Home / IAG / Determination 901223

Determination 901223

Delay in repairs following accepted storm damage claim; compensation for non-financial and indirect loss

FirmIAG
Decided2023-05-03
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$10,000
Amount claimed—
SourceAFCA PDF

Summary

A storm damage claim was accepted but repairs were delayed about 19 months. AFCA ordered $5,000 non-financial loss to each of the two complainants but rejected unproven indirect loss claims.

The insurer and its agents caused significant delay warranting non-financial loss compensation under Rule D.3.3, but indirect losses were not proved.

Issues

Subjects and remedies

home or building damagepay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 901223 Financial firm Insurance Australia Limited Determination | Case number: 901223 Page 2 of 6 Case number: 901223 11 April 2023 1 Determination overview 1.1 Complaint In August 2021, the complainants made a claim to the financial firm (the insurer) for damage caused by a gum tree falling onto their home‟s roof during a storm under a policy they jointly held. The claim was accepted by the insurer but there have been considerable delays in repairing the damage. This complaint is about:  whether the insurer‟s offer of $1,000 co mpensation for the male complainant ‟s non- financial loss is fair  if not, the fair and reasonable amount of compensation for the complainant‟s non-financial loss  whether the complainants are entitled to receive compensation for their indirect loss. The complainant says he and his wife should receive $5,000 each for their non-financial loss and $6,459.16 for their indirect financial loss and costs incurred to pursue the complaint. 1.2 Issues and key findings Should the insurer pay compensation for the complainant’s non -financial loss? Yes. The insurer must pay $5,000 to each of the complainants for their non-financial loss. The insurer is not required to pay compensation to the complainant‟s wife for her non - financial loss because she is not the complainant. The AFCA Rules only permits compensation for non- financial loss to “the complainant”. Should compensation be paid for indirect financial loss and costs incurred? No. The complainants have not proved the indirect losses they have claimed. Why is the outcome fair? I accept the complainant and his family have unduly inconvenienced by the delays caused by the insurer and its appointed agents. It is fair the insurer pays compensation for the complainants‟ non-financial loss. The complainants have not provided sufficient proof of their indirect losses. 1.3 Determination This determination is substantially in favour of the complainant. The complainant has 30 days to accept the determination. If the complainant accepts the determination, the insurer must pay each complainant $5,000 compensation for their non-financial loss. Determination | Case number: 901223 Page 3 of 6 2 Reasons for determination 2.1 Should the insurer pay compensation for the complainant’s non-financial loss? Th e insurer has mishandled the complainant’s claim The claim was made on 5 August 2021 and accepted by the insurer. As at 12 January 2023, the repairs to the complainant‟s home had not commenced . Scaffolding was erected in early March 2023 with a proposed commencement for repairs on 23 March 2023. A claim handling chronology is set out in Section 3.2 below. The insurer broadly accepts it has mishandled the claim, though it has pointed to some delays that have been out of its control, specifically delays caused by a local council in providing planning approvals. However, I am satisfied that this only contributed about 130 days to the delay. It has offered $1,000 to the male complainant as compensation for his non-financial loss. I am satisfied, from the available information, that the insurer and its authorised agents have contributed significantly to the del ay in commencing the repairs to the complainant‟s home . The following failures by the insurer‟s authorised agents have contributed to the delay:  the engineers: > did not highlight that a more complete report would be required because they were unable to conduct a thorough inspection of the damage as there was a tarpaulin covering the damaged roof > failed to identify the complainant‟s home was in a bushfire zone and that council planning applications would be required before repairs could commence  the initial planning development application submitted to the local council was not compliant with planning laws  a second planning application was not submitted until three months later The insurer contributed to the delays by:  taking 56 days to engage PG (building consultants) following a recommendation to make the engagement from JLG (the insurer‟s builders)  taking 39 days to finalise and submit a planning application to the local council  failing to engage trades in a timely manner after receiving council planning approval  failing to engage with JLG to commence repairs in a timely manner. The complainants are entitled to compensation for non-financial loss The complainants held the insurance policy jointly. This means they are both complainants and, under AFCA Rule D.3.3, I am able to award compensation for non-financial loss to each of them. I accept the complainants have suffered considerable interference with their expectation of enjoyment of their home and this is a clear result of the time the insurer has taken to resolve the situation. I do not accept the insurer‟s offer of $1,000 compensation for the male complainant‟s non - financial loss is adequate having regard to the length of the delays he and his wife have experienced and the manner in which the insurer has handled the claim. It was about 19 Determination | Case number: 901223 Page 4 of 6 months from when the claim was made to the date that scaffolding was erected for the repairs to commence. I further note, that the complainants ‟ roof was only covered by a tarpaulin for the entirety of that 19-month period which has included an extended period of wet weather due to the recent La Niña event. This would have added considerably to the complainants ‟ frustration and anxiety. In the circumstances, it is appropriate the insurer pay $5,000) to each of the complainants for their non-financial loss. 2.2 Should compensation be paid for indirect financial loss? The complainant seeks compensation for indirect loss and costs to pursue the complaint The complainant has made a claim for the following „consequential damage claims‟ :  $1,303.16 for his time taken to contact JLG  $279.00 for the additional costs of electricity due to “tarp on roof and damaged … ceiling and window area not airtight”  $45.00 for additional gas costs, also due to the damage  $4,332.00 for “[t]ime taken off work but had to make up time at work (Time in Lieu) for attending technicians, tradesmen and contractors” for 76 hours at $57 per hour. The insurer has not responded to the complainant‟s claim. I consider that each of the above claims are claims for indirect (or consequential) loss. Under the AFCA Rules, I am able to award up to $5,000 for indirect loss. However, rule D.3.2(a) does not permit me to award compensation for an indirect loss where the general insurance policy expressly excludes such liability. I note the policy excludes cover for consequential loss. The complainants have not proved their claimed indirect losses However, AFCA is able to award compensation for indirect financial loss (even when it is excluded from cover) if it is caused by the insurer‟s error, rather than being caused by the insured event. I am satisfied that the costs claimed are caused by the insurer‟s error. However, it would not be fair to award these costs without proof that they have been incurred. All loss must be proved, including indirect losses. As the losses have not be proved, I cannot award compensation for the complainants‟ claimed indirect losses. 2.3 Why is the outcome fair? The outcome is fair I accept the complainant and his family have unduly inconvenienced by the delays caused by the insurer and its appointed agents. It is fair the insurer pays compensation for the complainants‟ non -financial loss. The complainants have not provided sufficient proof of their indirect losses. Determination | Case number: 901223 Page 5 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness I have determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). There has been a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. 3.2 Claim chronology Date Description 5/8/2021 Claim received by the insurer 6/8/2021 JLG (the insurer‟s builders) appointed by the insurer to assess damage 11/8/2021 JLG conduct virtual assessment 14/8/2021 Onsite JLG assessment conducted following request by the complainant 20/8/2021 JLG say engineer required to attend 31/8/2021 Engineer report receive d and JLG updated report and scope of works (SOW) provided 6/9/2021 The insurer reviewed reports, accepted the claim and authorised repairs 23/9/2021 JLG identified that a bushfire rep ort required with surveying, drawing and D evelopment A pproval b efore repairs can begin 28/9/2021 Engineer and bushfire consultant inspected the damage 30/9/2021 Updated reports for council approval received by the insurer 8/10/2021 The insurer approve plan s for submission to the local council 10/11/ 2021 Plans submitted to council by the insurer 27/1/2022 JLG identified additional damage t o property Determination | Case number: 901223 Page 6 of 6 18/02/ 2022 PG (building consultants) engage d to find solution to meet liability requirements for „ flamezone ‟ upgrade 24/2/2022 PG report provided to JLG for review 7/3/2022 JLG said independent engineer or PG required to sign off on proposals in PG report 2/5/2022 PG engaged to provide sign off on above report 3/5/2022 JLG contact ed the complainant and advise d of proposed metal roof replacement 3/5/2022 The complainant reject ed the metal roof replac ement 30/5/2022 The complainant accepted the metal roof replacement 8/7/2022 New SOW, building plans and permit applications submitted to Council 5/9/2022 Council approval received 10/10/ 2022 JLG complete d final inspection 16/11/ 2022 JLG informed the complainant repairs would begin on 28 November 2022 27/11/ 2022 JLG informed the complainant new carpenter required and repairs would start on 29 November 20 2 2 29/11/ 2022 Carpenter says scaffolding was required before works could commence 16/12/ 2022 JLG unable to find scaff older and was engaging new builder 17/01/ 2023 R epairs have not begun and new contractor was being appointed 9/03/2023 Scaffolding installed. Repairs estimated to commence on 13 March 2023

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.