Home / QBE / Determination 905742

Determination 905742

Strata corporation disputed cash settlement limited to the sum insured after fire damage, claiming insurer's claim handling caused delays and repair cost increases beyond the sum insured

FirmQBE
Decided2023-05-29
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A strata corporation disputed the insurer's offer to cash settle a fire claim as a total loss at the $1,248,000 sum insured, saying insurer-caused delays inflated repair costs. AFCA found for the insurer, which need only pay the sum insured as already offered, with no non-financial loss.

The insurer's liability is limited to the policy sum insured because delays and cost increases were mainly due to factors outside its control, such as the tenant and council approvals, and its handling was not unreasonable.

Issues

Subjects and remedies

home or building damagethird party authorityno remedy

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 905742 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 905742 Page 1 of 8 Case number: 905742 4 May 2023 1 Determination overview 1.1 Complaint The complainant is a strata corporation which held a commercial strata insurance policy with the financial firm (insurer). For clarity, any reference to the complainant includes the strata corporation and its authorised representative. The complainant lodged a claim for damage to the insured property caused by a fire in October 2020. The insurer accepted the claim in November 2020 and has since offered to cash settle it as a total loss (based on the sum insured of $1,248,000). The complainant is not satisfied with the insurer’s approach to settling the total loss, as it will provide insufficient funds to complete the necessary repairs. The complainant says this could have been avoided if the insurer and its trades had more effectively managed the claim process and communicated more clearly. The insurer disagrees. It says the factors leading to a delay in settling the claim were outside its control. The insurer says it is meeting its obligations by settling the claim with a payment up to the policy limit, and should not be required to pay more. 1.2 Issues and key findings Is insurer’s liability limited to the policy sum insured ? Yes. The insurer is entitled to settle the claim by paying the policy sum insured to the complainant. It is not liable for any further costs or losses. Is complainant due non-financial loss compensation? No. The information has not shown the insurer ’s handling of the matter warrants payment of compensation, nor that it should otherwise be held responsible for the time taken and consequences of the delayed finalisation of the claim. Why is the outcome fair? This outcome is fair as the insurer has an obligation to settle an accepted claim in line with the policy wording, and has offered to do so. The insurer has shown it is fair and appropriate to cash settle the claim as a total loss, based on the policy limit of the sum insured; and the available evidence does not establish the insurer has any further liability beyond this, either under the terms of the policy or otherwise. 1.3 Determination This determination is in favour of the insurer. The insurer is required to promptly settle the claim by paying the sum insured stated in the policy, as it has agreed to do. It is not required to take any further action. Determination | Case number: 905742 Page 2 of 8 2 Reasons for determination 2.1 Is insurer’s liability limited to the policy sum insured ? Having reviewed all the available evidence, the panel is satisfied the insurer is entitled to limit its liability for the claim to the policy sum insured. This is because, for the reasons set out below, the panel is not satisfied that the insurer should be held responsible for the delays and cost escalations which have occurred since the claim was accepted, and which now mean the cost of the claim-related repairs will exceed the sum insured. On balance, total loss decision is reasonable There is no dispute that the complainant has a valid claim, nor is there a dispute as to the extent of the damage to the insured building from the fire. The insurer has confirmed it is prepared to treat the building as a total loss, since the repair quotes mean that possible variations/contingencies arising in the course of the repair process would likely mean the costs would exceed the policy limit (sum insured). The insurer says there is a reasonable chance of this occurring. The panel notes the value of the most recently quoted repair work is over $1,100,000. There is no information from the complainant disputing this. The panel is satisfied the insurer’s decision to treat the building as a total loss, and to cash settle, is reasonable in the circumstances. The issue in dispute is whether the insurer – because of its handling of the claim – should accept liability (beyond the policy sum insured) for the increase in repair costs which has since occurred. Evidence shows substantial increase in repair costs following the initial quote The insurer supplied four repair quotes in total for the work necessary to repair the damaged building. The first of the quotes was completed by a builder (WI) on 22 February 2021. This quote proposed a repair totalling $683,000, which was well below the policy limit of $1,248,000. The quote gave two options to complete the repair. One involved rebuilding units two and three which were damaged in the fire, with a limited demolition of the shared wall between units one and two. The second option was to demolish all three units and replace them with a different design using tilt up concrete. Both options are in line with the recommendations in the engineer’s (SE) report dated 5 November 2020. WI supplied an updated quote for the repair of units two and three, following the disputed delays showing the repair costs had increased to $1,112,785.89 on 12 July 2022. This figure was supported by comparative quotes (MC quoted $1,147,435.04 on 18 October 2022, and BB quoted $1,141,410.79 on 23 November 2022). T he complainant says the insurer’s handling of the claim (including lack of oversight and poor communication) is the cause of the delays in finalising the claim, and therefore of the increased costs which now apply. In the circumstances, it is appropriate to consider the timeline of events. A broad summary is included in section 3 of this determination. Determination | Case number: 905742 Page 3 of 8 Insurer’s contribution to delay s not sufficient to establish additional liability The panel has reviewed all the available evidence and is satisfied the delay in repairing the property is the result of multiple factors, only some of which we re in the insurer’s control. The panel is satisfied the initial assessment and approval period is not unusual for a claim of this kind. WI supplied their initial quote on 22 February 2021 showing the lengthy period it expected would be needed to complete council approvals and then repair the property. They also notified the owner of unit one that the tenant would need to vacate the property. WI’s predictions on the approval process timeline appear justified, as the evidence indicates there were lengthy delays getting council approval. The complainant argues this is due to repeated document errors caused by WI and the insurer’s loss adjuster (AN) rather than the alleged issues with the local council. The complainant’s supporting evidence is limited, although there is an email from WI accepting the initial demolition company had not met expectations. That suggests the insurer might reasonably take some responsibility for initial difficulties in obtaining approval to complete the demolition. This period would be from 25 March 2021 to 18 June 2021. The council approval of the demolition was received on 15 October 2021, and work was booked to commence on 15 November 2021. The panel is not satisfied there is sufficient evidence showing this further delay was in the insurer’s control. The owners of unit one also disputed the decision to repair unit one instead of demolishing it, meaning the insurer could not proceed with the work until this was resolved in any case. This covered the period of 2 July 2021 to 22 September 2021. The delays caused by the tenant of unit one are well documented and compelling. The information paints a picture of a business acting with its own interests in mind, which is not, in itself, inherently unreasonable, but which had the unfortunate flow-on effect of delaying the repairs and generally complicating the matter. Given the extent of demolition work required (which also included a shared brick wall between units one and two), the panel is satisfied the insurer was justified in being concerned about the unit one tenant remaining in occupation during the work. It was reasonable to seek agreement for the tenant to vacate the premises while the repairs were completed. The information in the timeline of events shows the unit one tenant went to considerable lengths to avoid vacating the property, including engaging a solicitor and seeking a substantial compensation value from both the unit one owner and the insurer. This is in addition to repeated attempts to minimise their rental costs while the damage remained unrepaired. This delay began on 31 March 2021, continuing to 21 April 2022. After this, there was an agreement made to adjust the repair process, so the tenant could remain in the property for as long as possible. The insurer then offered an alternative repair method. Following 12 April 2022, WI was completing the approval process to begin the work, with the cost increases noted in AN’s report on 17 July 2022 leading to the current dispute. Having considered the available evidence, the panel accepts each party has contributed, to some degree, to the delays at various times. However, given the complications arising from the input and actions of others (outside the insurer’s control), the panel is not satisfied the insurer’s contribution was so substantial that it should be liable for repair costs exceeding the policy limit. Determination | Case number: 905742 Page 4 of 8 Complainant’s rebuttal has not advanced its position The panel acknowledges the complainant’s concerns that the delay could have been avoided with more proactive assessment and more effective communication by the insurer. However, the panel is not persuaded that is necessarily the case: the insurer engaged suitably qualified experts who made their assessment and recommendations. The insurer acted reasonably in response to those assessments (including acknowledging some initial shortcomings) and offered the more recent solution to the issues with the unit one tenant because the ongoing delay had become excessive. The panel does not consider the evidence shows the alternative repair method should have been adopted earlier, nor that it was plainly obvious or necessary at the time. Instead, multiple building experts and engineers did not consider the option the complainant now prefers, prior to the 21 April 2022 agreement. The panel is more persuade d by the insurer’s position, which is that the repair option was ultimately offered as a compromise because of the ongoing delay created by an unco-operative tenant. The insurer had, in the first place, acted appropriately and reasonably in advising the relevant party (the unit one owner) of the need for the unit one tenant to vacate the premises to enable the initially proposed repair. The panel is not satisfied the further loss to the complainant (from the increased costs of repairs since the claim was accepted, and appropriate repairs first proposed) can fairly or reasonably be attributed to any communication or other error by the insurer. AN notified unit one’s owner about the requirement for that unit to be vacated during the demolition on 1 April 2021. By 9 November 2021 the unit one tenant had refused to comply and sought ways of avoiding having to vacate. Arguably, the complainant itself (or at least, the unit one owner – a member of the strata corporation) had ample time and opportunity to attempt a resolution with the tenant. It is not fully clear how those parties addressed the matter in the meantime. Until it was established the tenant would not comply with the requirement to vacate in order to facilitate the recommended repairs, and the complainant was either unwilling or unable to enforce compliance, it is not reasonable to expect the insurer would instruct the builder to investigate alternative solutions. The panel is not persuaded the insurer acted unreasonably or inappropriately in its handling of the matter overall. 2.2 Is complainant due non-financial loss compensation? An award of non-financial loss is not warranted Under the AFCA Rules, we can consider compensation of up to $5,400 compensation for non-financial loss. We will only award this type of compensation in limited circumstances, including if a complainant suffers an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the complainan t’s expectation of enjoyment or peace of mind because the insurer mishandled the claim. Making a claim can be stressful and time-consuming, even if an insurer handles the claim correctly. AFCA does not award compensation for the ordinary degree of inconven ience that comes with making a claim. In this complaint, the panel is not satisfied the insurer acted unreasonably or inappropriately; nor that it should be responsible for the delays, inconvenience and further loss which has occurred for reasons outside its control. Compensation for non-financial loss is not warranted in the circumstances. Determination | Case number: 905742 Page 5 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 905742 Page 6 of 8 3.2 Summary timeline of relevant events Date Action 9 October 2020  The insured property is damaged by a fire.  The complainant lodges a claim with the insurer. 16 October 2020  AN completed its initial review of the claim and damage to the property. 5 November 2020  SC completes their assessment of the fire damage. 19 November 2020  Claim accepted by the insurer. 26 November 2020  Complainant supplied building plans to AN, which would need to be sent a further three times as requested by AN. 23 December 2020  SC provides their report on the extent of the damage and the repair options. 30 December 2020  AN completes their analysis of the cost of the repair options and organises quotes. 25 January 2021  AN updates the repair options following the report from a builder (PI). 9 February 2021  AN reviews the complaint for loss of rent and the request from u nit one owner to claim reduced rent for the tenant. 12 February 2021  AN compi l es the options based on the repair quotes obtained and requests instructions from the insurer. 22 February 2021  AN updates the latest quote from WI and requests further instructions on the repair from the insurer. 26 February 2021  Insurer authorised repair with WI. 4 March 2021  AN organises payment for loss of rent to unit one relating to unit one tenant pursuing reduction in rent for fire impact to their retail and wholesale trade. 25 March 2021  WI advises tenant they will need to vacate as building approval cannot be obtained until after demolition completed and slab assessed.  AN notes discussions need to occur with unit one owner about this. 31 March 2021  unit one owner contacts AN seeking further loss of rent payments.  unit one tenant emails unit one owner to complain about different timeframes given about when they will have to Determination | Case number: 905742 Page 7 of 8 stop trading during the repairs. 1 April 2021  AN confirmed the original understanding was six months would be needed for planning and permits but this changed based on WI advice.  AN report s tates: > unit one owner was advised of this on several occasions why the timeframe for tenant to vacate has changed > unit one owner advised tenant must vacate the premises for repairs to proceed > AN attempting to facilitate with unit one owner and the tenant > repair timeframe likely to be between 18 months to two years > review of claim for compensation by the tenant is that the policy does not respond to this and tenants should approach their insurer. 30 April 2021  AN reviewing options to dismantle the refrigeration units in unit one . 18 May 2021  AN supplied recommendation about comparative quote for unit one refrigeration units. 18 June 2021  WI met with local council and was permitted to lodge the demolition perm it. 29 July 2021  AN notes unit one owner disputes the insurer’s decision to only demolish unit two and three when repairing the damage and IDR complaint foreshadowed. 31 August 2021  Air quality report obtained due to concerns raised with unit one ’s trade being affected. No health hazards noted, but enjoyment likely to be affected during the demolition. 22 September 2021  Insurer delivers its final decision letter upholding the decision to demolish only u nit s two and three . 24 September 2021  AN sends an update about unit one refrigeration units to the insurer asking for instructions. 15 October 2021  WI receives demolition approval from council, scheduled for 15 November 2021. 9 November 2021  AN notes demolition works scheduled to begin on 19 November 2021 now on hold as unit one tenant has refused to vacate. 24 December 2021  AN notes review of the roof which would not result in an order for unit one tenant to vacate.  unit one tenant solicitors letter received s tating they were Determination | Case number: 905742 Page 8 of 8 intending to continue with the lease.  AN requested whether the matter should be referred to the insurer’s legal team. 1 March 2022  AN notes unit one owner and tenant may come to an agreement to vacate if unit one and two wall repairs can be done first. 21 April 2022  Parties agree to a compromise on the repair work to resolve the impasse created by unit one tenant. 7 June 2022  AN notes waiting on demolition approval from the council.  unit one owner request for a site meeting with the unit one tenants who wanted to pursue further rent reduction. Not resolved. 17 July 2022  AN notes building cost increases have risen significantly due to changes in labour and material cost. Variations may now t ake the repair above the sum insured limit. 18 August 2022  Complaint is lodged with AFCA for review.