Determination 902266

Cash settlement of malicious damage claim

FirmIAG
Decided2023-04-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$54,000
Non-financial loss$2,000
Amount claimed$160,000
SourceAFCA PDF

Summary

The complainants claimed malicious damage to their renovating home and sought over $160,000 including mould remediation, temporary accommodation and professional fees. AFCA found the cash settlement offer of repair costs reasonable, rejected mould and TA claims, and ordered the insurer to waive the excess and pay $54,000 plus $2,000 non-financial loss.

The insurer may cash settle under the PDS, the complainants did not show a causal link for mould or entitlement to TA, and the policy excess must be waived given the known perpetrators and prior representation.

Issues

Subjects and remedies

criminal recordhome or building damagenatural disasterpay claimpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 902266 Financial firm Insurance Australia Limited Determination | Case number: 902266 Page 1 of 7 Case number: 902266 13 April 2023 1 Determination overview 1.1 Complaint The complainants hold home building insurance with the financial firm (insurer). They lodged a claim for malicious damage which occurred on 9 November 2021, while the property was being renovated. The male complainant, NS, had a disagreement with some painters, who then assaulted him and damaged the property. As the house was being renovated at the time it was damaged, the insurer proposes to cash settle the claim. It recently offered $53,000. The offer was based on its building consultant’s repair cost estimate and included a 20% contingencies uplift, a four week allowance for temporary accommodation (TA) costs and $2,000 in non-financial loss compensation. The complainants say the insurer’s unreasonable delays resulted in extensive mould growth . They seek over $160,000, based on their repair quote (including mould remediation), ten months of TA costs, professional fees reimbursement and non-financial loss compensation. 1.2 Issues and key findings Is the insurer ’s repair cost settlement offer reasonable ? Yes, overall. The complainants have not shown that the insurer is liable for mould remediation or that its estimate of repair costs is otherwise unreasonable. However, the insurer is required to waive the $1,000 excess as it previously offered to do so, in keeping with the policy terms. Are the complainants entitled to more in TA costs? No. The complainants have not shown the malicious damage rendered their home unliveable or that the insurer’s offer of four weeks of TA at $1,000/week during repairs is unreasonable. Is the insurer required to reimburse professional fees? No. The panel is not satisfied that the complainants ’ expert quantity surveyor or legal representative assisted them in establishing a more substantial coverage entitlement. Is more non-financial loss compensation payable? No. To the extent the insurer may have mishandled the claim and caused the complainants stress, its $2,000 offer represents reasonable compensation. Why is the outcome fair? Other than waiving the excess, the insurer’s cash settlement offer is reasonable. It would not be fair to require it to pay more when the complainants have not shown a greater entitlement. 1.3 Determination This determination is substantially in favour of the insurer. Within 14 days of the complainants accepting this determination, the insurer is to pay them $54,000 ($53,000 plus the $1,000 excess amount). Determination | Case number: 902266 Page 2 of 7 2 Reasons for determination The complainants are represented by WJ, lawyers. In this determination, the complainants and WJ are referred to as ‘the complainants’, un less context requires otherwise. The parties provided numerous submissions to AFCA. While this determination does not refer to them all, the panel has taken each submission into account in reaching their decision. 2.1 Is the i nsurer’s repair cost settlement o ffer reasonable? Yes, overall. The complainants have not shown that the insurer is liable for mould remediation or that its estimate of repair costs is otherwise unreasonable. However, the insurer is required to waive the $1,000 excess as it previously offered to do so, in keeping with the policy terms. Parties disagree on cost of repairs Following claim lodgement, the insurer appointed builder AI to assist with the assessment process. On 22 November 2021, AI inspected the property and reported that:  NS said he had purchased the property earlier in 2021 and had since been renovating it  the property had been unoccupied during the renovations  painters engaged by NS turned on him during a meeting to discuss workmanship issues. The painters assaulted NS, damaged walls throughout the house and were arrested  the damage ranged from scratches to deep gouges  if the claim was to be accepted, it recommended cash settlement as patching the damage may not match the existing texture of the walls such that it could not warrant repairs  TA was not currently required as the home was unoccupied due to renovations. Nor would it be required during repairs. On 1 December 2021, AI prepared a scope of works (SOW) for the required repairs to the walls and a window frame. AI quoted $13,203.17. The insurer’s claim notes show that the complainants were informed on 10 December 2021 that the insurer intended to cash settle their claim based on AI’s SOW and quote. The complainants were dissatisfied so the insurer indicated it was willing to consider an itemised counter quote from a builder of the complainants’ choosing. The complainants provided an SOW dated 8 February 2022 from NR, builders. NR quoted $121,400 as the cost of repairs but provided no itemisation. The insurer requested itemisation. It also asked AI to revisit its SOW. AI provided an updated SOW dated 19 April 2022, quoting $19,812.31 for repairs. On 29 April 2022, the insurer offered to cash settle the claim for that amount. It said it would be unable to manage and warrant repairs due to the extent of the damage, challenges relating to matching finishes, and given that the property was under ongoing renovation. The complainants obtained an SOW dated 22 June 2022 from BY, builder. BY provided an itemised quote totalling $171,362. The complainants also obtained a report dated 25 July 2022 from JB, quantity surveyor and builder. JB inspected the property on 2 July 2022 and reported that:  in addition to the wall and window frame damage, there was also mould growth, water damage and ceiling damage  it estimated the cost to repair the abovementioned damage would be $127,239  BY’s SOW included items outside the required rectification work Determination | Case number: 902266 Page 3 of 7  AI’s quote was insufficient to cover the rectification work and not a genuine quotation  while NR had not provided an itemisation, its quoted figure was within the realistic repair cost range of $120,000 to $130,000. The insurer denied it was responsible for the mould or water damage. It offered to lodge a separate claim to assess that damage, but the complainants maintained the damage was relat ed to the painters’ malicious actions . On 17 August 2022, the insurer offered to increase its cash settlement offer by 15% to allow for contingencies. This took the amount to $22,784.16. On 26 August 2022, it offered to increase the uplift to 25%, taking the amount to $24,765.39. On 23 November 2022, CM, a builder associated with JB, provided an itemised quote solely for mould rectification works. The total quoted was $40,771. The insurer proposed engaging a building consultant to inspect the property and report on the reasonableness of the various quotes. The complainants refused to access to the property. On 16 February 2023, building consultant CF provided a desktop report to the insurer. CF analysed the available quotes. It concluded that the complainants’ quotes were ‘grossly excessive, both for inclusions and rates applied ’ . It also determined that AB quote may have understated plastering and painting works. CF estimated repair costs at $39,504.30. On 28 February 2023, the insurer offered to cash settle repair costs for CF’s estimated amount plus a 20% contingencies uplift. The insurer also offered to cover four weeks of TA ($4,000) and $2,000 as non-financial loss compensation. After deducting the $1,000 excess and rounding up, the total amount offered was $53,000. On 8 March 2023, JB responded to CF’s report. JB questioned CF’s exper tise and local knowledge given it was based in a different state to the location of the insured property. JB nevertheless reduced its quote to $118,648. Insurer’s repair cost settlement offer is overall reasonable The panel is satisfied that it is appropriate for the insurer to cash settle the claim. This is because the PDS permits it to do so and in light of the reasoning the insurer has put forward. To be entitled to a higher cash settlement amount, the complainants must demonstrate that the insurer’s off er does not reasonably reflect the likely retail costs of repairs. This requires the complainants to show one or more of the following:  the SOWs the insurer relies on do not adequately encompass the required repairs  the quotes the insurer relies on are under priced  the insurer has failed to include a reasonable contingencies uplift. The co mplainants submit that the insurer’s SOWs are inadequate because they do not allow for mould rectification. They say: before the malicious damage occurred, there was no mould present in the premises. After the malicious damage occurred and the premises were left vacant for several months including as a result of [the insurer]’s improper delays, mould developed at the premises. We submit this is not a matter of expert evidence as, self-evidently, without the existence of the malicious damage and the improper delays, the mould would not be there. [The insurer] should bear the consequences of its conduct and that delay… Determination | Case number: 902266 Page 4 of 7 The panel does not agree with the complainants. There is no evidence to show a causative link between the malicious damage and subsequent water ingress and mould growth. Given that the malicious damage involved scratching and gouging to internal walls and a window frame, the panel on balance considers it unlikely any such link exists. The panel is also not satisfied the insurer improperly delayed progression of the claim. It made a claim decision well within the standard timeframe referred to in the General Insurance Code of Practice. Within a month of the claim being lodged it had also obtained an itemised quote and explained why it intended to cash settle. The complainants did not provide an itemised quote until 22 June 2022, over six months later. Nor have they explained why they could not maintain the property to prevent mould growth. It remains open to the complainants to lodge a separate claim for mould damage. Whether it may have been caused by a separate insured event can then be assessed. The complainants also say that, leaving aside mould remediation, their SOWs more accurately reflect the repairs required. However, their SOWs include extensive allowances for areas such as flooring that were not maliciously damaged. It appears those items may relate to defective workmanship during the renovation works, to which the policy does not respond. The panel finds CF’s detailed analysis explaining why the complainants’ SOWs/quotes are excessive to be persuasive. It is notable that JB also in effect concluded that BY’s quote was too high. JB also confirmed that full replacement of the internal wall rendering is not required. The panel is not satisfied that the insurer’s proposed cash settlement is based on under - pricing given that CF’s costing was p repared only two months ago. On the available information, the panel considers a 20% uplift sufficient to take into account contingencies and the loss of the lifetime guarantee that would apply to insurer approved repairs. The complainants have not suggested otherwise. The panel is therefore satisfied the insurer’s repair cost cash settlement offer is reasonable. Insurer is required to waive the policy excess The PDS states an excess is not payable if the claim is for an incident for which someone else is r esponsible and that person’s name and address is known. The names and addresses of the perpetrators of the malicious damage were provided. On 2 December 2021 and on 16 February 2022, the insurer wrote to the complainants confirming the malicious damage claim had been accepted and the excess had been waived. In calculating its overall $53,000 cash settlement offer, the insurer deducted the $1,000 excess. The panel is satisfied that, consistent with the PDS and the insurer’s previous representation, the excess is to be waived. 2.2 Are the complainants entitled to more in TA costs? No. The complainants have not shown the malicious damage rendered their home unliveable or that the insurer’s offer of four weeks of TA at $1,000/week during repai rs is unreasonable. Policy provides TA costs cover in certain circumstances The TA additional benefit is set out in the PDS applies when a listed event causes damage to the insured home, such that the insured is unable to live in the home and must move out Determination | Case number: 902266 Page 5 of 7 while it is repaired. The availability of the cover is also subject to conditions, including that the insured must have lived in the home permanently before the listed event occurred. Complainants seek ten months’ TA The complainants say the insurer represented to them that their TA costs would be covered. They say relying on that representation and as their home was unliveable, they incurred TA costs from 22 November 2021 (the date on which they intended to move in) to 5 September 2022. They seek a total of $23,336.57 in TA costs. That equates to approximately $569/week. Insurer has offered TA costs for estimated repair period The insurer denies that it represented that the complainants’ TA costs would be covered. Further, it says that the TA additional benefit is not applicable because:  the complainants were not living in the home before the malicious damage occurred  as AI had confirmed, the home was not rendered unliveable. In addition, the insurer says the complainants have not provided adequate documents in support of the TA costs claim. It notes that the complainants have refused to provide rental agreements or invoices. Further, the redacted bank statements they did provide merely show amounts described as ‘rent’ were paid to an accommodation prov ider by a company. However, the insurer asked AI to provide an estimate of the extent, if any, TA would be reasonably required during repair works. AI responded that TA was unlikely to be required, but ‘ if you are looking to be accommodating to the insured to minimise disruption, we would say approx. 3 weeks for the repairs ’ . Given AI’s three week estimate, but allowing a contingencies uplift, the insurer has offered to pay TA for four weeks. Adopting a rental rate of $1,000/week, that amounts to $4,000. In surer’s TA costs offer is reasonable The panel has carefully reviewed the insurer’s claim notes and correspondence. They have also listened to a recording of a call on 11 February 2022, in which the complainants say they were advised their TA costs would be covered. The panel is not satisfied from those materials that the insurer told the complainants that their TA costs would be covered or otherwise misled them in that regard. At most, the insurer in effect confirmed that the policy included the TA additional benefit. In addition, the panel agrees with the insurer that the TA additional benefit does not apply as the complainants were not living in the home when it was damaged. Further, there is no cogent evidence that the malicious damage rendered the home unliveable. Even though AI suggests future TA will likely not be necessary, there is sufficient uncertainty to justify an allowance being made. On the available information, the panel considers the insurer’s offer to pay the complainants $4,000 for potent ial future TA needs reasonable. 2.3 Is the insurer required to reimburse professional fees? No. The panel is not satisfied that the complainants’ expert quantity surveyor or legal representative assisted them in establishing a more substantial coverage entitlement. Determination | Case number: 902266 Page 6 of 7 AFCA may require insurer to contribute to a complainant’s professional costs The AFCA Rules enable AFCA to require an insurer to contribute to the professional costs incurred by the complainant. These costs are, however, usually capped at a total of $5,000. When considering whether to require an insurer to make a costs contribution, AFCA takes into account the complexity of the complaint, and whether the particular complainant needed to incur costs to understand or establish their claim. Insurer is not required to reimburse professional costs The complainant wants the insurer to reimburse professional costs they incurred in obtaining expert reports from JB and in being represented by WJ. However, neither JB or WJ assisted the complainants in establishing an entitlement to cover beyond what the insurer offered. The panel is also not satisfied that the complainants needed to involve JB or WJ to understand the claim or the insurer’s position in relation to it. Accordingly, the insurer is not required to reimbur se the complainants’ professional costs. 2.4 Is more in non-financial loss compensation payable? No. To the extent the insurer may have handled the claim better and caused the complainants stress, its $2,000 offer represents reasonable compensation. AFCA can award compensation for poor claim handling Under paragraph D.3.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $5,400) where the insurer’s actions have caused an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant’s expectation of enjoyment or peace of mind. Insurer is required to pay compensation it offered The complainants say the insurer caused unreasonable delays, misled them and acted unethically. They say they have suffered immense stress and inconvenience as a result. The panel accepts that the complainants have found the claim process stressful and that the claim event must have been very traumatic. However, as noted above, the panel is not satisfied that the insurer caused unreasonable delay or misled the complainants. The insurer has acknowledged that the complainants have found the claim process challenging, stressful and inconvenient. It has offered them $2,000 in compensation. The panel considers that offer reasonably addresses stress the complainants may have experienced due to potential shortcomings in the insurer’s claim handling. The insurer is required to pay them $2,000 in total as non-financial loss compensation. 2.5 Why is the outcome fair? Other than waiving the excess, the insurer’s cash settlement offer is reasonable. It would not be fair to require it to pay more when the complainants have not shown a greater entitlement. Determination | Case number: 902266 Page 7 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.