Insurer's liability for compliance costs for storm-damaged gutter and handling of the claims
Text of the determination
Determination
Case number 912143
Financial firm AAI Limited
Determination | Case number: 912143 Page 1 of 10
Case number: 912143 5 October 2023
1 Determination overview
1.1 Complaint
The complainant is represented by his broker (HB). For simplicity, I will refer to the
complainant and HB as the ‘complainant’.
The complainant lodged two claims with the financial firm (insurer) under his home insurance
policy. This is for the damage sustained to his home following two storm events. The insurer
accepted the claim; however, parties dispute the extent of the insurer’s liability under the
policy. Further, the complainant is dissatisfied with the insurer’s handling of the claims.
1.2 Issues and key findings
Is the insurer liable for the additional compliance costs?
Yes, this is because:
on balance, the gutter was partially damaged by hail and rain
the policy provides cover for compliance costs with the current building regulations for the
damaged part of the property
the insurer has not shown the property did not comply with the relevant building
regulations at the time of its construction.
How should the claim be settled?
The insurer is required to engage a roof plumber to establish the extent of the compliance
work required to the damaged portion of the gutter. The insurer is then required to settle the
claim as outlined in section 2.2 of the determination.
Is the insurer liable for compensation?
The insurer handled the claim poorly. The insurer is required to pay the complainant $2,000
compensation.
Why is the outcome fair?
The expert evidence shows the property is not compliant with the current building code. The
policy covers the reasonable costs in making the damaged part of the property compliant with
the current regulations. Given the policy is the contractual agreement, parties are bound by its
terms and conditions.
1.3 Determination
This determination is in favour of the complainant.
Within 14 days of receiving notification the complainant accepts this determination, the
insurer is required to:
settle the claim as outlined in section 2.2 of the determination
pay the complainant $2,000 compensation.
Determination | Case number: 912143 Page 2 of 10
Determination | Case number: 912143 Page 3 of 10
2 Reasons for determination
2.1 Is the insurer liable for the additional compliance costs?
Yes, this is because:
on balance, the gutter was partially damaged by hail and rain
the policy provides cover for compliance costs with the current building regulations for the
damaged part of the property
the insurer has not shown the property did not comply with the relevant building
regulations at the time of its construction.
Complainant says the gutters need to be replaced and the fall reinstated
The following relevant facts are not in dispute:
the property has been subject to two storm events
the complainant has established a claimable loss for both events
the property sustained damage to different areas, including hail damage.
Amongst other things, the complainant says:
the insurer has incorrectly calculated the roof’s catchment area
the gutters have been sagging since the events
the overflow of the rain water since has been substantial
during one the storm events there was hail and ice blocking the valleys and gutters.
The complainant provided a video which clearly shows the inundation of rain under the
pergola during heavy rain.
The complainant’s plumber (PG) says the overflowing gutter is because it is sagging in the
middle, allowing water to pool and not escape fast enough.
PG says:
all gutters to the pergola need resetting to ensure adequate fall to the downpipes
the heavy rain and hail has caused the gutters to sag.
The insurer says the gutters are insufficient for the roof catchment area
In addressing the cause of the rain overflow, t he insurer’s builder (CB) says the two
downpipes to the rear of the property were enough to cope with the volume of water when the
house was initially constructed. However, CB says the addition of the pergola’s roof
(approximately 58 square metres) made these down pipes inadequate. CB recommended the
installation of additional downpipes.
The insurer’s builder (G R) says due to the insufficient fall of the gutter, water is backing and
overflowing at the back of the gutter. GR says the fall cannot be increased due to the
pergola’s brackets extending through the fascia. GR recommended the installation of a box
gutter to prevent the overflow. GR says repairs cannot be guaranteed as water is ponding in
the gutter and the fall cannot be increased.
The insurer’s internal building coordinator (B) has reviewed GR and PG reports. B says , as
per the Australian Building Standards AS/NZS 3500.3:2015 (revised from 2003) the guttering
size is inadequate.
Determination | Case number: 912143 Page 4 of 10
B explained that the gutter size is calculated on the roof catchment area and average rainfall.
B says when the pergola was installed, the roof area was increased, and the gutters should
have been upgraded to suit additional water catchment for the surrounding roof.
B says the current gutter does not comply with the current building code. I note PG did not
provide any comments or assessment on the extent of the roof catchment area or any
required alterations to the gutter.
The insurer says the complainant is required to install additional downpipes to mitigate further
water damage from heavy rain.
No evidence gutters did not comply with relevant building code at construction
It is not in dispute the property was constructed in 2007. There is no information to establish
when the pergola was built. It is unknown whether it was constructed along with the dwelling
or built at a later date. It is not in dispute that the complainant bought the property with the
pergola attached. The insurer says at the time of the construction of the pergola, the gutters
were undersized. I disagree.
Firstly, the building code that B referenced is not the building code that was applicable in
2007, being the time of the building construction. The code the insurer referred to, is the
revised building code which came into effect in 2015.
B says to obtain the 2003 building standards, being the applicable building code, the insurer
would have incurred additional costs. The code B provided is a revised code and it is unclear
which parts of the code are updated and which parts remained the same as the 2003 building
code. The insurer says the 2003 code is the same as the 2015 code. However, the insurer
has not provided any evidence to substantiate this assertion.
I have carefully considered the exchanged information. I am not satisfied the insurer has
shown that the addition of the pergola and subsequently increasing the roof catchment area
was not compliant with the applicable building code at the time of its construction and/or
addition.
I accept the current gutter is not managing the water flow in the event of heavy rain. There is
no dispute there is internal water damage because of the rainwater backflow.
Relevantly, parties dispute the extent of the roof catchment area. Parties have provided
different diagrams and measurements of the catchment area. In my opinion, I do not need to
assess the extent of the roof catchment area to conclude whether the gutter is currently
compliant or not. I accept the gutter, including the damaged parts, do not comply with the
current building code and this is consistent with CB’s and GR’s findings.
Whilst the complainant provided his measurements and calculations for the roof catchment
area, I am not satisfied he has shown that his calculation is consistent with the current
building code.
On balance, I accept additional work is required to the roof plumbing to make it compliant with
the current building code and to mitigate any further loss.
Insurer is liable for the compliance costs of the damaged sections of the gutter
The policy states that when there is a claim for loss or damage to the home, additional covers
are applicable including ‘Other repair/rebuilding costs’ .
Under this section, the policy states:
Determination | Case number: 912143 Page 5 of 10
When you are covered for the costs of rebuilding or repairing damaged parts of
your home, we will pay the reasonable and necessary costs:
• of any temporary work required to make the damaged or destroyed home and
insured address safe;
• for the services of professionals, such as architects or surveyors, to repair or
rebuild at the insured address;
• making the home comply wi th building regulations and laws. We only pay these
costs if the building components complied with building regulations and laws
when the home was originally built or when construction, repairs, renovations or
alterations were undertaken.
Limit
The most we will pay for any one event is 10% of your home sum insured.
PG says the gutter is sagging because of the hail and the heavy rain. The insurer has not
provided any evidence to refute this assertion. Conversely , GR’s scope of work covers the
supply and installation of the damaged gutter to match existing.
There is no dispute:
the policy covers loss or damage caused by a storm
the sagging occurred during the subject storm.
The insurer says the non-compliance of the gutter is a defect which the policy clearly
excludes. I disagree. In the absence of persuasive evidence to show the property was not
compliant with the relevant building code at the time of its construction, I am not satisfied the
current non-compliance of the gutter is a defect for the purpose of the policy.
The policy clearly covers additional compliance costs for the damaged part of the gutter. In
other words, the insurer is required to meet any additional costs associated with the
compliance of the damaged section of the gutter. In saying that, I am not satisfied the insurer
is liable for the compliance costs of the undamaged sections of the gutters (if any).
2.2 How should the claim be settled?
The insurer is required to engage a roof plumber to establish the extent of the compliance
work required to the damaged portion of the gutter. The insurer is then required to settle the
claim as outlined in section 2.2 of the determination.
Insurer must exercise its discretion under the policy fairly
The insurer’s policy provides it with the discretion to either repair or cash settle its liability.
The insurer is expected to exercise its discretion under the policy fairly.
The insurer says it is unable to warrant the repairs due to the gutter’s inadequate fall.
Accordingly, the insurer seeks to cash settle its liability rather than undertake the repairs.
In the event the insurer’s builder is unable to complete the repairs, the policy states:
Determination | Case number: 912143 Page 6 of 10
When a me mber of our supplier network is unable to complete the repair or
rebuild
When your claim for loss or damage to the home is covered and a member of our
supplier network is unable to complete the repair or rebuild, we will ask you to
engage a builder to provide a scope of works and provide a quote on the cost to
repair or rebuild the home on a ‘new for old’ basis .
Once the scope of works and quote is provided to us, we will arrange for it to be
assessed. This will involve reviewing the quote to determine it is appropriate and
reasonable for the scope of works. This includes a consideration of the
appropriateness of materials, repair method, labour and material costs and overall
cost effectiveness.
If the quote is appropriate and reasonable for the scope of works, we will then pay
you the assessed amount. If it is not, the quote may be adjusted. This may
include adjusting the scope of works or the quote. We will then pay you the
adjusted amount of the quote.
Amongst other things, the complainant says:
the insurer is seeking to cash settle the claim due to the complexity of the claim
the insurer’s experts are builde rs and not plumbers and lack the correct expertise.
The insurer is required to engage a roof plumber
All experts engaged by the parties concluded that further plumbing work is required to the
gutters to ensure its compliance with the current building standards and to mitigate further
losses. This is not in dispute.
In saying that, I note the different experts recommended different measures. PG
recommended the resetting of the gutters to ensure adequate fall, whereas CB and GR
recommended respectively installing two down pipes or a box gutter. Further, it is unclear
whether additional plumbing work is required to the entire gutter or only the damaged section.
As outlined above, I accept the insurer is liable for the additional plumbing costs of the
damaged section of the gutter for it to comply with the current building standards. I am not
satisfied the insurer is liable for the resetting of the remainder of the gutter or meeting the
compliance costs for the undamaged sections of the gutter.
I have carefully reviewed the exchanged information. I consider it is fair and reasonable the
insurer engages a roof plumber to assess the extent of the additional plumbing work required
to the gutter. For clarity, this roof plumber is only required to establish the nature of the
additional plumbing work required to make the damaged section of the gutter compliant.
Insurer is entitled to cash settle the gutter repairs including compliance cost
I acknowledge the insurer ’s argument regarding its inability to warrant the repairs because of
the non-compliance of the gutter. Further, PG says all gutters to the pergola will need to be
reset to ensure adequate fall. GR’s scope of work allows for the replacement of 12 lineal
meters of the gutter.
Determination | Case number: 912143 Page 7 of 10
It is unclear whether the entire gutter on the property is non-compliant or the gutter only
servicing the pergola. Further, I note the policy states that the insurer will ‘pay’ the compliance
costs rather than undertake the compliance repairs. I consider it is fair that the insurer cash
settles the complainant for the repair cost of the gutter damage.
Within 14 days of receiving notification the complainant accepts this determination, the
insurer is required to engage a roof plumber to assess the extent of the additional plumbing
work required for the damaged section of the gutter.
Within 14 days of his/her assessment, the roof plumber is required to provide his/her report to
parties outlining the scope of works for the repairs of the damaged section of the gutter,
including the additional compliance plumbing work for this section.
The roof plumber’s scope of works and quote should be actionable i.e. the roof plumber is
willing to undertake these repairs if engaged privately by the complainant.
The insurer is then required to cash settle the complainant the repair cost of the storm
damaged gutter including the additional compliance plumbing work plus a 15% contingency
for the transfer of risk.
Insurer is willing to complete repairs once guttering is upgraded and compliant
Generally, when the insurer repairs the home, it guarantees the quality of the workmanship
for the lifetime of the home. This is consistent with the policy wording.
It must also be recognised that in cash settling the claim, the complainant has given up the
lifetime guarantee provided under the insurer’s policy. Further, a cash settlement transfers all
the risk from the insurer to the complainant of any unforeseen damage and any additional
work required once repairs commence.
The insurer says it can repair the resultant damage as it would be able to warrant the repairs
once the complainant has addressed the roof plumbing issues. Alternatively, the insurer says
it can cash settle its liability. I accept this is a reasonable position and consistent with the
policy.
Subject to the complainant providing evidence of the completion of the additional compliance
plumbing work outlined by the roof plumber, the insurer can commence the repairs of the
resultant damage.
Should the complainant seek a cash settlement, then the insurer is required to factor in a 15%
contingency for the transfer of risk. The exchanged information shows the complainant was
willing to accept a cash settlement given the builder can complete the repairs at the same
time. Whilst I acknowledge the complainant ’s argument, I accept an insurer cannot compel a
builder to undertake any repairs once it cash settles its liability. In saying that, the insurer is
required to ensure that the quote on which it bases its liability is actionable and the cash
settlement is adequate to cover the storm damage.
I consider it is fair in all circumstances that the insurer obtains an updated scope of work for
the resultant damage given the passage of time. I accept GR’s scope of work is not an
accurate reflection of the current mark et rates. I acknowledge the complainant’s concerns
regarding GR and CB. However, there is no persuasive evidence to show that either GR or
CB have erred in their assessments or are not qualified to repair the damage. The
complainant can engage his own builders to finalise the repairs should he wish.
Determination | Case number: 912143 Page 8 of 10
The complainant says there are make -safe repairs required to the property which the insurer
failed to attend to. I accept the insurer is required to proactively address the complainant ’ s
concerns regarding any make safe repairs to mitigate further loss or damage to the property.
2.3 Is the insurer liable for compensation?
The insurer handled the claim poorly. The insurer is required to pay the complainant $2,000
compensation.
AFCA can award compensation for non-financial loss
AFCA will award compensation for non-financial loss (capped at $5,400) if there has been an
unusual degree or extent of physical inconvenience, time taken to resolve a complaint or
interference with the complainant’s expectation of enjoyment o r peace of mind.
AFCA takes a conservative approach to awarding compensation. We do not award
compensation because the complainant has suffered some inconvenience and delays. AFCA
expects complainants to be moderately robust and to bear the normal degree of
inconvenience experienced when a problem occurs and to take reasonable steps to manage
the situation.
The complainant is dissatisfied with the way the insurer handled the claim. Amongst other
things, the complainant says:
he had multiple case managers handling his claim
some of the interactions were challenging
the rain affecting the outdoor area has impacted his family
the insurer unreasonably delayed the repairs of the damage that is not in dispute
the insurer provided inconsistent information regarding the number of the applicable policy
excesses.
The complainant is entitled to $2,000 compensation
The insurer does not dispute it has caused delays in the claim’s handling. Relevantly, the
insurer apologises for the poor service it has provided the complainant.
The exchanged evidence shows the complainant has pro- actively followed up the claim’s
progress and attempted to work with the insurer towards a resolution. I have carefully
considered the claim notes and I acknowledge that most of the contact has been initiated by
the complainant or his wife.
I accept the insurer has not provided any plausible explanation as to the reasons it did not
complete the repairs of the undisputed damage, including urgent electrical repairs.
Further, the claim notes show the complainant questioned the insurer’s representatives
regarding the applicable building code and the insurer failed to provide timely responses. It is
evident the complainant has raised several questions to the insurer and the insurer failed to
provide a response.
The available information shows significant delays in the progress of the claims. I accept the
insurer did not proactively manage the progress of the claims from May to November 2022.
The insurer is required to pay the complainant $2,000 in compensation.
Determination | Case number: 912143 Page 9 of 10
2.4 Why is the outcome fair?
The expert evidence shows the property is not compliant with the current building code. The
policy covers the reasonable costs in making the damaged part of the property compliant with
the current regulations. Given the policy is the contractual agreement, parties are bound by its
terms and conditions.
Determination | Case number: 912143 Page 10 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information. If there are conflicting recollections and these are evenly weighted, we may find
that a claim cannot be established.