Home / Suncorp Group / Determination 906706
Determination 906706
Dispute over adequacy of cash settlement and delay in settling accepted storm damage claims
Summary
The insurer accepted storm and hail claims but the complainant disputed the cash settlement and delays. AFCA found the $24,695 cash settlement reasonable, rejected pool and sale-loss claims, and awarded $3,000 for non-financial loss due to delay.
The complainant must prove claimed loss and provided no evidence the scope of works was inadequate, but the insurer's excessive delay warranted non-financial loss compensation.
Issues
- Claim amount dispute primary · not upheld
“The insurer's assessment is reasonable and there is no information from the complainant to show that the updated scope of works is inadequate.”
- Poor claim handling secondary · upheld
“the insurer, through its claims handling, caused the complainant to suffer an unusual degree of inconvenience.”
- Delay secondary · upheld
“The delay in settlement of these claims is certainly excessive.”
- Repairs or contractors secondary · not upheld
“Pool damage and mould remediation: insufficient evidence damage caused by insured event or insurer delays; mould remediation provided for in scope.”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial loss
Text of the determination
Determination
Case number 906706
Financial firm AAI Limited
Determination | Case number: 906706 Page 1 of 6
Case number: 906706 21 June 2023
1 Determination overview
1.1 Complaint
The complainant holds a home insurance policy with the financial firm (the insurer). On 24
July 2018 the complainant lodged a claim for storm damage to his roof top solar panels. A
further claim was lodged for damage caused by a hail storm in 2020. The insurer has
accepted both claims but the complainant says the cash settlement being offered is
inadequate and that he suffered damages due to the insurer’s delays.
1.2 Issues and key findings
Has the insurer correctly assessed the claim?
Yes. The insurer’s assessment is reasonable and there is no information from the
complainant to show that the updated scope of works is inadequate.
Is the complainant entitled to non-financial loss compensation?
Yes, the insurer is to pay $3,000 to the complainant in non-financial loss compensation due to
the excessive delay.
Why is the outcome fair?
This outcome is fair because a cash settlement is the only mode of resolution available and
the material shows the amount of the cash settlement is reasonable.
1.3 Determination
This determination is substantially in favour of the insurer.
Within 21 days of the complainant’s acceptance of this determination the insurer is to pay the
complainant:
$24,695 in respect of storm damage from the 2008 and 2020 events; and
$3,000 in respect of non-financial loss.
Determination | Case number: 906706 Page 2 of 6
2 Reasons for determination
2.1 Has the insurer correctly assessed the claim?
Yes, the insurer’s assessment is reasonable and there is no information from the complainant
to show that the updated scope of works is inadequate.
Complainants must establish claimable loss
A party making an insurance claim must establish they suffered a loss that is covered under
the insurance policy. They must establish this on the balance of probabilities (i.e. that it is
more likely than not).
If a claimable loss is established, the insurer must accept the claim, unless it can establish
the application of a relevant exclusion. The insurer must establish the exclusion on the
balance of probabilities.
Whilst the insurer has accepted it is liable for the 2018 and 2020 storm claims, the
complainant is still required to prove each item of damage which he says resulted from those
storms.
The appropriate resolution is by cash settlement
The parties have proceeded on the basis that the damages from the 2018 and 2020 claims
be dealt with together. The precise date of the 2020 event is unclear on the material. As the
insurer has accepted both claims the issues in dispute concern the assessment of the
damages and the proposed cash settlement.
On 23 June 2022 the insurer cash settled part of the claim for damaged solar matting and
lazerlite sheeting. The complainant has throughout objected to cash settlement, preferring
instead that the insurer undertake the work. The insurer’s position was that maintenance work
was needed before repairs could be undertaken. This issue likely contributed to the delays
which have occurred. At some time in late 2022 the complainant sold the property. As a result
cash settlement is now the only resolution available.
In October 2022 the insurer reviewed its position on items in dispute. It instructed its builder J
to prepare an expanded scope of works. On 4 January 2023 the insurer increased its cash
settlement offer to $20,579.84 plus a 20% uplift for contingencies. This is a total sum of
$24,695.
Insurer has accepted corrosion damage to roof and guttering
The complainant claimed that corrosion had been caused to the metal roof and gutters of his
property due to chlorine leaking from the storm damaged solar panel tubing. The insurer had
previously accepted responsibility for the damaged solar panels but not the resulting
corrosion. In October 2022 the insurer accepted it would provide cover for the corrosion
damage. Th is is now included in J’s scope of works and the proposed cash settlement.
Damaged skylight is part of cash settlement
The complainant claims that the insurer has failed to fix his damaged skylight. However, the
repair of the skylight is included in J’s s cope of works and forms part of the cash settlement.
There is no material provided to suggest the provision made is inadequate.
Determination | Case number: 906706 Page 3 of 6
Insurer is not required to pay for pool repairs
The complainant says that due to the insurer’s delay in fixing the solar panels, the pool could
not be heated and was unused. As a result he says both pumps, sand filter and gas heater all
seized up. There was a build-up of algae growth on the pool walls.
The complainant submitted a quotation from S pool company dated 14 June 2022 which
mentions that the damage to the Solar Collector of the pool is consistent with hail/wind/storm
damage. The complainant submitted a second quote from W with itemised costing for a full
pool repair. The quotations do not explain how or when the damage occurred and the insurer
requested the complainant supply a causation report. The insurer also requested permission
for a pool specialist to inspect the solar collector and assess the pool and equipment. The
insurer says it has been difficult to make contact with the complainant. An inspection is no
longer possible due to the sale.
It appears the damage to the pool was not initially inspected by the insurer because it did not
develop until much later. There is now no opportunity for the insurer to inspect. I am not
satisfied that the inability to heat the pool makes the insurer liable for the subsequent damage
which occurred or that it can be said that the damage is a result of the storms. Further, the
complainant has an obligation under the policy to properly maintain the insured property and
mitigate damage. The damage appears to be due, at least in part, to a lack of maintenance.
In the absence of any causation information there is insufficient evidence to show the damage
to the pool was caused by a listed insured event or due to the delays by the insurer. Further
the policy excludes liability for consequential loss (PDS page 36).
Insurer remediated the mould
The complainant says that due to delays by the insurer, black mould developed on the
ceilings and that the insurer did not remediate the mould in a timely way. The information
available shows the insurer’s expert F attended on 10 December 2021, 11 January 2022, 12
January 2022 and 13 January 2022 to assess and remediate the mould issues to the lounge
room, bedrooms and the hallway. The complainant has acknowledged that the insurer
removed most, if not all, of the mould affected plaster. The insurer offered for F to re-attend
but this did not happen prior to the home being sold. It is now no longer possible to form an
opinion of the adequacy of the remediation work. Curiously the updated scope of work by J in
October 2022 includes reference to plaster removal for mould affected rooms. Accordingly,
there is in any case some provision for remediation in the proposed settlement sum.
No evidence cash settlement is inadequate
The complainant has provided very limited written submissions. In December 2022 the
complainant submitted that he had not been offered a cash settlement for the ceilings and
that the rooms were very large. However, J’s updated scope of works includes repainting the
ceilings in the hallway, living room and spare room. There is no evidence of other ceilings
requiring repainting. There is no material from the c omplainant to demonstrate that J’s scope
of works and costings are inadequate.
The complainant will not actually be undertaking the repair work and in the circumstances the
insurer’s offer of a 20% uplift seems reasonable.
Determination | Case number: 906706 Page 4 of 6
Complainant is not entitled to compensation for any loss in property sale
The complainant says the sale price of the property was negatively affected because of the
insurer’s failure to promptly undertake the necessary repairs. The complainant provided an
email from his real estate agent indicating the property was sold only for land value and could
have ‘ attracted at least $200,000 more’ . This is an assertion which is difficult to support. In
particular, the complainant has not provided the actual sale price or details of comparable
sales.
The insurer says the policy specifically excludes cover for consequential losses that follow an
incident covered by the policy. In any event I am not satisfied the complainant has provided
persuasive evidence showing the property could have been sold for a greater value if the
outstanding repairs were addressed. Nor should the insurer be held liable for the
complainant’s decision to sell the property pending any necessary repair work. Furthermore,
the complainant is now receiving a cash settlement for any incomplete work. The complainant
has not established a financial loss when selling the property.
2.2 Is the complainant entitled to non-financial loss
compensation?
Yes, the insurer is to pay $3,000 to the complainant in non-financial loss compensation due to
the excessive delay.
AFCA may award compensation
AFCA will only award compensation for non-financial loss where there has been an unusual
amount of physical inconvenience, time taken to resolve a situation, or interference with the
complainant’s expectation of enjoyment or peace of mind. The maximum amount of
compensation that AFCA can award is $5400.
There has been excessive delay in settlement
The complainant says the insurer caused unreasonable delays in assessing and repairing the
property. The delay in settlement of these claims is certainly excessive. No doubt however
the corrosion damage from the 2018 event was not apparent until later.
The timeline includes as follows:
the initial claim was lodged on 24 July 2018
the insurer agreed to have all damages to the property re-assessed on 22 June 2021
the insurer updated the cash settlement for the repairs required on 30 August 2021
the insurer ’s internal review on 20 October 2021 found it should accept the solar matting
the insurer did not arrange for F to undertake mould remediation until after October 2021
mould remediation was not completed until 13 January 2022
in an internal review 10 June 2022, the insurer acknowledged the complainant had not yet
been settled for any damages
the insurer settled for the solar matting on 23 June 2022, being 8 months after this
component was accepted
the insurer advised the complainant no cover will be provided to re-roof the property and
cover the pool damages in its IDR response on 8 July 2022.
Part of the delay appears to be contributed to by the complainant ’s limited availability, and his
not following through with his stated preference to provide independent reports and quotes
(refer to 3.2). The insurer’s case notes also show there was delay with missed
Determination | Case number: 906706 Page 5 of 6
communications due to the complainant citing the wrong claim numbers. However, these
matters do not adequately explain the full extent of the delay. There is a substantial lack of
activity by the insurer before 2021.
I accept the insurer, through its claims handling, caused the complainant to suffer an unusual
degree of inconvenience. I consider it reasonable for the insurer to pay the complainant for
non-financial compensation in the amount of $3,000.
2.3 Why is the outcome fair?
This outcome is fair because a cash settlement is the only mode of resolution available and
the material shows the amount of the cash settlement is reasonable.
Determination | Case number: 906706 Page 6 of 6
3 Supporting information
3.1 AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.