Determination 905431

Cash settlement amount for fire damage repairs and application of the under-insurance (co-insurance) clause

FirmQBE
Decided2023-03-09
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$300,980
Non-financial loss—
Amount claimed$404,441
SourceAFCA PDF

Summary

The complainant's commercial building was damaged by fire and the insurer offered a cash settlement reduced by an under-insurance clause. AFCA upheld the application of the clause but increased the offer by 20% for cost escalation, requiring payment of $300,979.56.

The insurer was entitled to apply the co-insurance clause using the CBS replacement estimate, but the offer was increased by 20% because the repair quote was dated.

Issues

Subjects and remedies

home or building damagesmall businesspay claim

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 905431 Financial firm QBE Insurance (Australia) Limited Case number: 905431 28 February 2023 Determination | Case number: 905431 Page 2 of 8 1 Determination overview 1.1 Complaint The complainant lodged a claim on 3 January 2021 under his business insurance policy with the financial firm (insurer) for fire damage to his commercial property (building). The insurer accepted the claim. However, a dispute has arisen about the scope of works (SOW) necessary to repair the damages to an appropriate standard, the reasonable cost of repairs and the way in which the insurer handled the claim overall. The complainant seeks the insurer to cash settle the claim based on his repair quotation of $404,440.84 from his builder, CBS. 1.2 Issues and key findings What is the insurer’s extent of liability? The insurer’s extent of liability in respect of the claim has been appropriately determined in line with the terms of the policy. Why is the outcome fair? The outcome is fair as the insurer is entitled to rely upon the terms and conditions of the policy and the exchanged information, to determine its obligations to the complainant, regarding the claim. 1.3 Determination This determination is in favour of the insurer. Within 14 days of the complainant’s acceptance of this determination, the insurer must pay the complainant cash settlement of $300,979.56 for the building repairs. Determination | Case number: 905431 Page 3 of 8 2 Reasons for determination Due to the nature of the complaint we have considered it appropriate to expedite this complaint in accordance with the Operational Guidelines to the AFCA Rules. Accordingly, this complaint has not been the subject of a preliminary assessment and has proceeded directly to determination. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions where applicable. While the parties have raised numerous issues in their submissions, for the purposes of this determination commentary has been restricted to those issues considered directly relevant to the outcome only. 2.1 What is the insurer’s extent of liability? The insurer’s extent of liability in respect of the claim has been appropriately determined in line with the terms of the policy. Coverage of the policy The complainant’s business insurance policy covers the comp lainant’s buildings for damage caused by insured event. One of the insured event being ‘fire’. The coverage provided by the policy is subject to conditions, limitations, and exclusions. This means that not all loss and damage is automatically covered. Rather, only loss and damage, subject to the conditions, limitations and exclusions, is covered. The full details of the policy coverage, conditions, limitations, and exclusions are contained within the Product Disclosure Statement (PDS) and Certificate of Insurance (COI). I am satisfied that the PDS and COI have been provided to the complainant. Therefore, the insurer is entitled to rely upon the terms of the policy, including its conditions, limitations, and exclusions, to determine its obligations to the complainant. The building is insured for $630,000 Property Section Particulars Total Sum Insured Excess Buildings $630,000 $1,000 Contents NIL NIL … Determination | Case number: 905431 Page 4 of 8 The PDS details: Conditions applying to this section 1. Co-insurance For each occurrence, we will pay the proportion of the loss or damage that the sum insured bears to 80% of: (a) the reinstatement or replacement cost of the business property where the method of settlement is reinstatement or replacement cost; or (b) the indemnity value of the business property, on the day the loss or damage occurs where the method of settlement is indemnity value. This condition will not apply if the amount of loss or damage is less than 5% of the sum insured. Parties disagree on reasonable cost of repair The insurer says the policy was incepted since May 2013 with the building sum insured of $630,000. It says at each renewal the complainant has been invited to review the policy in general and the building sum insured to make sure the sum insured represents the full replacement value of the building. In determining its liability to the claim, the insurer has relied on the under-insurance clause of the policy and the sum insured for the building. The insurer has considered a replacement and repair costs from a builder, CBS for $1,154,802.96 and $367,673.49 respectively, the amounts are GST exclusive. However, the insurer says: After deducting 50% for common fencing and the allowance for an alarm, the replacement amount reduced to $1,147,362.46 CBS repair estimate is indicated in the sum of $367,673.49. After deduction of $2,242.50 included for an alarm which is not part of the scope of works, repair costs are indicated in the amount of $365,431.00. Accordingly, the insurer has offered $250,816.30 (excluding GST) based on the below calculation factoring in the under-insurance formulae:  Repair cost x sum insurer / 80% of replacement value ($1,147,362.46)  = $365,432 x $630,000 / $917,889.92  = $250,816.05. The insurer says the under-insurance clause under the policy applies because the building sum insured of $630,000 is less than 80% of the insurable value of $1,174,362.46. The complainant disagrees with the terms of the policy and seeks cash settlement of $404, 440 (GST inclusive) as quoted by CBS. Determination | Case number: 905431 Page 5 of 8 Insurance Contract Act Section 44 of the Act notes the provisions for underinsurance, however, defines this as Average provisions as follows: 44 Average provisions (1) An insurer may not rely on an average provision included in a contract of general insurance unless, before the contract was entered into, the insurer clearly informed the insured in writing of the nature and effect of the provision including whether the provision is based on indemnity or on replacement value of the property that is the subject-matter of the contract. (2) Where the sum insured in respect of property that is the subject-matter of a contract of general insurance that provides insurance cover in respect of loss of or damage to a building used primarily and principally as a residence for the insured, for persons with whom the insured has a family or personal relationship, or for both the insured and such persons, or loss of or damage to the contents of such a building, or both, is not less than 80% of the value of the property, the liability of the insurer in respect of loss of or damage to the property is not reduced by reason only of the operation of an average provision included in the contract. (3) Where: (a) the sum insured in respect of property that is the subject-matter of such a contract is less than 80% of the value of the property; and (b) but for this subsection, an average provision included in the contract would have the effect of reducing the liability of the insurer in respect of loss of or damage to the property to an amount that is less than the amount ascertained in accordance with the formula where: A is the number of dollars equal to the amount of the loss or damage. S is the amount of the sum insured under the contract in respect of the property; and P is 80% of the number of dollars equal to the value of the property. the average provision has the effect of reducing the liability of the insurer to the amount so ascertained. Determination | Case number: 905431 Page 6 of 8 (4) In this section: value , in relation to property, means: (a) if the relevant contract provides for indemnifying the insured in respect of loss of or damage to the property ¾ the indemnity value of the property; or (b) if the relevant contract provides for reinstatement or replacement of the property ¾ the reinstatement or replacement value of the property; at the time when the relevant contract was entered into. CBS replacement quote is preferable In general terms, the parties agree on CBS repair quote. However, the complainant disagrees with CBS replacement quote. The complainant submitted a quote from MMS for replacement of the building for $823,000, which he says is more accurate and represents the fair cost of rebuilding the property in the present time. The complainant says the fact the insurer first provided a replacement quote for $1,617,362 then a reversed quote from CBS the settlement is based on shows the insurer’s replacement estimate is excessive and wrong. He said his replacement quote from MMS for $823,000 was based on the actual cost he had spent on a new building he built on the same road. Based on the information to hand, there is no compelling reason the replacement quote from MMS should be preferred. It lacks critical details and is demonstrably low. Further, I do not accept the replacement quote should be based on another building built on the same street a few years ago. The complainant says he insured the building based upon the amount he spent on a new building on the same road. Unfortunately, this is not sufficient to assess the replacement value. I consider CBS replacement quote more appropriate and preferable. The quote is authored by a suitably qualified professional and is based closely on the detailed repair audit and agreed scope of works . The complainant criticises CBS replacement amount as a basis to determine settlement of the claim and on a number of grounds, which I reviewed in light of AFCA’s approach to assessing evidence. AFCA approach to assessing evidence AFCA forms a view of the dispute based on the weight of available information. We consider documents, submissions, and all relevant circumstances. We tend to give more weight to reports authored by those with relevant expertise. Therefore, where there is a conflict between an opinion of a less qualified party and that of an expert, we tend to prefer the expert’s opinion unless there are compelling reasons to do otherwise. Determination | Case number: 905431 Page 7 of 8 In addition, AFCA makes findings about the key issues in dispute. This means where information provided by the parties is not directly relevant to those issues or is otherwise extraneous, I have not referred to it as part of my decision. With this in mind, I carefully reviewed the available evidence about the scope of works and costings. Insurer’s offer for building repair is fair in the circumstances Having carefully reviewed the available information, I am not satisfied that the complainant’s quote most accurately reflects the reasonable cost of replacing the building for the purpose of determining the insurer’s extent of liability. For the above reasons, there is insufficient evidence for me to prefer the complainant’s quotes over CBS. Secondly, I am satisfied the insurer has correctly assessed its extent of liability as represented in the settlement calculation above and has appropriately applied the terms of the policy. Therefore, I am satisfied that the insurer’s offer of $ 250,816.30 represents a reasonable starting point for determining an appropriate cash settlement amount. However, I note the CBS quote for repair was dated 1 November 2021. Accordingly, in my view, it is fair in all the circumstances the cash settlement for $250,816.30 be increased by additional 20% ($50,163.26) to allow for increased cost of labour and material. In summary, the insurer is required to cash settle the complainant’s claim f or the building repairs for $300,979.56. 2.2 Why is the outcome fair? The outcome is fair as the insurer is entitled to rely upon the terms and conditions of the policy and the exchanged information, to determine its obligations to the complainant, regarding the claim. Determination | Case number: 905431 Page 8 of 8 3 Supporting information 3.1 The AFCA processes AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.