Determination 905742
Strata corporation disputed cash settlement limited to the sum insured after fire damage, claiming insurer's claim handling caused delays and repair cost increases beyond the sum insured
Summary
A strata corporation disputed the insurer's offer to cash settle a fire claim as a total loss at the $1,248,000 sum insured, saying insurer-caused delays inflated repair costs. AFCA found for the insurer, which need only pay the sum insured as already offered, with no non-financial loss.
The insurer's liability is limited to the policy sum insured because delays and cost increases were mainly due to factors outside its control, such as the tenant and council approvals, and its handling was not unreasonable.
Issues
- Claim amount dispute primary · not upheld
“The insurer is entitled to settle the claim by paying the policy sum insured... not liable for any further costs or losses.”
- Poor claim handling secondary · not upheld
“not persuaded the insurer acted unreasonably or inappropriately in its handling of the matter overall.”
- Delay secondary · not upheld
“the delay in repairing the property is the result of multiple factors, only some of which were in the insurer's control.”
- Poor communication secondary · not upheld
“further loss cannot fairly be attributed to any communication or other error by the insurer.”
Subjects and remedies
home or building damagethird party authorityno remedy
Text of the determination
Determination
Case number 905742
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 905742 Page 1 of 8
Case number: 905742 4 May 2023
1 Determination overview
1.1 Complaint
The complainant is a strata corporation which held a commercial strata insurance policy with
the financial firm (insurer). For clarity, any reference to the complainant includes the strata
corporation and its authorised representative.
The complainant lodged a claim for damage to the insured property caused by a fire in
October 2020. The insurer accepted the claim in November 2020 and has since offered to
cash settle it as a total loss (based on the sum insured of $1,248,000).
The complainant is not satisfied with the insurer’s approach to settling the total loss, as it will
provide insufficient funds to complete the necessary repairs. The complainant says this could
have been avoided if the insurer and its trades had more effectively managed the claim
process and communicated more clearly.
The insurer disagrees. It says the factors leading to a delay in settling the claim were outside
its control. The insurer says it is meeting its obligations by settling the claim with a payment
up to the policy limit, and should not be required to pay more.
1.2 Issues and key findings
Is insurer’s liability limited to the policy sum insured ?
Yes. The insurer is entitled to settle the claim by paying the policy sum insured to the
complainant. It is not liable for any further costs or losses.
Is complainant due non-financial loss compensation?
No. The information has not shown the insurer ’s handling of the matter warrants payment of
compensation, nor that it should otherwise be held responsible for the time taken and
consequences of the delayed finalisation of the claim.
Why is the outcome fair?
This outcome is fair as the insurer has an obligation to settle an accepted claim in line with
the policy wording, and has offered to do so. The insurer has shown it is fair and appropriate
to cash settle the claim as a total loss, based on the policy limit of the sum insured; and the
available evidence does not establish the insurer has any further liability beyond this, either
under the terms of the policy or otherwise.
1.3 Determination
This determination is in favour of the insurer. The insurer is required to promptly settle the
claim by paying the sum insured stated in the policy, as it has agreed to do. It is not required
to take any further action.
Determination | Case number: 905742 Page 2 of 8
2 Reasons for determination
2.1 Is insurer’s liability limited to the policy sum insured ?
Having reviewed all the available evidence, the panel is satisfied the insurer is entitled to limit
its liability for the claim to the policy sum insured.
This is because, for the reasons set out below, the panel is not satisfied that the insurer
should be held responsible for the delays and cost escalations which have occurred since the
claim was accepted, and which now mean the cost of the claim-related repairs will exceed the
sum insured.
On balance, total loss decision is reasonable
There is no dispute that the complainant has a valid claim, nor is there a dispute as to the
extent of the damage to the insured building from the fire.
The insurer has confirmed it is prepared to treat the building as a total loss, since the repair
quotes mean that possible variations/contingencies arising in the course of the repair process
would likely mean the costs would exceed the policy limit (sum insured). The insurer says
there is a reasonable chance of this occurring. The panel notes the value of the most recently
quoted repair work is over $1,100,000.
There is no information from the complainant disputing this. The panel is satisfied the
insurer’s decision to treat the building as a total loss, and to cash settle, is reasonable in the
circumstances.
The issue in dispute is whether the insurer – because of its handling of the claim – should
accept liability (beyond the policy sum insured) for the increase in repair costs which has
since occurred.
Evidence shows substantial increase in repair costs following the initial quote
The insurer supplied four repair quotes in total for the work necessary to repair the damaged
building. The first of the quotes was completed by a builder (WI) on 22 February 2021. This
quote proposed a repair totalling $683,000, which was well below the policy limit of
$1,248,000.
The quote gave two options to complete the repair. One involved rebuilding units two and
three which were damaged in the fire, with a limited demolition of the shared wall between
units one and two.
The second option was to demolish all three units and replace them with a different design
using tilt up concrete. Both options are in line with the recommendations in the engineer’s
(SE) report dated 5 November 2020.
WI supplied an updated quote for the repair of units two and three, following the disputed
delays showing the repair costs had increased to $1,112,785.89 on 12 July 2022. This figure
was supported by comparative quotes (MC quoted $1,147,435.04 on 18 October 2022, and
BB quoted $1,141,410.79 on 23 November 2022).
T he complainant says the insurer’s handling of the claim (including lack of oversight and poor
communication) is the cause of the delays in finalising the claim, and therefore of the
increased costs which now apply. In the circumstances, it is appropriate to consider the
timeline of events. A broad summary is included in section 3 of this determination.
Determination | Case number: 905742 Page 3 of 8
Insurer’s contribution to delay s not sufficient to establish additional liability
The panel has reviewed all the available evidence and is satisfied the delay in repairing the
property is the result of multiple factors, only some of which we re in the insurer’s control.
The panel is satisfied the initial assessment and approval period is not unusual for a claim of
this kind. WI supplied their initial quote on 22 February 2021 showing the lengthy period it
expected would be needed to complete council approvals and then repair the property. They
also notified the owner of unit one that the tenant would need to vacate the property.
WI’s predictions on the approval process timeline appear justified, as the evidence indicates
there were lengthy delays getting council approval. The complainant argues this is due to
repeated document errors caused by WI and the insurer’s loss adjuster (AN) rather than the
alleged issues with the local council.
The complainant’s supporting evidence is limited, although there is an email from WI
accepting the initial demolition company had not met expectations. That suggests the insurer
might reasonably take some responsibility for initial difficulties in obtaining approval to
complete the demolition. This period would be from 25 March 2021 to 18 June 2021.
The council approval of the demolition was received on 15 October 2021, and work was
booked to commence on 15 November 2021. The panel is not satisfied there is sufficient
evidence showing this further delay was in the insurer’s control. The owners of unit one also
disputed the decision to repair unit one instead of demolishing it, meaning the insurer could
not proceed with the work until this was resolved in any case. This covered the period of 2
July 2021 to 22 September 2021.
The delays caused by the tenant of unit one are well documented and compelling. The
information paints a picture of a business acting with its own interests in mind, which is not, in
itself, inherently unreasonable, but which had the unfortunate flow-on effect of delaying the
repairs and generally complicating the matter.
Given the extent of demolition work required (which also included a shared brick wall between
units one and two), the panel is satisfied the insurer was justified in being concerned about
the unit one tenant remaining in occupation during the work. It was reasonable to seek
agreement for the tenant to vacate the premises while the repairs were completed.
The information in the timeline of events shows the unit one tenant went to considerable
lengths to avoid vacating the property, including engaging a solicitor and seeking a
substantial compensation value from both the unit one owner and the insurer. This is in
addition to repeated attempts to minimise their rental costs while the damage remained
unrepaired.
This delay began on 31 March 2021, continuing to 21 April 2022. After this, there was an
agreement made to adjust the repair process, so the tenant could remain in the property for
as long as possible. The insurer then offered an alternative repair method.
Following 12 April 2022, WI was completing the approval process to begin the work, with the
cost increases noted in AN’s report on 17 July 2022 leading to the current dispute.
Having considered the available evidence, the panel accepts each party has contributed, to
some degree, to the delays at various times. However, given the complications arising from
the input and actions of others (outside the insurer’s control), the panel is not satisfied the
insurer’s contribution was so substantial that it should be liable for repair costs exceeding the
policy limit.
Determination | Case number: 905742 Page 4 of 8
Complainant’s rebuttal has not advanced its position
The panel acknowledges the complainant’s concerns that the delay could have been avoided
with more proactive assessment and more effective communication by the insurer. However,
the panel is not persuaded that is necessarily the case: the insurer engaged suitably qualified
experts who made their assessment and recommendations. The insurer acted reasonably in
response to those assessments (including acknowledging some initial shortcomings) and
offered the more recent solution to the issues with the unit one tenant because the ongoing
delay had become excessive.
The panel does not consider the evidence shows the alternative repair method should have
been adopted earlier, nor that it was plainly obvious or necessary at the time. Instead,
multiple building experts and engineers did not consider the option the complainant now
prefers, prior to the 21 April 2022 agreement. The panel is more persuade d by the insurer’s
position, which is that the repair option was ultimately offered as a compromise because of
the ongoing delay created by an unco-operative tenant. The insurer had, in the first place,
acted appropriately and reasonably in advising the relevant party (the unit one owner) of the
need for the unit one tenant to vacate the premises to enable the initially proposed repair.
The panel is not satisfied the further loss to the complainant (from the increased costs of
repairs since the claim was accepted, and appropriate repairs first proposed) can fairly or
reasonably be attributed to any communication or other error by the insurer. AN notified unit
one’s owner about the requirement for that unit to be vacated during the demolition on 1 April
2021. By 9 November 2021 the unit one tenant had refused to comply and sought ways of
avoiding having to vacate. Arguably, the complainant itself (or at least, the unit one owner – a
member of the strata corporation) had ample time and opportunity to attempt a resolution with
the tenant. It is not fully clear how those parties addressed the matter in the meantime.
Until it was established the tenant would not comply with the requirement to vacate in order to
facilitate the recommended repairs, and the complainant was either unwilling or unable to
enforce compliance, it is not reasonable to expect the insurer would instruct the builder to
investigate alternative solutions.
The panel is not persuaded the insurer acted unreasonably or inappropriately in its handling
of the matter overall.
2.2 Is complainant due non-financial loss compensation?
An award of non-financial loss is not warranted
Under the AFCA Rules, we can consider compensation of up to $5,400 compensation for
non-financial loss. We will only award this type of compensation in limited circumstances,
including if a complainant suffers an unusual degree or extent of physical inconvenience, time
taken to resolve the situation or interference with the complainan t’s expectation of enjoyment
or peace of mind because the insurer mishandled the claim.
Making a claim can be stressful and time-consuming, even if an insurer handles the claim
correctly. AFCA does not award compensation for the ordinary degree of inconven ience that
comes with making a claim.
In this complaint, the panel is not satisfied the insurer acted unreasonably or inappropriately;
nor that it should be responsible for the delays, inconvenience and further loss which has
occurred for reasons outside its control. Compensation for non-financial loss is not warranted
in the circumstances.
Determination | Case number: 905742 Page 5 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 905742 Page 6 of 8
3.2 Summary timeline of relevant events
Date Action
9 October 2020 The insured property is damaged by a fire.
The complainant lodges a claim with the insurer.
16 October 2020 AN completed its initial review of the claim and damage to
the property.
5 November 2020 SC completes their assessment of the fire damage.
19 November 2020 Claim accepted by the insurer.
26 November 2020 Complainant supplied building plans to AN, which would
need to be sent a further three times as requested by AN.
23 December 2020 SC provides their report on the extent of the damage and
the repair options.
30 December 2020 AN completes their analysis of the cost of the repair options
and organises quotes.
25 January 2021 AN updates the repair options following the report from a
builder (PI).
9 February 2021 AN reviews the complaint for loss of rent and the request
from u nit one owner to claim reduced rent for the tenant.
12 February 2021 AN compi l es the options based on the repair quotes
obtained and requests instructions from the insurer.
22 February 2021 AN updates the latest quote from WI and requests further
instructions on the repair from the insurer.
26 February 2021 Insurer authorised repair with WI.
4 March 2021 AN organises payment for loss of rent to unit one relating to
unit one tenant pursuing reduction in rent for fire impact to
their retail and wholesale trade.
25 March 2021 WI advises tenant they will need to vacate as building
approval cannot be obtained until after demolition
completed and slab assessed.
AN notes discussions need to occur with unit one owner
about this.
31 March 2021 unit one owner contacts AN seeking further loss of rent
payments.
unit one tenant emails unit one owner to complain about
different timeframes given about when they will have to
Determination | Case number: 905742 Page 7 of 8
stop trading during the repairs.
1 April 2021 AN confirmed the original understanding was six months
would be needed for planning and permits but this changed
based on WI advice.
AN report s tates:
> unit one owner was advised of this on several occasions
why the timeframe for tenant to vacate has changed
> unit one owner advised tenant must vacate the premises
for repairs to proceed
> AN attempting to facilitate with unit one owner and the
tenant
> repair timeframe likely to be between 18 months to two
years
> review of claim for compensation by the tenant is that
the policy does not respond to this and tenants should
approach their insurer.
30 April 2021 AN reviewing options to dismantle the refrigeration units in
unit one .
18 May 2021 AN supplied recommendation about comparative quote for
unit one refrigeration units.
18 June 2021 WI met with local council and was permitted to lodge the
demolition perm it.
29 July 2021 AN notes unit one owner disputes the insurer’s decision to
only demolish unit two and three when repairing the
damage and IDR complaint foreshadowed.
31 August 2021 Air quality report obtained due to concerns raised with unit
one ’s trade being affected. No health hazards noted, but
enjoyment likely to be affected during the demolition.
22 September 2021 Insurer delivers its final decision letter upholding the
decision to demolish only u nit s two and three .
24 September 2021 AN sends an update about unit one refrigeration units to
the insurer asking for instructions.
15 October 2021 WI receives demolition approval from council, scheduled
for 15 November 2021.
9 November 2021 AN notes demolition works scheduled to begin on 19
November 2021 now on hold as unit one tenant has
refused to vacate.
24 December 2021 AN notes review of the roof which would not result in an
order for unit one tenant to vacate.
unit one tenant solicitors letter received s tating they were
Determination | Case number: 905742 Page 8 of 8
intending to continue with the lease.
AN requested whether the matter should be referred to the
insurer’s legal team.
1 March 2022 AN notes unit one owner and tenant may come to an
agreement to vacate if unit one and two wall repairs can be
done first.
21 April 2022 Parties agree to a compromise on the repair work to
resolve the impasse created by unit one tenant.
7 June 2022 AN notes waiting on demolition approval from the council.
unit one owner request for a site meeting with the unit one
tenants who wanted to pursue further rent reduction. Not
resolved.
17 July 2022 AN notes building cost increases have risen significantly
due to changes in labour and material cost. Variations may
now t ake the repair above the sum insured limit.
18 August 2022 Complaint is lodged with AFCA for review.