Home / Suncorp Group / Determination 907003

Determination 907003

Insurer declined storm damage cover for roof and sarking as deterioration and maintenance; also disputed kitchen, contents, accommodation and delay

FirmSuncorp Group
Decided2023-10-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$32,462
Non-financial loss$2,500
Amount claimed—
SourceAFCA PDF

Summary

The insurer declined cover for roof and sarking storm damage, citing deterioration, and under-settled the kitchen. AFCA found the storm likely caused the damage and ordered payment for roof, kitchen and $2,500 non-financial loss, but rejected further contents and accommodation claims.

On balance the complainant's pre-purchase, restoration and builder evidence showed storm damage, and the insurer did not establish the wear and tear exclusion; delays warranted non-financial loss compensation.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial lossreassess claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 907003 Financial firm AAI Limited Determination | Case number: 907003 Page 1 of 10 Case number: 907003 20 October 2023 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (the insurer). On or about 28 February 2022 the complainant lodged a claim for storm damage, saying his roof was leaking in multiple areas. The insurer accepts there was a storm event and settled the complainant the sum insured for the contents. The insurer also partially accepted the internal resultant damage. However, the insurer declined cover for the roof and sarking, saying the storm did not damage these areas. Rather, it says the damage is due to maintenance issues and deterioration. 1.2 Issues and key findings Has the insurer correctly assessed the claim? No. The information shows the storm, on balance, damaged the roof and sarking. It is fair for the insurer to accept this cost. The panel also considers it fair for the insurer to cover the cost of the kitchen replacement. The insurer is not liable to cover any further amount for contents. Is the complainant is entitled to accommodation payments? No. The complainant has received accommodation payments in excess of the policy limit. Is the complainant is entitled to compensation? Yes. The complainant is entitled to non-financial loss compensation. Why is the outcome fair? The determination is fair in the circumstances because the complainant has shown, on balance, the storm damaged the sarking and roof and that the kitchen required replacement. It is therefore fair for the insurer to increase cover for these items. However, the panel considers the insurer’s settlement for the contents and temporary accommodation is fair, as it has paid the complainant’s maximum entitlement under the policy. 1.3 Determination This determination is substantially in favour of the complainant. If the complainant accepts this determination, within 14 days of receipt of the complainant’s acceptance, the insurer is required to pay the complainant:  $15,500 for the sarking/roof repairs, plus interest from 27 June 2023 to the date it makes payment, in accordance with section 57 of the Insurance Contracts Act 1984 (the Act)  $23,375 for the kitchen replacement, less $6,413 if already paid  $2,500 in non-financial loss compensation. Following completion of the repairs, it is fair for the insurer to arrange an assessment of the flooring to determine whether it is liable for any further damage to the flooring at that point. Determination | Case number: 907003 Page 2 of 10 2 Reasons for determination 2.1 Has the insurer correctly assessed the claim? No. The information shows the storm, on balance, damaged the roof and sarking. It is fair for the insurer to accept this cost. The panel also considers it fair for the insurer to cover the cost of the kitchen replacement. The insurer is not liable to cover any further amount for contents. Complainant has initial onus to establish loss covered by terms of policy It is accepted insurance law that the complainant carries the initial onus to establish, on the balance of probabilities (that is, more likely than not), a loss which is covered by the terms and conditions of the policy. Only if the complainant can do this, will the onus shift to the insurer to show, on balance, it is entitled to decline cover in line with the policy wording or otherwise. The policy is an ‘insured events’ policy. T his means not all loss and damage is automatically covered. Rather, only loss or damage caused by one or more of the insured events, and not subject to exclusions, is covered. The product disclosure statement (PDS) outlines the insurer will cover loss or damage caused by storm. There is no dispute there was a storm event that caused damage to the home. However, there is a dispute as to whether the storm damaged the roof and sarking, or if it was due to deterioration and maintenance issues. The insurer refers to exclusions in the PDS relating to the home not being in good condition and gradual deterioration. Relevant sections of the PDS are included in section 3.1 of this determination. The insurer accepted the resultant damage caused by the event and offered a cash settlement of $140,576.80 based on its assessment of the cost to repair this damage. The complainant confirmed the insurer has settled its obligations for mould remediation. The panel considers this is no longer in dispute and has therefore not been considered as part of this determination. The insurer also reimbursed the complainant his expert report cost of $700, which means this is no longer in dispute. Insurer says its reports show sarking not damaged due to the storm The insurer provided a report from a builder (KB) dated 25 March 2022. This states the sarking below the roof tiles is torn and degraded generally, and water staining is evident on the timber roof framing below tears near the manhole. It believes this pre-dates the claimed event. KB’s roof report dated 25 March 2022 states the roof is in good condition. It states the leaking and mould issues downstairs are related to a single skin brick wall being soaked by rain and seepage from ground water, not from the roof. It states the rain has blown in under tiles, and there are rips in sarking where leaks are present. KB’s roof report dated 26 July 2022 states the tiles failed due to excessive rain. It states the degraded sarking underneath the tiles has then allowed water to enter the roof cavity. It states the sarking is a maintenance issue. Determination | Case number: 907003 Page 3 of 10 The insurer provided a mould and moisture evaluation report from an environment scientist company (CD) dated 4 April 2022. CD states there was limited physical damage seen in the roof area, which indicates that the roofing failures have occurred recently. It states the recent water damage and humidity has resulted in mould growth. CD’s report dated 16 December 2022 states remediation is incomplete, the residence is at risk of further water damage and the furniture in the residence may be contaminated with mould. The insurer provided a report from an engineer (JH) dated 21 February 2023. JH states:  an inspection of the visible areas of the roof (some areas obscured by tarp) showed the roof to be generally in a good condition with the ridge capping and pointing also in a good condition which is expected given the recent restoration  there are no readily discernible issues with the tiles and capping which would have led to the reported water ingress  the roof pitch was measured from inside the roof and found to be around 18.5 degrees which means that sarking is required for this roof  being below 20 degrees means the roof is more susceptible to minor water ingress during wind driven rain events, which means the sarking has likely been exposed to many weather events over the life of the property which will have led to gradual deterioration  it did not have available a copy of the pre-purchase inspection so cannot comment on what may or may not have been included  there are occasions where parts of the roof void are not inspected due to accessibility limitations however it is expected that each of the tears would have been visible during any reasonable inspection of the cavity  the prevalence of age deterioration, fatigue cracking, and other tears in the sarking would suggest that the torn sarking which has resulted in the observed ingress is due to general aging and wear and tear  the sheer magnitude of the February 2022 event has seen a greater volume of water enter the roof space which has exposed the already partially compromised sarking into eventual failure and subsequent ingress to the dwelling  it is anticipated that if the sarking had been in a better condition, the event would not have had such an adverse effect on the material and not resulted in the observed tear. The insurer says some of the damage to the home was due to maintenance related issues, having occurred over a period of time. Complainant says the storm caused the damage The complainant disputes that there were maintenance issues with the roof prior to the insured event in February 2022. The complainant provided a pre-purchase inspection report carried out on 6 February 2020. The report highlighted that the general condition of the roof was in a serviceable condition for its age. A visual inspection of the roof void identified sarking to be in a serviceable condition, with no tearing or sagging evident. The complainant also engaged SR to carry out roof restoration work in April 2021. SR provided an email confirming the work carried out. It also stated an inspection of the roof cavity for leaks after high pressure cleaning of the roof found no leaks and sarking condition was serviceable with no defects found. The complainant also provided a report from a builder (JP). JP inspected the home on 26 November 2022 and states: Determination | Case number: 907003 Page 4 of 10 It is of my opinion and I would posit; a significant rain event has the capacity to overwhelm the roof tile system. This can also be exacerbated on the lee side of the roof where wind gusts flowing over a roof can cause a negative pressure on the lee side of the roof this can also create a suction effect that has the capacity to hinder water flow off the roof causing a ponding or flooding of the roof system allow water ingress. … It is my opinion the roof and sarking to the subject property is sufficient for light, moderate and heavy rain; the major rain event experienced in February and May of 2022 by Lismore, Byron and much of Northern NSW has exposed a latent, undiscoverable fault in the sarking. Further to this discussion I suggest that the sarking strength had been diminished over time by small amounts of water ingress which has ponded and not penetrated the sarking until being impacted by severe storms and excessive amounts of concentrated rainfall. As the information yielded from the Bureau of meteorology below ascribes the weather event that has caused this water entry problem and ceiling damage to [the complainant’s] ceilings was of a major catastrophic magnitude… Reports show damage to sarking, on balance, is due to the storm Having considered all the available information, the panel is persuaded by the complainant’s submissions. The complainant provided several reports to support his position, and a pre- purchase inspection report from 2020 which shows the r oof to be in ‘a serviceable condition’ and sarking being installed which also ‘is generally in a serviceable condition’. Pictures taken from the roof void in February 2020 do not demonstrate failed sarking. The roof was also restored in April 2021 and SR had also indicated that there were no defects on the completion of their work. The panel considers there is insufficient information to show the sarking was in a deteriorated state prior to the storm event, in light of this persuasive information the complainant provided on its condition prior to the storm. The JP report presents a reasonable theory of how the damage to the sarking could have been caused by the storm. The insurer's expert JH does not rule that possibility out or present any compelling evidence as to why wear and tear is more likely an explanation for the relevant damage. The panel also notes KB’s reports are brief and do not explain in detail why it considered the damage to the sarking pre-dated the storm event. The panel finds these reports are not persuasive in the circumstances. Given the severity of the weather in February 2022, and noting the detail and analysis provided in the JP report, the panel accepts, on balance, the storm damaged the sarking. The panel does not consider the insurer has shown the damage is excluded under the policy. Insurer to cash settle the complainant for the sarking repairs The insurer is required to accept the claim for repairs to the roof and sarking. The complainant provided quotes to replace the sarking. These amounted to $15,500, $20,000 and $17,116. The panel understands the complainant has now completed the repairs to the roof and sarking for $15,500. The insurer has not argued any of the amounts quoted were unreasonable. In the circumstances, and in the interests of bringing finality to the complaint, the panel considers it Determination | Case number: 907003 Page 5 of 10 fair for the insurer to reimburse the complainant $15,500. The insurer is to cash settle this cost, plus interest from the date the complainant confirmed to AFCA he paid this amount (27 June 2023), to the date it makes payment, in accordance with section 57 of the Act. Insurer to increase settlement for kitchen repairs The insurer also partially accepted damage to the kitchen. The complainant says the kitchen is a wooden design and the bench tops, cupboards and hinges are no longer made. He says the door handles and wood grain laminate could not be matched as it was an original 1971 kitchen in pristine condition. He says as the kitchen was built on site and nailed to the floor, it could not be reinstalled once removed. The complainant says during the removal of asbestos it all had to be removed. He provided an invoice for $23,375 for a new kitchen. The insurer accepted $6,413 towards the kitchen. It says the complainant has not provided any detail as to what could not be matched and why. However, the panel accepts the information shows extensive damage to the kitchen area that required most of it to be removed. A report on file from KB dated 22 February 2023 states the kitchen is original, and it cannot ensure the existing kitchen will be salvageable upon demolition given its age of over 50 years. The complainant also provided a quote from the kitchen repairer (PT) dated 30 April 2023, which states due to the structural design of the original cabinetry it is unable to be removed and reinstalled. Based on this information, the panel considers it fair for the insurer to cover the cost of the kitchen replacement for $23,375. This is because the information shows, on balance, it required replacement following the damage. The insurer is entitled to deduct the $6,413 already accepted for the kitchen, if this has already been paid. The complainant also says the pine flooring has been damaged by the insurer’s trades. The insurer has not responded to this. However, there is insufficient information at this stage to show the insurer’s trades have caused damage. Following completion of the repairs, it is fair for the insurer to arrange an assessment of the flooring to determine whether it is liable for any further damage to the flooring at that point. Insurer not required to pay any additional amount for contents The insurer has settled the full sum insured for contents. The complainant says he is underinsured and the insurer’s actions caused him to incur additional losses to his contents. However, the panel does not consider the complainant has provided sufficient information to show the insurer caused him to suffer a loss above his sum insured value of his contents. The onus is on the complainant to ensure the sum insured for a property is accurate. The panel does not consider the insurer is liable for any further contents payment. 2.2 Is the complainant is entitled to accommodation payments? No. The complainant has received accommodation payments in excess of the policy limit. The complainant is not entitled to further accommodation expenses The policy limit for accommodation expenses is $31,500. This represents 10% of the building sum insured which is $315,000. The complainant has received $40,030. Determination | Case number: 907003 Page 6 of 10 The complainant says he is incurring further temporary accommodation costs. However, as the complainant has received an additional $8,530, beyond the policy limit, the panel accepts the insurer has met its obligations to the complainant for temporary accommodation costs and he is not entitled to any further payment. The panel does not consider the insurer is liable for any additional temporary accommodation costs beyond the maximum entitlement. Whilst the panel accepts there were delays on the claim, the panel considers the appropriate remedy in the circumstances is non-financial loss compensation, which is discussed below. 2.3 Is the complainant entitled to compensation? Yes. The complainant is entitled to non-financial loss compensation. Compensation may be awarded in certain circumstances Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $5,400) where there has been an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to compensation and expects a complainant to bear a normal degree of inconvenience during a claim. The complainant raised several issues with the insurer’s handling of the claim, including its lack of communication, the time he took to try to manage the claim, inadequate mould remediation and make-safe causing additional loss. Make-safe not carried out in a timely manner The insurer was notified of the claim on 28 February 2022. The insurer’s hygienist (C D) initially inspected the home on 31 March 2022 and advised make-safe works pertaining to the roof had not been completed. CD also indicated that until make-safe work was completed, it would be impossible to remediate the residence. The insurer confirmed that it was not until 14 April 2022 that a tarp was placed on the roof to prevent further water leaks. When CD inspected the property on 8 December 2022 it noted that the tarp that had been fitted to the area where the roof had leaked had degraded. Pieces of the degraded tarp were seen around the premises. CD recommended that the property remain uninhabited until remediation works were completed. The insurer confirmed that it was not until 22 February 2023 that the tarp was replaced. The panel considers the insurer could have done more to assist the complainant with ensuring the property was protected following the damage. Delay with appointing expert The insurer advised the complainant on 19 August 2022 that it needed to obtain additional information to determine how water had penetrated the roof, given the roof had shown no signs of damage. The insurer’s appointed expert (JH) attended the property on 30 January 2023 and completed its report on 21 February 2023. Determination | Case number: 907003 Page 7 of 10 The insurer has also acknowledged to the complainant on 2 February 2023 that it would have been prudent to e ngage an engineer much ea rlier. The panel considers there were delays in the insurer’s appointment of experts that caused delays on the claim that could have been avoided. Insurer has caused unreasonable delays Given the above, the panel accepts the insurer caused unnecessary delays on the claim. The panel also accepts these issues caused the complainant to suffer inconvenience and an interference with his expectation of enjoyment or peace of mind. The panel considers it fair for the insurer to pay the complainant $2,500 in non-financial loss compensation in the circumstances. 2.4 Why is the outcome fair? The determination is fair in the circumstances because the complainant has shown, on balance, the storm damaged the sarking and roof and that the kitchen required replacement. It is therefore fair for the insurer to increase cover for these items. However, the panel considers the insurer’s settlement for the contents and temporary accommodation is fair, as it has paid the complainant’s maximum entitlement under the policy. Determination | Case number: 907003 Page 8 of 10 3 Supporting information 3.1 Relevant wording from PDS The most we will pay for all contents (page 18) The most we will pay for loss or damage to all contents arising from any one insured event is the contents sum insured (which includes any specified contents) plus any personal effects and/or enthusiast items sums insured (shown on your certificate), unless otherwise stated in your policy. There are limits that apply to individual contents items or types of items. These limits are set out in the tables on page 19 ‘Contents with fixed limits’ and ‘Contents with flexible limits’. … Temporary accommodation when you have home cover (Home cover only) Page 39 What is covered When we cover loss or damage to your home and the insured incident damages the home to the extent that it cannot be lived in by you, we will pay for your reasonable and necessary temporary accommodation costs for the time it will take to repair or rebuild the home so that it can be lived in again. We will also pay for temporary accommodation for your domestic pets in a commercial boarding establishment for the same period that we pay for your temporary accommodation. The most we will pay is the reasonable and necessary costs for: • short term accommodation agreed to by us (e.g. standard rates for a hotel, mo tel or serviced apartment) (up to 4 weeks only); • residential accommodation of a similar standard to the home (e.g. if the insured home is a 3 bedroom home we will aim to put you in a 3 bedroom home). We will also pay the reasonable and necessary costs for: • redirection of mail from the insured address; • utility connection costs such as water, electricity or gas at the temporary accommodation residence; • relocation of your contents to and from the temporary accommodation residence if you have contents cover under this policy; • assistance with bond payment for the temporary accommodation if required, however any amount we pay in bond is recoverable from you by us. We may deduct this amount from any amount payable to you; • if applicable, the break fees a ssociated with early termination of the lease or other rental agreement for your temporary accommodation, if you are able to return to the home in accordance with this additional cover, before the term of the lease or rental agreement ends. Limit The most we will pay under this cover for any one incident is 10% of your home sum insured. … Things we don't cover (page 78) Loss or damage to, or caused by, connected with or arising from, or liability caused by, connected with or arising from: Determination | Case number: 907003 Page 9 of 10 Home, unit or contents not in good condition any part of the home, unit or contents not being in good condition, such as, but not limited to: • the roof leaks when it rains; • there are blocked gutters; • there are areas of the roof that are rusted thr ough; • there is wood rot, termite or ant damage; • there are holes in floors, walls, ceilings or any other parts of the home or unit (e.g. external wall cladding, internal plaster, floorboards); • there are boarded up or broken windows; • there are st eps, gutters, flooring, walls, ceilings, gates, fences or wall fences or any other areas of the home or unit that are loose, falling down, missing or rusted through or otherwise in disrepair; • previous damage including damage caused by flood has not been repaired; • the home or unit is infested with vermin; • plant matter is growing on the home (e.g. walls, windows and gutters); • the home (including all sheds, outbuildings and any other structural improvement at the insured address) is not structurally sound or is unsafe or unfit to live in; • there are rings (i.e. jewellery) where the claw (surrounding the stone) is obviously damaged or worn. …. Things we don't cover (page 81) Loss or damage to, or caused by, connected with or arising from, or liability caused by, connected with or arising from: … Wear, tear, mould, gradual deterioration and other conditions any part of the home or contents that has wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration such as, but not limited to: • tiles and their adhesive or grouting breaking down; • weathering of roof tiles or roof ridge capping; • gradual weathering and breakdown of bricks, mortar or concrete; • fading of curtains and drapes; • gradual weathering of pot plants; • wear and tear of carpets, furniture and furnishings; • gutters r usted after exposure to the elements. 3.2 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. Determination | Case number: 907003 Page 10 of 10 While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.