Home / IAG / Determination 912209

Determination 912209

Storm damage claim: insurer declined to cover roof repair as deterioration, covered only resultant internal water damage

FirmIAG
Decided2023-03-02
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Complainants' home was damaged by water ingress during a storm; the insurer covered internal damage but not the roof, citing deterioration. AFCA found for the insurer, requiring only that it help obtain a roof quote at complainants' expense and then settle or repair the internal damage.

Roof deterioration, not storm damage, caused water entry and the policy excludes gradual deterioration, wear and tear, so the insurer need not repair the roof and its excess waiver and counselling offer were sufficient compensation.

Issues

Subjects and remedies

health or medicalhome or building damagenatural disasterno remedy

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 912209 Financial firm Insurance Australia Limited Determination | Case number: 912209 Page 1 of 6 Case number: 912209 16 February 2023 1 Determination overview 1.1 Complaint The complainants hold a home buildings and contents insurance policy underwritten by the financial firm (insurer). They say that on 24 February 2022, their home was damaged by a storm. The insurer arranged for ‘make safe’ temporary repairs whilst it reviewed the claim. It concluded the cause of the damage was the poor state of the complainants’ roof . The insurer agreed to cover the resultant water damage only. It requires that the complainants repair or replace the roof before it repairs the resultant internal damage. The complainants have not been able to source suitable building experts to review or repair the roof. They consider the insurer should attend to the damage and say it is taking too long. These delays have upset them, as well as the poor quality of the make safe repairs. They want their home repaired. 1.2 Issues and key findings How should the claim be resolved? The insurer must arrange for a contractor to prepare a quote to repair the complainants’ roof, although the complainants will be responsible for paying for this work. The insurer can then either cash settle them for the internal damage or repair this damage, as detailed in section 2.1 of this determination. Is an award of compensation appropriate? No. The insurer agreed to waive the policy excess ($500) and offered the use of a free counselling service to the complainants. These steps are sufficient compensation for the extent to which the insurer has unreasonably caused the complainants ’ stress. It is not required to provide further compensation. Why is the outcome fair? There is no persuasive evidence the roof sustained any specific storm damage. It would not be fair to require the insurer to cover it. However, assisting the complainants with sourcing a quote to repair the roof damage (at their expense) should help get the repairs completed. There is no need for the insurer to pay additional compensation. 1.3 Determination This determination is in favour of the insurer. The insurer must arrange a contractor to prepare a quote for the repair of the complainants’ roof, although they will be responsible to pay for this. The insurer can then settle the balance of the claim as stipulated in section 2.1 of this determination. The insurer is not required to provide any further compensation for stress it caused. Determination | Case number: 912209 Page 2 of 6 2 Reasons for determination 2.1 How should the claim be resolved? The insurer must arrange for a contractor to prepare a quote to repair the complainants’ roof, although the complainants will be responsible for paying for this work. The insurer can then either cash settle them for the internal damage or repair this damage, as detailed below. Insurer’s experts assessed the storm damage to the home The complai nants’ home is a single storey property built in or about 1980. It was later extended in some areas. The roof has pressed metal tiles. After the complainants lodged a claim for storm damage, the insurer arranged for several experts to inspect the home. Building assessor OS confirmed:  there was damage to the kitchen and bedrooms due to overflowing roof valley gutters  the storeroom and sunroof are extensions of the original home – the apron flashings overflowed wetting the insulation and plasterboard causing cracks and partial collapse  there are maintenance issues which directly caused or contributed to the damage, including leaking and rusting roof tiles. OS suggested the complainants retain a contractor to attend to the roof issues. It otherwise accepts the balance of the claimed damage was storm related. OS prepared a scope of works to address the covered damage for $17,545,57. Plumber TB found many loose fixings on the roof and some perished silicone seals. TB says water entered the roof space through the loose fixings and the roof tile laps. Builder RI confirmed there were ‘at least four leaks’ where w ater entered the home. RI noted there were a ‘large number’ of loose fixings on the roof and the silicone seals for flashings and fixings had deteriorated or perished in several areas. RI says the complainants require ‘a full roof restoration’ and this nee ds to be done before any claim-related repairs commence. The insurer also used other experts to review the claimed damage or attend to make safe and other minor repairs. The complainants have not provided any expert reports. Policy covers listed events, including storm, subject to terms and conditions The insurer’s policy is made up of the Certificate of Insurance (COI) and the Product Disclosure Statement (PDS). There is no dispute the insurer sent these documents to the complainants. The policy covers damage caused by one of the listed events. It does not provide cover for all damage. Amongst these events is cover for storm. This includes rain, thunderstorm, hail, snow, violent wind, cyclone and tornado damage. Insurer is not liable to repair or replace the roof of the home There is no dispute rainwater got into the roof space and damaged parts of the home. The insurer agrees it is liable for the internal damage. I accept water got into the roof space due to the deterioration of the roof over time. Loose fixings, failed silicone seals and deteriorating tiles permitted water to enter through several Determination | Case number: 912209 Page 3 of 6 vulnerable areas. The overflow of the valley gutters and apron flashings also contributed to this. There is no persuasive evidence the roof was specifically damaged by the storm event. Further, the policy confirms it does not cover loss or damage arising from: rust, corrosion, gradual deterioration, depreciation, wear or tear The reason water entered the property is the roof did not fulfil its specific duty to prevent water ingress. This is because certain areas had deteriorated and other areas were ill equipped to deal with the severity of the storm. I accept the insurer is not required to cover the repair or replacement of the roof. It is merely responsible to cover the resultant damage. Insurer to assist the complainants to obtain a quote to repair/replace the roof The issues with the roof need to be addressed before any internal repairs can be conducted. The complainants have been informed of this but have not repaired or replaced the roof damage themselves. I am satisfied the complainants may choose to either:  undertake the roof restoration or replacement work with a contractor of their choice before the insurer attends to internal repair work, or  receive a cash settlement for the estimated costs of the damage. I note the complainants say they have not been able to source a contractor to undertake the repairs. They have also cited vulnerability and health concerns over the delays. Given this, I consider it fair and reasonable that the insurer arranges for a roofer to prepare a quote for the repair/replacement of the roof. This quote needs to be from a contractor prepared to undertake the work for the complainants. They can then choose if they are prepared to proceed with this quote (at their expense) or if they will continue to look for a new repairer. Once a viable repair quote is obtained, I am satisfied the insurer can choose to either:  wait for this work to be undertaken and then conduct the interior repairs, or  cash settle the claim for the interior damage. The OS repair quote for the internal damage does not provide a costs breakdown. To be a valid basis for any settlement, the full quote will need to be shared with the complainants. The insurer will also need to verify OS is prepared to undertake the work for the quote. Should the insurer cash settle the claim, it must also include a 15% contingency uplift. This will compensate the complainants for any minor additional work and the loss of a lifetime guarantee that would otherwise apply to insurer authorised repairs. 2.2 Is an award of compensation appropriate? No. The insurer agreed to waive the policy excess ($500) and offered the use of a free counselling service to the complainants. These steps are sufficient compensation for the extent to which the insurer has unreasonably caused the complainants stress. It is not required to provide further compensation. Determination | Case number: 912209 Page 4 of 6 Complainants unhappy with delays and want the repairs done The complainants are dissatisfied with the delays incurred and the quality of the make safe work conducted by the insurer. They say this left the home with a derelict appearance and they want the roof repaired. They are frustrated by the number of experts who have visited the home, believing this has delayed the claim. They say the insurer did not arrange alternate accommodation or to rehouse their artwork. AFCA can award compensation for non-financial loss Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. Repair delays contributed to by the complainants I acknowledge there have been some delays with the resolution of the claim. This is largely because the insurer is not liable to repair or replace the roof. The complainants report having difficulty sourcing a builder to assist with the issues. This responsibility to repair the roof falls to the complainants. I acknowledge they have been inconvenienced in waiting on expert reports and with the temporary make safe repairs affecting the appearance of the home. However, I accept this is not the insurer’s fault. The insurer cannot attend to the repairs until the complainants address the roof issue. The complainants provided no persuasive evidence any of their contents (including artwork) required special consideration or separate housing due to the event. Insurer has made suitable offers to compensate the complainants The complainants say they are suffering chronic health issues due to delays. They are depressed and unhappy with the insurer’s handling of the matter . By early August 2022, the complainants reported the tarpaulin used for the make safe repairs was unsafe. They complained it was an ‘eyesore’. They are frustrated with the excessive number of contractors used to go through the home and the delay in attending to repairs. They say they were inconvenienced by their neighbours complaining about the home. I acknowledge the complainants have experienced some inconvenience and that they consider the make safe repairs were unsightly. It is not unusual to be inconvenienced in a claim where the home sustains damage which requires assessment and consideration. However, I note the storm event was not the insurer’s fault and it is not responsible for the pre-loss condition of the roof which permitted water into the ceiling area. There is also no persuasive information the complainants required or were entitled to temporary accommodation. The insurer acknowledges its overall handling of the claim should have been better. To compensate the complainants, it waived the policy excess for the claim ($500). It also says it offers a free, confidential counselling service to its customers and offered the complainants the use of this service for four one-hour consultations. It also offered to arrange Determination | Case number: 912209 Page 5 of 6 an inspection by an independent building consultant to review the conclusions it reached about the property. The complainants did not take up these options. I am satisfied the insurer’s approach has been fair. The insurer is not required to provide any additional compensation, beyond the excess waiver and the offer to provide counselling services. Determination | Case number: 912209 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.