Home / IAG / Determination 912179
Determination 912179
Claim declined because subsidence damage did not occur within 72 hours of an escape of liquid event
Summary
The owner of an investment unit claimed for sewer, path and brick wall damage he attributed to a 2016 council water main burst. AFCA found the damage was caused by subsidence not shown to occur within 72 hours of a covered event, so the insurer's decline was upheld.
The policy covers subsidence damage only if it occurs within 72 hours of specified events, and the complainant did not show the damage met this condition.
Issues
- Claim denial primary · not upheld“Policy requires subsidence damage to occur within 72 hours of the escape of liquid; the evidence does not show this, so the policy does not respond.”
- Product terms interpretation secondary · not upheld“The policy provides accidental loss cover but imposes conditions where loss is due to landslide or subsidence.”
Subjects and remedies
home or building damagethird party authorityno remedy
Related
Text of the determination
Determination
Case number 912179
Financial firm Insurance Australia Limited
Determination | Case number: 912179 Page 2 of 6
Case number: 912179 6 April 2023
1 Determination overview
1.1 Complaint
The complainant is an eligible beneficiary under a landlord insurance property underwritten by
the financial firm (insurer) for his investment unit.
He says on or about 6 June 2016, a council water main burst. This caused a large sink hole
to develop immediately adjacent to the complai nant’s property. The council agreed to repair a
damaged brick wall. On or about 8 March 2020, the complainant says he observed a second
sink hole in the street. He says no investigation was undertaken by the council. The
complainant subsequently claimed for damage to his home on 12 March 2020.
The council denied this claim. The complainant later sought cover from the insurer on 19
November 2021. The insurer accepts there was an escape of liquid which contributed to the
damage. However, it denied the claim saying the claimed damage (to the concrete path,
sewer connection and bricks) did not occur within 72 hours of the claimed event.
The complainant believes the policy should respond to the damage.
1.2 Issues and key findings
Is the insurer liable for the claimed loss?
No. The experts agree the claimed damage was caused by subsidence of the soil around the
home. The policy requires that any claim involving subsidence must occur within 72 hours of
certain specific events. The claimed event occurred in 2016 and the exchanged material does
not show this was the case. Therefore, the policy does not respond to the claimed loss.
Why is the outcome fair?
For claims involving subsidence, the evidence must show the damage occurred within 72
hours of the claimed event. The complainant says the event occurred in 2016. The
exchanged material does not show the damage occurred within 72 hours of this. On balance,
it developed more than three years later and likely due to unrelated reasons. It would not be
fair in these circumstances to require the insurer to cover the claimed loss.
1.3 Determination
This determination is in favour of the insurer.
The insurer is not required to take any further action in relation to this claim or the complaint.
Determination | Case number: 912179 Page 3 of 6
2 Reasons for determination
The complainant (VC) is the co-owner of the insured property, the husband and authorised
representative of the insured party (AC). Reference to ‘the complainant’ in this determination
includes both, unless indicated otherwise.
2.1 Is the insurer liable for the claimed loss?
No. The experts agree the claimed damage was caused by subsidence of the soil around the
home. The policy requires that any claim involving subsidence must occur within 72 hours of
certain specific events. The claimed event occurred in 2016 and the exchanged material does
not show this was the case. Therefore, the policy does not respond to the claimed loss.
Complainant says burst council pipe caused damage to unit
The complainant owns a unit, constructed in or about 1982. He has owned the building for
about 30 years. He says the water main burst on 6 June 2016 and caused a sinkhole
adjacent to the rear of the property.
Believing the local council to be responsible, the complainant sought cover from it for damage
to his rear brick fence. After a review, the council agreed to cover the cost to replace the
fence, subject to the complainant agreeing to sign a deed of release for $14,430. The
complainant complied, and the repairs were completed on or about 30 May 2018.
On 8 March 2020, the complainant reported there were new sinkholes at the end of his street.
He raised this again with the council, although he says it declined to investigate further. Four
days later, he reported the claimed damage. He engaged plumber LP to inspect the sewer
line. LP said there was subsidence surrounding the ground along the sewer line.
The complainant says the council refused to cover this damage. After exhausting his efforts to
claim from the council, the complainant lodged a claim with the insurer on 19 November
2021. The claimed damage sought from the insurer includes:
the concrete path adjacent to the unit, which cracked and pulled away from the wall
the sewer connection in the bathroom wall, which was sheared in two, and
the east and west brick walls of the unit, which cracked due to the settlement.
The complainant believes the damage was caused by the burst water main on 6 June 2016.
He says because of this, water began flowing along the stormwater easement running east-
west along the north side of the property. This caused ground movement and settlement,
which in turn led to the damage to the sewer line, concrete path and brick walls.
Experts confirm there is damage to the home
The complainant provided a report from plumber LP dated 24 March 2020. LP inspected the
sewer pipes with CCTV and found a broken junction on the toilet line. LP wrote that it
believed the:
broken junction had sheared due to pressure being induced by ground movement.
The gap in the junction at the shear location appears similar to the gap distance in
the footpath movement away from the brick wall. We believe this break could only
have been caused by surrounding ground subsidence which appears to have
affected the entire length of sewer line and will most likely continue to cause
Determination | Case number: 912179 Page 4 of 6
further stress and damage to pipework and fittings, possibly also including but not
limited to kitchen and laundry branch lines.
The insurer appointed structural engineer CE to review the damage. CE found a gap between
the home and the concrete path along the northern elevation (adjacent to the easement on
the property). CE says water leaks from the stormwater line was not the cause of this
damage. A similar gap is present between the concrete path and the western wall, which is
not close to the stormwater line.
CE says the claimed damage is not related to the council drain. It says the concrete slab
around the perimeter of the home has no caulking. The area is vulnerable to drying and
wetting. CE says the cracks in the bricks are from brick expansion. This occurs due to the
bricks retaining moisture and through the absence of vertical control joints. CE concluded:
the concrete path moved due to inadequate caulking and sealing of the join, and
inadequate compaction of the subgrade
the brick cracking is due to expansion of the bricks due to a lack of vertical control joints.
The council reportedly had experts review and submit reports in relation to the damage from
the 2016 event. The complainant cited excerpts from these reports, however no copy of the
documents was made available for AFCA or the insurer to review. In the circumstances, I
have given no weight to this information as it would not be fair to rely on excerpts alone.
Policy covers accidental damage subject to terms and conditions
The insurer’s policy is made up of the Renewal Schedule and the Product Disclosure
Statement (PDS). There is no dispute the insurer sent these documents to the complainant.
The 2019 PDS (applicable at the time of the claim being lodged) provides accidental damage
cover. It says:
We will cover your buildings and contents for any accidental damage or
accidental loss including that caused by:
landslide or subsidence but only if it occurs within 72 hours after one of the
following:
o storm, flood, rainwater or wind
o earthquake
o liquid that escapes from a fixed pipe or something attached to a
pipe, fixed gutter, fixed tank or a drain.
This cover also applies to gates, fences or retaining walls that are attached to,
and are part of, the structure of the buildings .
Noting the complainant seeks to claim for an event he says occurred in 2016, I obtained a
copy of the PDS applicable at this time for comparison (2014 PDS). This document provides
the same cover, although it is expanded to include an ‘explosion’ amongst the events it
considers for landslide coverage.
The policy provides accidental loss or damage cover but imposes conditions where such a
loss is due to landslide or subsidence. The parties accept the damage was due to
subsidence. Therefore, I am satisfied the evidence must show the loss occurred within 72
hours of the claimed event to be covered.
Determination | Case number: 912179 Page 5 of 6
The complainant says the claimed damage was caused by the escape of liquid in 2016. To be
covered, I must be satisfied this damage occurred within 72 hours of the escape of liquid.
No mention was made of this damage at the time the complainant sought cover from the
council for his damaged fence. If any sign of the claimed damage was present at that time, I
expect a claim would have been made. The complainant signed a release when accepting
settlement from the council and I consider it is unlikely he would have done this if he had
doubts about the extent of damage.
There is nothing persuasive in the exchanged material to show the claimed damage occurred
in or about 2016, let alone within three days of the escape of liquid event.
The complainant notes he and his wife do not reside in the units. They only become aware of
damage when it was reported. I acknowledge this, however there was a considerable period
between the original report of damage (2016) and the discovery of the claimed damage
(2020).
I also considered whether the claimed loss might have occurred within three days of 8 March
2020 (when the complainant observed the second sink hole). There is no evidence provided
to show this damage occurred within that time frame due to any of the specific events the
insurer covers. As this is required for the complainant to be covered for subsidence damage, I
am not satisfied the policy responds.
Insurer is not required to cover the claimed loss
Whilst the policy covers accidental loss or damage, for claims involving landslide or
subsidence it must be shown this occurred within 72 hours of certain events. Here, the
relevant event was liquid that escaped from a fixed pipe in 2016.
For the reasons stated above, I do not accept the claimed damage occurred in 2016. The
available evidence says it manifested in or about 2020, nearly four years after the event.
Therefore, even if I accept the loss was due to the escape of liquid, I do not accept the
claimed damage occurred within 72 hours.
The insurer says the damage to the sewerage pipe and the movement experienced at the
complainant’s property has been occurring over ‘a period of years’.
The complainant reported secondary sink holes developing in 2020, although the complainant
does not suggest this caused the claimed damage. Even if he did, he has not shown how this
claimed damage developed from the 2020 event. There was no evidence of a secondary
escape of liquid which accompanied the 2020 event and no reason to believe this caused the
claimed damage.
Given this, I am satisfied the complainant is unable to discharge his onus to show the policy
responds to the claimed loss.
The complainant also submits the council should be liable for the loss but says it relies on the
signed deed of release as a reason to not pay for the damage. AFCA has no jurisdiction in
relation to the council and I cannot comment on whether it is liable or not. However, I consider
this has no bearing on the insurer’s liability. The claim before me is a matter of whether the
insurer is liable for the loss. I am satisfied the policy does not respond.
Determination | Case number: 912179 Page 6 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.