Determination
Case number 912046
Financial firm Hollard Insurance Partners Limited
Case number: 912046 13 November 2023
1 Determination overview
1.1 Complaint
The complainants hold a home building and contents policy (policy) with the financial firm
(insurer). A claim was lodged for significant flood damage to the insured property in July
2022.
The insurer accepted the claim. However, it limited its liability to damage it assessed to be
consistent with the flooding of the insured property and offered to cash settle the
complainants under the claim. The complainants are dissatisfied with the cash settlement
amount and the insurer’s handling of the claim .
The complainants say t he insurer’s settlement amount is insufficient to repair the damage
caused by the event. Further, the complainants are seeking a higher settlement for additional
temporary accommodation, contents storage, contents damage and believe they are entitled
to loss of rent.
1.2 Issues and key findings
Should the insurer increase its cash settlement for building damage?
Yes. The insurer should make further contributions towards the building damage. This is
because the insurer’s cash settlement does not fairly account for costs to repair/remediate the
ducted air-conditioning unit, the mould in the roof cavity and the damaged brick pavers.
Is the insurer liable to cover additional alternative accommodation costs?
No. The insurer is entitled to limit its liability to 52 weeks of accommodation in accordance
with the policy terms and conditions, which it has covered under the claim.
Is the insurer required to cover loss of rent?
No. The complainants are not covered for loss of rent under the policy. It would be unfair to
require the insurer to pay the complainants for a loss not covered under the policy.
Should the insurer increase cover for storage costs?
No. The insurer has paid the complainants their maximum policy entitlement towards storage
costs and is not required to increase its settlement in this regard.
Is the insurer liable to increase its settlement for contents damage?
No. The complainants’ have been paid their full entitlement of $125,000 less applicable
excess for loss or damage to their contents from the flood event. The insurer is not obliged to
make any further payment to the complainants towards the contents loss or damage.
Determination | Case number: 912046 Page 2 of 10
Are the complainants entitled to non-financial loss compensation?
Yes. The insurer is to arrange a payment of $1,000 in non-financial loss compensation to the
complainants, this being in addition to the $2,000 already offered/paid by the insurer in line
with the AFCA Rules.
Why is the outcome fair?
The outcome is fair because the insurer is entitled to limit its liability under the claim based on
the policy provisions. It is fair that the insurer be required to increase its final claim settlement
to include works which do not form part of the scope of works it has relied on to assess its
liability under the claim. Further, it is fair that the insurer pays the complainants compensation
for non-financial loss in the circumstances.
1.3 Determination
This determination is in favour of the complainants.
In addition to the loss or damage already accepted by the insurer, within 14 days of receiving
notice of the complainants’ acc eptance of this determination, the insurer is to:
Increase its claim settlement by a further $89,047 to account for:
- $18,238 for costs to replace the ducted air-conditioning unit
- $6,105 for costs to remediate mould in the roof cavity
- $49,683 to pull, clean and relay the brick pavers
- a 20% increase to the above amounts to allow for contingencies and the transfer of
risk in arranging the works
arrange payment of $1,000 in non-financial loss compensation (this being in addition to the
$2,000 previously paid/offered to the complainants by the insurer).
Determination | Case number: 912046 Page 3 of 10
2 Reasons for determination
The panel notes at the time the complainants brought this complaint to AFCA there were
several issues in dispute between the parties. However, since then and with the assistance of
AFCA a number of these issues have been resolved between the parties including but not
limited to the damaged swimming pool, make safe expenses and mould remediation to both
buildings situated on the premises.
In providing this determination, the panel has limited consideration to those issues that are
considered directly relevant to the outcome and which remain in dispute between the parties.
The panel has considered all the information provided to AFCA by the parties for
consideration. The panel is satisfied all the information has been exchanged with the parties,
each having had the opportunity to respond and provide information in support of their
positions.
2.1 Should the insurer increase its cash settlement for building
damage?
Yes. The insurer should make further contributions towards the building damage. This is
because the insurer’s cash settlement does not fairly account for costs to repair/remediate the
ducted air-conditioning unit, the mould in the roof cavity and the damaged brick pavers.
Parties disagree with the scope of works and suitability of the settlement offer
The insurer tendered two quotes from its repairers in the amount of $270,231.81 and
$390,761 for repairs to the building based on the scope of works (SOW) prepared by
consultants ‘IC’ . Having considered all the available information, the panel is satisfied IC’s
SOW provide a fair representation of the flood damage to the insured buildings, with a few
exceptions which have been considered in this determination.
The panel notes the insurer originally sought to settle its liability for the building damage on
the lower of these quotes, then on an average of these two quotes and finally on the higher of
the quotes from ‘SR’ ($390,761) plus an uplift bring it s offer to $468,913.20. The insurer has
also accepted to cover the damaged pool ($103,110) and the make safe and mould
remediation expenses ($198,271.38) claimed by the complainants.
The complainants are dissatisfied with the insurer’s offer and believe the insurer should be
required to assess its liability for the building damage based on a quote from consultants ‘A’
based on the SOW from IC including variations proposed by A. In the complainants ’ opinion,
A’s quote accounts for all necessary works and required variations to IC ’s SOW and which
totals $510,619.44.
Insurer’s quote to be used as fair basis for settlement of building damage
The panel notes that A’s quote including variations ($510,619.44) incorporates IC ’s SOW but
it also includes works which have already been accepted and cash settled by the insurer
under its offer to pay the complainants an $198,271.38. This cash settlement covers
remediation and make safe works as set out below:
the hygienist assessment fee $3,000
F’s quote for mould r emedial works on level 1 of both dwellings $35,030.05
H’s quote for plumbing works $4,012.80
AY’s quote for mould remedial works for main house and granny flat $105,242.50
Determination | Case number: 912046 Page 4 of 10
AC’s quote for electrical works $31,981.90
skip bin hire costs $8,236
pool remediation $7,386.50
clean-up costs $3,381.63.
The panel has also reviewed the second building repair quote provided by the complainants
from consultants ‘S’ totalling over $1,350,000. The panel believes this quote is excessive,
lacks adequate details and includes works such as the pool damage which has already been
accepted and cash settled separately by the insurer. The panel notes the complainants have
also subsequently advised this is not the quote they expect the insurer to consider for the
purpose of settling their claim.
The panel has considered the repairs and associated additions to A’s quote relating to the
tiling and cobblestone driveway referred to in ‘T’s report dated 10 October 2022. The panel is
not satisfied this information shows, on balance, the flood event caused any damage to these
areas. T ’s findings in this regard are inconclusive. Further, the panel is satisfied SR’s quote
includes a provisional sum for these works, which the panel considers fair and reasonable in
the circumstances.
In the absence of persuasive information to the contrary, the panel believes the two SOW ’s
and associated quotes from A and S are excessive, include costs already settled under the
claim and it would not be reasonable to require the insurer to accept these quotes as a basis
to settle the claim.
Overall the panel is satisfied SR’s quote is the most persuasive and provides a fair
assessment and costings for the building damage to be accepted under the claim. The panel
also accepts the insurer’s proposed 20% uplift of SR’s quote to allow for contingencies and
the transfer of risk in arranging the repairs is reasonable in the circumstances. However, the
panel finds it is fair that the insurer increases its liability under the claim to include the below
discussed repairs/costs in addition to its final claim settlement offer.
Insurer to increase its liability under the policy
Having considered all the information, the panel finds it is fair that the insurer increases its
claim settlement to include replacement of the air-conditioning unit ($18,238) based on
consultant ‘O’s quote , as well as, the cost to remediate the mould in the roof cavity ($6,105)
based on a quote from consultants ‘ TE ’. In the panel’s view, these costs are substantiated
with persuasive supporting information from the complainants.
The complainants say the herringbone brick pavers were professionally installed around three
years before the flood event. Further, that the insurer’s appointed loss adjustor and service
provider (IC) agreed on site (16 September 2022) that the pavers required to be pulled up,
cleaned and relayed.
The insurer has not refuted this by way of expert evidence or any contrary comment to
challenge the complainants’ position. On balance, the panel accepts the complainants ’ view
given the nature and the extent of the claimed event. The complainants have provided a
quote from their preferred consultant ‘ M ’ for these works in the amount of $49,863. It is fair
the insurer includes this cost in its settlement.
The panel is satisfie d it is fair and consistent with the insurer’s policy obligations that the
insurer increases its final cash settlement amount by a further $89,047 to account for:
- $18,238 for costs to replace the ducted air-conditioning unit
- $6,105 for costs to remediate mould in the roof cavity
Determination | Case number: 912046 Page 5 of 10
- $49,683 to pull, clean and relay the brick pavers
- a 20% increase to the above amounts to allow for contingencies and the transfer of
risk in arranging the works.
2.2 Is the insurer liable to cover additional alternative
accommodation costs?
No. The insurer is entitled to limit its liability to 52 weeks of alternative accommodation in
accordance with the policy terms and conditions.
Insurer has paid alternative accommodation costs
The policy includes an automatic additional benefit covering alternative accommodation costs
in certain circumstances, for up to a maximum of 52 weeks.
There is no dispute the insurer has covered the complainants for alternative accommodation
up to 10 July 2023, which represents 52 weeks of cover.
Complainants say the insurer should cover an additional 12 weeks
The complainants say the insurer should cover additional alternative accommodation, this is
because it will require approximately eight to nine months for the repairs. The complainants
say the insurer caused unnecessary delays in managing the claim and so should be required
to cover alternative accommodation in excess of the policy limit.
Considering the repair period and the circumstances, the complainants ask the insurer to
cover an additional 12 weeks.
Insurer is entitled to limit its liability in line with the policy provisions
There is no dispute the policy limits the complainants ’ entitlements to 52 weeks of alternative
accommodation or that the insurer has paid the complainants an amount equal to 52 weeks
of accommodation.
The panel acknowledges the complainants’ concerns regarding the insurer’s management of
the claim. However, the panel is not satisfied it would be fair to require the insurer to pay
more than its policy obligations in the circumstances. The panel is satisfied the available
information supports a view that both parties have contributed to the delays experienced
under the claim. Also, that the insurer’s management of the claim has not been so poor that it
would be reasonable to require it to cover costs that exceed its policy obligations.
Accordingly, the insurer is not required to make further payment towards alternative
accommodation.
2.3 Is the insurer required to cover loss of rent?
No. The policy does not include cover for loss of rent and it would be unfair to require the
insurer to pay the complainants for a loss not covered under the policy
The complainants did not choose policy with loss of rent cover
The insurer offers several different types of contracts of insurance allowing customers to
choose which option best suits their requirements. The complainants did not choose to
purchase the option that includes cover for loss of rent. Further, the complainants never
Determination | Case number: 912046 Page 6 of 10
informed the insurer that they were renting out part of the insured property at any time before
the flood event and associated damaged to the insured buildings.
Insurer is not liable to cover the loss of rent
The complainants accept the policy may not cover rental loss, but believe the insurer is liable
for the loss because of its management of their claim. In resolution, the complainants ask the
insurer to cover the rental loss between claim lodgement (2 July 2022) until the claim was
partially settled on 6 January 2023.
The complainants say they suffered rental loss because of the insurer’s delayed claim
process. The evidence available demonstrates the parties did not agree to the scope of works
and both parties engaged several service providers to assess and quantify the loss up until at
least January 2023.
The policy is clear in the panel’s view and does not cover rental loss. The panel
acknowledges the complainants’ concerns regarding the insurer’s management of the claim.
However, the panel is not satisfied it would be fair in the circumstances to require the insurer
to indemnify the complainants for a loss they chose not insure when arranging the policy.
Further, the available information supports a view that both parties have contributed to the
delays experienced under the claim. The insurer’s management of the claim has not been so
poor that it would be reasonable to require it to cover loss which is not covered under the
policy.
Accordingly, the insurer is entitled to decline cover for the claimed loss of rent in the
circumstances.
2.4 Should the insurer increase cover for the storage costs?
No. The insurer has paid the complainants their maximum policy entitlement towards storage
costs and is not required to increase its settlement in this regard.
Insurer has paid the storage costs up to the policy limit
The complainants are claiming the costs incurred ($13,757.68) to pack and store the contents
(that were undamaged in the event). The complainants say the insurer informed them they
were covered for 120 days.
The insurer accepts the policy covers the costs to store contents up to 120 days in a
commercially operated storage facility, which the insurer maintains it has already cash settled
the complainants.
Insurer not required to cover more than covered under the policy
There is no dispute the insurer has paid the complainants $3,428.57 at $200 per week
towards storage costs. The panel is satisfied this represents 120 days of storage cover.
The available information shows the complainants incurred a cost of $2,344 for storing the
contents in a storage facility, before moving their contents to their rental property. The
complainants also incurred costs to pack and move the contents for an approximate amount
of $11,000.
The panel is not of the opinion that the insurer is liable for the expenses incurred in the
packing and moving of the contents under the policy, its liability being limited to storage costs.
Determination | Case number: 912046 Page 7 of 10
Given the insurer has paid the complainants their maximum policy entitlement for storage
costs, the panel is satisfied the insurer is not required to make any further payment in this
regard.
2.5 Is the insurer liable to increase settlement for the contents?
No. The complainants’ have been paid their full entitlement of $125,000 less applicable
excess for loss or damage to their contents from the flood event. The insurer is not obliged to
make any further payment to the complainants towards the contents loss or damage.
Information relevant to considering the complainants’ contents claim
The insurer assessed the complainants’ claim for loss or damage to their contents from the
flood event as being a total loss. Given this, the insurer has paid the complainants their full
contents sum insured of $100,000 plus a further 25% as allowed under the policy.
The complainants say some of their contents were not damaged by the event and were
stored upstairs (of the dwelling). However, that further contents damage has occurred due to
the mould developing and spreading through the insured buildings.
In the complainants’ opi nion, the insurer is liable for the mould infestation and therefore
damage to their contents. The complainants say the insurer agreed to renew the policy on 9
August 2022 which includes $100,000 for contents cover.
The complainants have also lodged a new claim for damage to the contents under the
renewed policy. The insurer has declined this claim on the grounds the complainants have
been paid their maximum entitlement for contents damage arising from the flood event.
Cover under the policy is subject to conditions, limitations and exclusions
The complainants bear the onus to show it is more likely than not that the loss or damage
claimed is covered under the policy. There is no dispute the complainants’ elected to cover
their contents for a sum insured of $100,000 under the policy. It is also not in dispute the
insurer has accepted the claim and paid the complainants their maximum entitlement under
the policy for contents loss or damage from the flood event.
The panel accepts the policy limits the compla inants’ entitlement to the elected sum insured
(plus 25%) for contents damage from any single event covered under the policy. This means
the complainants ’ maximum entitlement for cover relating to their contents from the flood
event is $125,000 less applicable policy excess.
Insurer not required to increase cover for contents under the policy
The panel is not satisfied the complainants have established the insurer is liable for the
claimed mould damage to their contents. Further, that it is reasonable to accept the mould
and any associated damage is the result of the flood event giving rise to the claim.
The panel notes the insurer assessed and settled the complainants for their contents claim by
21 July 2022, which was around three weeks after claim lodgement. This means not only did
the insurer fulfil its obligations in this regard within a short period but that the insurer has
covered the complainants for the full extent of the value they chose to insurer their contents
for under the policy.
The complainants bear the responsibility to ensure they arrange cover that meets their needs
as well as ensure the safety of their property. The panel believes it is reasonably clear the
Determination | Case number: 912046 Page 8 of 10
complainants’ contents were underinsured at the time of the loss and that the complainants
failed to ensure it was safe to store their undamaged contents in the upstairs area of an
obviously significantly water damaged property.
The panel accepts there have been delays experienced under the claim. However, as noted
above the panel is not satisfied it is fair to determine the insurer is solely liable for these
delays. The insurer settled the complainants for their maximum entitlement for contents
damage and from this point onwards it was the complainants’ responsibility to arrange for
their required safety and storage.
The panel is not satisfied the complainants have provided reasonably compelling information
in support of their position that the insurer is liable for the mould and associated damage. It is
not uncommon, and it is often that mould develops in properties impacted by significant water
inundation events.
Accordingly, in the absence of persuasive information, the panel is not satisfied the
complainants have shown an entitlement to further cover for contents loss or damage under
their claim arising from the flood event.
Equally, the panel is satisfied that the mould and associated damage is directly related to the
flood event, which means the complainants are not entitled to again claim for flood damage to
their contents under the renewed policy term.
Accidental damage cover does not assist the complainants
In the interest of completeness, the panel notes the policy includes accidental damage cover,
which is generally accepted to be loss or damage that occurs unexpectedly, without design,
or by chance. The panel accepts the flood event was unexpected, without design or by
chance i.e. it could fall under the policy’s accidental damage benefit.
However, this does not assist the complainants’ claim for additional contents cover under the
policy. This is because the insurer has already accepted to cover the contents damage
caused by the flood to the maximum entitlement available to the complainants under the
policy. Whether this damage was to be accepted under the insured event flood or accidental
damage benefit, the proximate cause for the loss or damage is the same flood event.
The panel is not satisfied it would fair or consistent with the commercial intention of the policy
to allow the complainants to seek indemnity for the same loss caused by the same event
under two different policy benefits.
2.6 Are the complainants entitled to non-financial loss
compensation?
Yes. The insurer is to arrange a payment of $1,000 in non-financial loss compensation to the
complainants, this being in addition to the $2,000 already offered/paid by the insurer in line
with the AFCA Rules.
AFCA Rules allow for an award of compensation in certain circumstances
The AFCA Rule D 3.3 allows for an award of up to $5,400 for non-financial loss
compensation, if the insurer caused the complainant to suffer an unusual degree or extent of
inconvenience, delay or interference. AFCA takes a conservative approach when considering
any award of compensation.
Determination | Case number: 912046 Page 9 of 10
Insurer is to increase compensation for non-financial loss offer
The complainants say they have been subject to an unusual degree of stress, delays and
inconvenience because of the insurer’s handling of the claim.
The catastrophic events leading to the claim were devastating and the panel acknowledges
the challenging circumstances faced by the complainants. Based on the submissions made
by both parties, the insurer has acknowledged failures on its behalf and for which it has paid
the complainants $2,000 in compensation for non-financial loss.
The panel is satisfied it is fair that the insurer increases this by a further $1,000 in
compensation for non-financial loss. This is because the panel is not satisfied $2,000
represents fair compensation for the stress, anxiety and inconvenience experienced by the
complainants. This is especially with respect to the insurer’s management of the temporary
alternative accommodation arrangements and delays in issuing payments to the
complainants for loss or damage accepted under the claim.
The panel is not satisfied the complainants are entitled to the maximum or a higher award of
compensation for non-financial loss. This is because the available information shows it would
be unfair to hold the insurer solely responsible for the delays experienced under the claim as
well as a breakdown in communication between the parties.
The panel accepts the complainants have also contributed to delays in maintaining
expectations that are not consistent with the cover available to them under the policy. This
includes a failure to accept reasonable attempts by the insurer to resolve concerns raised by
the complainants albeit the insurer’s initial assessment of its liability and settlement offers
were not reasonable.
Accordingly, the panel is satisfie d that within 14 days of receiving notice of the complainants’
acceptance of this determination, the insurer is to pay the complainant a further $1,000 in
non-financial loss compensation.
2.7 Why is the outcome fair?
The outcome is fair because the insurer is entitled to limit its liability under the claim based on
the policy provisions. It is fair that the insurer be required to increase its final claim settlement
to include works which do not form part of the scope of works it has relied on to assess its
liability under the claim. Further, it is fair that the insurer pays the complainants compensation
for non-financial loss in the circumstances.
Determination | Case number: 912046 Page 10 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in consumer claims.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.