Determination 903535
Home building claim for damaged retaining wall declined under policy exclusions
Summary
The complainant claimed for a retaining wall collapse after a February 2022 storm, which the insurer declined as caused by defective construction and gradual deterioration. AFCA found the exclusions applied and that the insurer did not mishandle the earlier 2020 claim, so the determination was in favour of the insurer.
The policy's accidental damage cover is subject to exclusions for retaining walls not built to engineering criteria and for wear and tear or deterioration, which the insurer established on the expert evidence.
Issues
- Claim denial primary · not upheld
“The insurer is entitled to decline the claim; damage was not sudden or unforeseen and policy exclusions for defective construction and wear and tear apply.”
- Inadequate claim investigation secondary · not upheld
“Expert evidence from PCBS, LJB, QAT and CRD confirmed building defects were the proximate cause of the collapse.”
- Poor communication secondary · not upheld
“The insurer clearly advised the complainant he could request the builders' report relied upon in the 2020 claim decision.”
- Product terms interpretation secondary · not upheld
“The policy excludes retaining walls where design and construction was not according to engineering criteria, and gradual deterioration or wear and tear.”
Subjects and remedies
home or building damagenatural disasterno remedy
Text of the determination
Determination
Case number 903535
Financial firm Youi Pty Ltd
Determination | Case number: 903535 Page 2 of 7
Case number: 903535 19 January 2023
1 Determination overview
1.1 Complaint
The complainant holds a home building insurance policy with the financial firm (the insurer).
The policy covers damage caused suddenly or accidentally providing it is not otherwise
excluded by the policy.
The complainant made a claim on the policy for a damaged retaining wall following a storm
that occurred on 26 February 2022.
The insurer declined the claim because it says the proximate cause was not the storm.
Instead, it was gradual deterioration over time due to defective or faulty workmanship and
wear and tear.
The complainant is seeking for the claim to be accepted because he says the damage was
caused by the storm.
1.2 Issues and key findings
Is the insurer entitled to decline the claim?
Yes. This is because the damage was not sudden or unforeseen. The policy excludes
damage to retaining walls where the design or construction was defective. Further, the policy
excludes gradual deterioration or wear and tear.
Did the insurer mishandle the 2020 claim?
No. The insurer:
clearly and unambiguously advised the complainant he was entitled to request a copy of
the builders‟ report relied upon to decline the claim.
sent a maintenance letter to the complainant saying the entire retaining wall needed to be
rebuilt, not only the failed section.
Why is the outcome fair?
It would not be fair to require the insurer to cover a claim for damage which has been shown
to fall outside the scope of cover under the policy. The insurer has not mishandled the claims
or provided any misleading information to warrant the damage being accepted.
1.3 Determination
The determination is in favour of the insurer. The insurer is not required to take any further
action in relation to this complaint.
Determination | Case number: 903535 Page 3 of 7
2 Reasons for determination
2.1 Is the insurer entitled to decline the claim?
Yes. This is because the damage was not sudden or unforeseen. The policy excludes
damage to retaining walls where the design or construction was defective. Further, the policy
excludes gradual deterioration or wear and tear.
Onus on the insurer to establish policy exclusions limit its liability
When making a claim, an insured party has the onus of establishing they suffered a loss that
is covered by their insurance policy. This is known as a valid claim.
If a valid claim is established, the insurer has the onus of establishing the application of any
exclusion it relies on to reduce its liability.
The policy in this complaint is an „accidental damage‟ policy, meaning it covers all accidental
damage that occurs during the period of insurance, unless it is specifically excluded.
The word “accidental” is defined in the policy as:
… an unfores een, unintended, and unexpected event which occurs suddenly and at a
specific place and time.
There is no dispute that the insured building was accidentally damaged during the period of
insurance.
The onus rests with the insurer to establish policy exclusion applies to limit its liability.
The insurer says a policy exclusion applied
The insurer denied the complainant‟s claim relying on the following policy exclusions:
General exclusions
These general exclusions apply to all sections of your policy.
…
We will not pay for loss or damage:
…
21. to retaining walls where the design and construction of the wall was not according to
engineering criteria that applied at the time of construction; or
…
We will not pay for … loss or damage to property, caused directly or indirectly by:
…
37. wear and tear, rust corrosion, or deterioration …
The complainant was informed of the insurer‟s decision in a letter dated 1 May 2022.
Determination | Case number: 903535 Page 4 of 7
Evidence shows damage occurred gradually due to inherent defects
The complainant says the claim should be accepted because of the extreme weather event
and there was no evidence of defective workmanship, gradual deterioration, wear and tear or
wood decay prior to collapse of the retaining wall in February 2022.
The complainant submitted a pre-purchase inspection report completed by PCBS dated 4
September 2019. It is noted this report formed part of the complainants‟ submission for a
previous insurance claim he made with the insurer in March 2020.
The PCBS report:
confirms the presence of wood decay in the retaining walls as well as several other
external structures
notes the construction of the retaining wall is potentially non-compliant due to its height
and proximity to the house
recommended further invasive inspection to determine the extent of damage and to ensure
it was fit for purpose.
It is noted the complainant has not provided any evidence to show a suitably qualified
professional had been engaged to verify the extent of damage or certify the retaining wall
prior to its collapse. Further, the complainant has not provided any evidence to show the
wood decay had been rectified.
The insurer appointed LJB (a builder) to determine the cause of the damage as part of its
assessment of thee March 2020 claim. LJB confirmed the presence of mould and wood
decay in 10 posts, including 2 posts that had collapsed. LJB was of the opinion that the other
8 posts would fail “shortly”. It determined the proximate cause of the damage was
deterioration and wear and tear.
The insurer denied the March 2020 claim as it had assessed the proximate cause of the
damage was excluded by the policy. The insurer then sent a maintenance letter dated 6 April
2020 to the complainant advising him to rebuild the entire retaining wall and not just the
damaged section.
The available information shows the complainant opted to only rebuild the damaged section
rather than the entire wall , contrary to the insurer‟s advice in the maintenance letter .
The insurer appointed a builder (QAT) to inspect the damaged retaining wall in relation to the
complainant‟s 27 February 2022 claim. QAT attended the complainant‟s property on 10
March 2022. It:
confirmed the findings from PCBS and LJB stating wood decay was present in the base of
the posts from the undamaged section of the retaining wall
identified defects such as incorrect back fill material and the omission of sufficient
drainage.
concluded the cause of the retaining wall failure was its overall condition and a build-up of
hydrostatic pressure from inadequate drainage and the destabilisation of the ground
caused by the removal of a large tree.
QAT‟s report also includes several photographs. Those photographs show:
wood decay at the base of the undamaged section of retaining wall
no visible signs of drainage measures at the collapsed sections of the retaining wall.
While the photos do not show the base of the collapsed posts I am satisfied on the balance of
probabilities it is likely they would have had similar decay present.
Determination | Case number: 903535 Page 5 of 7
The insurer further engaged an engineer (CRD) who attended the complainant‟s property on
24 March 2022. CRD:
identified that the retaining wall was constructed in 1995 (using tags located at the base of
the retaining wall posts)
noted “Tradac Technical Datasheet 9 – Timber Retaining Walls” (published in March 1989)
stated the maximum allowable length of a retaining wall section was 2,700mm with vertical
posts with a minimum diameter of 250mm and must have drainage measures in place
noted the complainant‟s retaining wall
> had six continuous sections measuring 3,000mm each (ie, the distance between vertical
posts was 3,000mm)
> was 1,500mm high,
> had 150mm diameter vertical posts
noted the collapsed sections of the retaining wall was back filled with soil rather than loose
gravels and did not appear to have any drainage pipes in place
concluded the retaining wall was not constructed in accordance with industry standards at
the time of construction and this was the proximate cause of the damage to the retaining
wall.
The insurer was entitled to deny the complainant’s claim
I do not accept the complainant‟s position that the damage was caused by an extreme
weather event. This is because the available expert evidence confirms several building
defects were the proximate cause of the collapse, and no evidence has been submitted to
show the damage would have occurred regardless of the defects.
I am satisfied the insurer is entitled to rely on the policy exclusions to deny the claim. Had the
retaining wall been built in accordance with the relevant standards in place at the time it was
constructed, the damage would most likely not have occurred.
2.2 Did the insurer mishandle the 2020 claim?
No. The insurer:
clearly and unambiguously advised the complainant he was entitled to request a copy of
the builders‟ report relied upon to decline the claim
sent a maintenance letter to the complainant saying the entire retaining wall needed to be
rebuilt, not only the failed section.
The complainant says the insurer failed to provide a copy of the builders’ report
The complainant says he was not provided with a copy of the LJB report the insurer relied
upon to deny his March 2020 claim and was unaware of the report ‟ s existence until the new
claim was declined.
The available information shows the insurer sent a letter to the complainant outlining its
decision to decline the claim on 6 April 2020. This letter clearly and unambiguously says a
builder‟s report was relied upon to reach the decision to decline the claim.
The letter also outlined the complainant ‟ s entitlement to request a copy of any information the
insurer has used to reach its decision.
Determination | Case number: 903535 Page 6 of 7
The general insurance code of practice outlines various standards. One of which is that the
insurer must provide a copy of any expert report within 10 business days of receiving a
request from the claimant.
No evidence has been submitted to show the complainant made a request for this
information.
I am satisfied the insurer has not mishandled the claim in this respect and it has acted in
accordance with the insurance code of practice.
The insurer also sent a maintenance letter to the complainant advising the entire retaining
wall needed to be rebuilt. This means the complainant was put on notice that any future
damages arising from the incomplete maintenance will not be covered under the policy.
It is noted the complainant did not act on the advice provided in the maintenance letter.
The insurer acted reasonably in requesting the retaining wall to be rebuilt
The complainant says the insurer is not entitled to request the complainant rebuild the entire
retaining wall because there were no expert reports at the time to show this was required.
The complainant says given there were no expert reports to say it needed to be rebuilt, the
insurer should have refused renewal until the retaining wall was rebuilt or to continue the
cover and include indemnity for the retaining wall.
I do not accept the complainant‟s position . This is because the insurer sent a maintenance
letter to the complainant dated 6 April 2020 which outlined the entire retaining wall needed to
be rebuilt, not just the section which failed in 2020. The letter clearly states any damage
arising from the failure to undertake the required maintenance issues will not be covered by
the policy.
It is noted the complainant did not rebuild the entire retaining wall. Instead, he repaired only
the failed section, leaving the remainder of the defective retaining wall in place.
Further, I am satisfied the complainant was aware of the issues pertaining to the retaining
wall as they were also outlined in the pre-purchase inspection report prepared by PCBS.
I am satisfied the insurer acted reasonably in requesting the complainant to complete the
necessary maintenance repairs as identified in the expert report. This is because it is the
complainant‟s responsibility, under the policy, to maintain the property.
2.3 Why is the outcome fair?
The available evidence shows on balance the damage was caused by a combination of
defective design, inadequate construction, gradual deterioration or wear and tear. All of which
are specifically excluded by the policy.
It would not be fair to require the insurer to cover a claim for damage which has been shown
to fall outside of the scope of cover under the policy.
Determination | Case number: 903535 Page 7 of 7
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.