Reduction of cash settlement amount, allowance for contingencies, professional costs and compensation for claim handling delays
Text of the determination
Determination
Case number 907291
Financial firm Insurance Australia Limited
Determination | Case number: 907291 Page 2 of 7
Case number: 907291 15 May 2023
1 Determination overview
1.1 Complaint
The complainant has a home insurance policy with the financial firm (the insurer). On 20
March 2021, the complainant lodged a claim for water damage to the property that occurred
due to a flood event.
The insurer accepted the claim and advised, on 21 September 2021, that it would cash settle
the complainant. However, the settlement amount was subsequently reduced.
The complainant disagrees with the reduction in the settlement amount. She is also seeking
compensation for the insurer’s poor claims handling and the delays in settlement .
1.2 Issues and key findings
Is the insurer required to increase the cash settlement?
Yes. The insurer has elected to cash settle the claim. It should increase its settlement to
include a 15% allowance for contingencies and the loss of a lifetime guarantee on repairs.
The insurer must therefore pay the complainant a further $19,215.83 (15% of $128,105.56).
Is the insurer required to reimburse the professional costs?
No. Based on the available information, the insurer is not required to reimburse the
complainant’s professional costs of obtaining a further engineering report.
Is the complainant entitled to compensation?
Yes. The complainant is entitled to non-financial loss compensation for the delay, stress and
inconvenience caused by the insurer’s handling of the claim. However, the insurer’s
compensation offer of $3,250 is fair and reasonable in the circumstances.
Why is the outcome fair?
In circumstances where the insurer elects to cash settle a claim, it is fair that an allowance be
included for contingencies and the loss of a lifetime guarantee on repairs. It is also fair that
the insurer pay the complainant non-financial loss compensation for her claims experience.
1.3 Determination
This determination is mostly in favour of the insurer.
If the complainant accepts the determination, within 14 days of being notified of the
acceptance, the insurer must pay the complainant (less any amounts already paid):
the revised offer;
an additional $19,215.83 for contingencies and the loss of a lifetime guarantee on repairs;
$3,250 for non-financial loss compensation.
I otherwise confirm that the insurer has offered to waive the $750 excess and that no excess
is payable in relation to the claim.
Determination | Case number: 907291 Page 3 of 7
2 Reasons for determination
2.1 Is the insurer required to increase the cash settlement?
Yes. The insurer has elected to cash settle the claim. It should increase its settlement to
include a 15% allowance for contingencies and the loss of a lifetime guarantee on repairs.
The insurer must therefore pay the complainant a further $19,215.83 (15% of $128,105.56).
Parties do not dispute that there is a claimable loss
The complainant’s policy is a listed events policy. It provides cover for a series of events,
including storm, subject to the terms and conditions of the policy.
The parties do not dispute that the complainant has established a claimable loss under the
policy. However, the issues in contention between the parties relate to the insurer’s
assessment of its liability for the claim and additional costs incurred by the complainant.
Amount in dispute is limited to $5,891
The complainant refers to a letter from 21 September 2021 where she was advised that the
insurer would settle the claim for $128,105.56 (original offer). This was based on a quote the
insurer obtained from a builder, R, dated 25 March 2021. The insurer subsequently reduced
the settlement to $101,597.17 based on R ’s , revised scope of works.
Since advising the complainant she would be cash settled for the original offer, the
complainant commenced the rebuilding process and incurred fess of $9,914 (rebuilding fees).
This includes fees for an accredited certifier, builders levy, application fees, architect fees,
civil engineers, home warranty fees and council fees. The insurer has accepted the
complainant incurred the rebuilding fees and reimbursed the complainant for this sum.
On or about 14 June 2022, the insurer’s IDR team det ermined that it would settle the
complainant according to the initial quotation from R. The insurer therefore made a further
offer to the complainant of $121,374.56 (revised offer). This figure represents the original
offer less $5,981. The $5,981 reduction is for application fees, council fees, certification,
inspection fees and home warranty fees (which total $6,731) less the applicable excess of
$750 which the insurer has agreed to waive.
The complainant has accepted the revised offer. Therefore, the only amount in dispute is the
$5,981 reduction.
Complainant’s position
The complainant is seeking a further $5,981.
The complainant also argues the insurer delayed making the payment to their credit provider
which should have occurred when she returned the mortgage discharge letter to the insurer.
Due to this, the complainant says there was interest charged on the home loan account. The
complainant is also requesting an uplift of 30% to be included for the increase in building
costs since the original offer was first made.
Insurer’s position
The insurer argues the total settlement amount was assessed in accordance with the
complainant’s policy terms and conditions. The insurer relies on the quotation from R in the
sum of $128,105.56.
Determination | Case number: 907291 Page 4 of 7
It also says the $5,981 reduction is included in the rebuilding fees ($9,914) which the insurer
paid the complainant on or about 15 July 2022. Therefore, the insurer has settled the
complainant for a total of $131,288.56.
Further, the insurer submits it has acknowledged the concerns raised by the complainant and
increased the temporary accommodation benefit to cover the complainant until 10 March
2023. This is to allow the complainant’s trades to complete the repairs to the property. The
insurer notes it provided the complainant with an additional 8 months of accommodation, as
the benefit provided under the policy only covered her until July 2022.
Insurer ’s assessment is correct but must make allowance for contingencies
I have considered the parties’ position re lating to the settlement amount. I am satisfied the
insurer has correctly assessed the claim based on the quote received from R.
I accept the policy clearly states it will cover rebuilding fees on the condition that the insurer
agrees to do so prior to the works commencing. In this instance, the information available
suggests this was not communicated clearly to the complainant. However, the insurer has
agreed to cover the rebuilding fees.
I acknowledge the complainant was unprepared for the change in settlement as she had
already notified her credit provider of the original offer. However, it would not be fair to expect
the insurer to pay an additional $5,981, considering it has already settled the complainant for
the revised offer and rebuilding fees.
The complainant’s policy gives the insurer the discretion on how to settle a claim. This
includes either undertaking the repairs or cash settling the claim. When the insurer repairs the
building, it guarantees the quality of materials and workmanship for the life of the building. A
cash settlement on the other hand transfers all risks from the insurer to the complainant for
any unforeseen damage and any additional work or expense required once repairs
commence. It also means a loss of the lifetime guarantee on repairs.
Insurers should act fairly to ensure a cash settlement covers all the repairs and the transfer of
risk. Therefore, I am satisfied that a reasonable allowance for contingencies and a loss of a
lifetime guarantee on repairs in the circumstances is 15%. Accordingly, the insurer is
required to pay the complainant a further $19,215.83.
2.2 Is insurer required to reimburse the professional costs?
No. Based on the available information, the insurer is not required to reimburse the
complainant’s professional costs of obtaining a further engineering report.
AFCA may require insurer to contribute to a c omplainant’s professional costs
The AFCA Rules enable AFCA to require an insurer to contribute to the professional costs
incurred by the complainant. These costs are usually capped at a total of $5,000, unless
special circumstances apply.
When considering whether to require an insurer to make a costs contribution, AFCA takes
into account the complexity of the complaint and whether the complainant needed to incur the
particular cost to understand or establish their claim.
Determination | Case number: 907291 Page 5 of 7
Insurer is not required to reimburse professional costs
The complainant seeks reimbursement of the $605 fee she incurred in obtaining an additional
engineer’s report . The complainant submits the beams were required by the builder to
adequately repair the property. She also says the insurer advised it would cover the cost of
this report.
The insurer submits there is not enough information to substantiate a new engineering report
was needed. It says a change in design of beams is not required if completing repairs in a
like for like fashion. The insurer also says the invoice notes ‘ Propos ed Alterations & Additions’
suggesting the changes include repairs and modifications not present prior to the date of loss.
It has also requested a copy of the report in order to consider its position but has not received
it.
Therefore, on balance, I am not satisfied the engineering report was required in order to carry
out the repairs at the property. Accordingly, the insurer is not required to reimburse the
complainant for the engineering fees.
2.2 Is the complainant entitled to compensation?
Yes. The complainant is entitled to non-financial loss compensation for the delay, stress and
inconvenience caused by the insurer’s handling of the claim. However, the insurer’s
compensation offer of $3,250 is fair and reasonable in the circumstances.
AFCA can award compensation for poor claim handling
Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This
must relate to poor claims handling or other actions of the insurer which causes:
an unusual degree of stress, delay, or inconvenience, and/or
interference with a person’s expectation of enjoyment and/or peace of mind.
We expect complainants to be moderately robust, and we will not award compensation for the
ordinary degree of inconvenience involved in making a claim.
Complainant is entitled to non-financial loss compensation
I accept the complainant says the claims process has caused a high level of stress and
anxiety and with the insurer showing minimal duty of care to her situation. I acknowledge the
complainant’s concerns and dissatisfaction as she had to follow up on several decisions
made by the insurer. This includes (but is not limited to) decisions relating to the settlement
amount and temporary accommodation arrangements.
Further, the claim notes submitted by the insurer show that, due to an oversight, the
settlement payment was delayed from 17 March 2022 (the day the mortgage discharge
information was received by the insurer) until 3 January 2023, being 292 days. The notes also
show there was a further delay of one month for the rebuilding fees to be paid.
Over the course of the claim, the complainant raised concerns the delays in receiving
payments was impacting her mortgage repayments, the interest payable and her ability to pay
the trades on time.
The insurer acknowledges the service issues and associated delays experienced in relation
to the claim. It has offered to pay the complainant $3,250 in non-financial loss compensation
(compensation offer) and waived the excess payable on the claim given the level of service
provided did not meet the complainant’s expectations. It has also agreed to extend the
Determination | Case number: 907291 Page 6 of 7
complainant’s temporary accommodation benefit to 10 March 2023 to allow the complainant’s
builder time to complete the repairs.
On balance, I am satisfied that the compensation offer is reasonable and provides sufficient
compensation to the complainant.
2.3 Why is the outcome fair?
In circumstances where the insurer elects to cash settle a claim, it is fair that an allowance be
included for contingencies and the loss of a lifetime guarantee on repairs. It is also fair that
the insurer pay the complainant non-financial loss compensation for her claims experience.
Determination | Case number: 907291 Page 7 of 7
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.