settlement offer is not fa ir because it is not based on a SOW that
adequately accounts for all claim related repairs and a quote actionable by a retail customer.
It is fair that the insurer obtains a fresh SOW/quote and pays compensation for stress caused.
1.3 Determination
This determination is in favour of the complainant. If the complainant provides written notice
she accepts this determination (notice), the following steps are to be taken:
the insurer is to cash settle the claim related building repairs and future TA entitlements in
accordance with section 2.1 of this determination, and
within 14 days of the notice, the insurer is to pay the complainant $2,000 in compensation.
Determination | Case number: 912215 Page 2 of 7
2 Reasons for determination
The complainant is represented by claim advocate, DK. In this determination, the complainant
and DK are referred to as ‘the complainant’, unless context requires otherwise.
The parties provided numerous submissions to AFCA. While this determination does not refer
to each submission, the panel has taken them all into account in reaching its decision.
2.1 Are investigations still required to enable cash settlement?
Yes. The claim related repairs include the piers and stumps. The insurer is to obtain from an
expert not previously involved in the claim an actionable retail quote based on an adequate
SOW. The cash settlement is to include a TA allowance based on the expert’s estimate of
how long the property will be unliveable during repairs. A 20% uplift is to be applied.
Complainant has shown a claimable loss under the policy
The complainant is required to show, on the balance of probabilities (that it is more likely than
not), that she suffered a claimable loss under the policy. This means she must show the loss
was caused by a risk for which they are insured.
Subject to the terms and conditions set out in the product disclosure statement (PDS), the
compl ainant’s policy covers damage to the insured property caused by a listed insured event.
Thos e events include ‘Flood’ . The applicable sum insured for building damage is $500,000.
It is not in dispute that the complainant’s home and some of its contents were damaged
during a flood event on 28 February 2022. The insurer has accepted and settled the contents
claim and partially accepted the building claim.
Accordingly, the insurer accepts that the complainant has shown a claimable loss. However,
the in surer maintains the damage to the home’s piers and stumps was pre -existing and the
result of excluded ground movement.
Once the complainant proves the existence of a claimable loss, the insurer is liable for the
loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of
proving on the balance of probabilities the application of the exclusion or condition.
Insurer says the disputed damage is excluded
On 15 April 2022, the insurer’s appointed builder, RP, inspected the insured property. In
relation to the foundations, RP reported that:
the property had been relevelled with packers on stacked bricks
there was no subfloor drainage and the localised piers were inadequate
the piers’ condition and the internal movement cracking were not related to the flood event.
The insurer also obtained reports from EC, engineer. In its report dated 9 May 2022, EC said:
the dwelling had sustained significant foundation movement since construction (about 100
years ago) and, more recently but prior to the flood, attempts had been made to relevel the
floor frame
as such, and noting level survey results, the floor remained within expected tolerances and
was therefore not presenting any movement consistent with being caused by the flood
the lack of recent cracking within the dwelling also suggested there was no flood damage
there was no evidence indicating that the dwelling has sustained further significant flood
related damage to the footings, piers or dwelling structure.
Determination | Case number: 912215 Page 3 of 7
EC concluded:
During the inspection it was noted that the dwelling is supported on brick piers
packed with loose bricks and other material. The evidence indicates that the
dwelling has a pre-existing foundation movement issue that may remain ongoing.
The dwelling does not have any effective site drainage on the uphill side of the
dwelling, as such moisture can run downhill into the subfloor during rainfall
events. The repeatedly saturated subfloor soils can cause significant foundation
movement over a long-term duration.
EC provided a report dated 2 February 2023, responding to the complainant’s criticisms . EC
said it had concluded the property was founded on reactive clay soils from observation,
excavation and publicly available soil resources. EC confirmed the level survey did not show
the floor level was undesirable, noting the pre-flood relevelling . However, that ‘ is confirmation
that the dwelling does not have poor foundation performance or reactive clay soils ’ .
The insurer says it is therefore not liable for the damage to the piers and stumps. It says that
damage is pre-existing and precluded from cover as the PDS contains general exclusions for
damage caused by long term earth movement and gradual deterioration.
Complainant disagrees
The complainant disagrees with the insurer’s decision that the pier and stump damage is
excluded. In doing so, she notes that the claim event involved significant flooding and
resulted in her home being inundated to about 600mm above the floor level.
The complainant refers to a report by GT, the insurer’s assessor, following an inspection on
12 March 2022. GT said:
the observed damage was consistent with having been caused by the flood event
the property had sustained damage to the footings and piers
the resultant damage from the flood included ‘piers have been washed out’
there were no (prior) property conditions that contributed to the damage
there was ‘no evidence to suppo rt ongoing or long- term issues’.
In addition, the complainant said that EC’s findings were unreliable because EC:
did not undertake soil testing or other geotechnical investigations
was not seen to undertake excavation despite being accompanied during its inspection,
and had not provided supporting photos or details such as the depth of excavation
had not provided full copies of the soil resources it said it had relied upon
had illogically concluded that moisture level changes in the subfloor soil had caused
significant foundation movement over time, but that the most extreme moisture change
(due to the flood) was not causative
had made contradictory statements such as significant foundation movement being
present, yet the level survey showed movement within expected tolerance levels.
On behalf of the complainant, DK submits that:
The fact that stumps may have been 'packed' at some point historically prior to
the insured purchasing the property does not in and of itself prove that the stumps
were not damaged by a catastrophic and major flood event. The historical
'packing' would indicate that if there had been historical movement, this was
Determination | Case number: 912215 Page 4 of 7
actually addressed by the previous property owner and is therefore irrelevant to
the damage that is now showing, following the flood event.
Insurer is not entitled to deny the disputed damage
Based on the information provided, the panel is not satisfied that the insurer has established
that the pier and stump damage is excluded. This is because:
the insurer’s assessor inspected the property within two weeks of the claim event and
concluded that the piers had been washed out by floodwater
the insurer has not adequately explained why seasonal moisture variations caused the
foundational movement but the major flood event which inundated the property did not
EC accepts that the packing of the stumps prior to the flood (and before the complainant
owned the property) successfully relevelled the floor to within a desirable tolerance
there are no images or documents pre-dating the flood depicting the status of the piers.
However, the post-flood images show the piers to be noticeably compromised
there is no information showing the property was not in a liveable state pre-flood due to
foundation movement. It is not in dispute that post-flood the piers need replacement
EC has suggested the presence of erosion runnels and escarpments under the house
suggests inadequate drainage. However, that erosion could readily have been caused by
fast moving floodwater and noting the level of inundation
the panel is not satisfied that EC has provided sufficient support for its conclusion
concerning the soil type. Soil testing results should have been provided, given the
emphasis EC put on the soil type in the context of its overall findings.
The panel is not satisfied that the insurer is entitled to deny coverage for the disputed
damage. The claim related repairs include the piers and stumps.
Further investigations are required before claim may be cash settled
A cash settlement must be based on a reasonable quote for repairs, actionable by a retail
customer. An uplift is then to be applied to the quoted amount to allow for contingencies and
the loss of the lifetime guarantee that applies to insurer approved repairs.
For the complainant to be entitled to a higher cash settlement amount, the panel must be
satisfied that the insurer’s offer does not reasonably reflect the likely retail costs of covered
repairs. This requires one or more of the following:
the SOW the insurer relies on does not adequately encompass the required repairs
the quote the insurer relies on is under priced
the insurer has failed to include a reasonable contingencies uplift.
Since May 2022, and commencing at $82,801.51, the insurer has made several cash
settlement offers for the building damage. On 20 September 2022, the insurer offered the
complainant $233,006.83 as a ‘total settlement figure including the 30% contingency’.
That suggests underlying accepted repair costs of $179,236.02. However, the insurer:
in an email dated 6 January 2023, indicated its ‘final position’ was $177,673.96 plus a 30%
contingency uplift
in its submission to AFCA dated 2 February 2023, calculated fair and reasonable repair
costs at $178,870.67
has provided an ‘estimate’ SOW and ‘liability’ quote dated 21 March 2023 from RP (which
the insurer says it has approved), setting out repair costs totalling $174,189.16.
The complainant has provided a ‘re - stump and renovate’ quote dated 10 November 2022
from local builder GB, totalling $401,523.83.
Determination | Case number: 912215 Page 5 of 7
In its submission to AFCA dated 17 April 2023, the insurer acknowledged that RP’s quote
was not actionable because RP could not warrant repairs due to the pre-existing pier
damage. The insur er’s assessor had reviewed GB’s quot e in light of RP’s quote and
concluded a reasonable payout would be $185,526.25 plus a 20% uplift ($222,631.50).
The complainant has proposed three cash settlement options to resolve the dispute:
GB’s quote plus a 10% uplift - $441,676.21
GB’s quote less t he stumping work, plus a 30% uplift - $423,734.38, or
the parties each obtain engineering reports on the operative cause of the stumping
damage, and a decision is then made on that issue. The parties then obtain detailed
costings from their builders, to be reviewed by an independent building consultant or
quantity surveyor. Once the independent expert reaches a final figure, the insurer is to pay
that amount plus a 30% uplift.
How the insurer reached the $233,006.83 cash settlement offered is not clear. What is clear
is that RP’s SOW does not encompass the required repairs given the panel’s determination
that the pier and stump damage is claim related. It is also apparent that RP’s liability quote
does not reflect retail pricing and is not actionable.
However, the panel is not satisfied that GB’s quote represents a reasonable estimate of claim
related repairs. The reference in its title to ‘renovate’ suggests that the quote may include
items beyond rectifying the flood damage. The panel also notes that pricing for some items
appear inflated, such as $12,402 for insurance and $29,287 for site supervision (ex. GST).
In the circumstances, the panel is satisfied that further investigations must be undertaken to
enable a fair and reasonable cash settlement.
The insurer has previously paid $20,000 in TA costs. The applicable TA sum insured is
$50,000 and is in addition to the building sum insured. It is reasonable to assume that during
claim related repair work, the property will be unliveable, at least for a period.
If the complainant provides notice, the following steps are to be taken:
within 21 days of the notice, the insurer is to retain two building consultants not previously
involved in the claim to prepare SOWs that adequately account for claim related repairs,
and actionable retail quotes based on current prices. To assist them, the consultants are to
be provided with a copy of this determination and the SOWs and quotes the parties have
submitted to AFCA. The consultants are also to provide an estimate of the period in which
the property will be unliveable during the claim related repairs
within 14 days of receiving the building consultants’ SOWs/quotes, the insurer is to provide
a copy of them to the complainant and pay her the higher of the quoted amount plus a
20% contingency uplift, but subject to application of the $500,000 building sum insured
at the same time as the insurer makes the abovementioned payment, the insurer is to cash
settle the complainant’s entitlement to further TA based on the relevant consultant’s
‘unliveability’ estimate multiplied by a comparable weekly rental rate in the complainant’s
area, plus a 20% contingency uplift, but subject to application of the remainder of the
$50,000 TA sum insured.
The panel considers that a 20% uplift is appropriate rather than the 30% the insurer
previously offered, taking into account that the building consultants’ quote will reflect current
retail prices.
Determination | Case number: 912215 Page 6 of 7
2.2 Is non-financial loss compensation payable?
Yes. The insurer’s poor claim handling and dela ys have caused the complainant unnecessary
stress and inconvenience. It is required to pay her $2,000 in non-financial loss compensation.
AFCA can award compensation for poor claim handling
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
Insurer has caused further stress and inconvenience
The complainant says the insurer’s poor claim handling and delays have exacerbated the
stress and inconvenience the claim event caused. She says ‘ the toll this has taken on my
mental health, my work life and my relationships is something that deserves to be
recognized’.
Having carefully reviewed the information provided by the parties, including the insurer’s
claim notes, the panel is satisfied that the insurer should have handled the claim in a more
efficient and emp athetic manner. It’s failure to do so has caused the complainant
unnecessary stress and inconvenience.
The insurer is required to pay the complainant $2,000 in non-financial loss compensation.
2.3 Why is the outcome fair?
The insurer’s cash settlement offer is not fair because it is not based on an SOW that
adequately accounts for all claim related repairs and a quote actionable by a retail customer.
It is fair that the insurer obtains a fresh SOW/quote and pays compensation for stress caused.
Determination | Case number: 912215 Page 7 of 7
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.