Cash settlement amount for fire damage repairs, further temporary accommodation costs and delay in claim handling
Text of the determination
Determination
Case number 900991
Financial firm Allianz Australia General Insurance Limited
Determination | Case number: 900991 Page 1 of 8
Case number: 900991 31 March 2023
1 Determination overview
1.1 Complaint
The complainants hold a Home and Contents Insurance policy with the financial firm (insurer).
A claim was lodged in July 2022, for a fire event. The insurer accepted the claim and there
was a delay while the complainants tried to obtain a cash settlement.
The complainants seek additional temporary accommodation.
The insurer says it has exhausted the temporary accommodation costs under the policy and it
is not prepared to offer further costs.
The insurer made a cash settlement offer of $779,781.31 for repairs, this includes a 15%
contingency amount. However, the complainants remain dissatisfied.
The complainants are seeking a further $10,000 in temporary accommodation costs, plus
non-financial loss compensation due to the way the insurer handled the claim.
1.2 Issues and key findings
Should the insurer increase its cash settlement for repairs?
Yes. There are items not included in the final settlement offer. The insurer is to work with the
complainants to finalise the few remaining items. A 20% contingency is fair in the
circumstances.
Should the insurer cover further temporary accommodation costs?
Yes. It is fair the insurer pays for temporary accommodation the complainants requested.
Should the complainants be awarded non-financial loss compensation?
Yes. The insurer did delay the claim. It is fair the complainants are awarded $2,000 each.
1.3 Determination
This determination is in favour of the complainants.
Wit hin 21 days of the complainants‟ acceptance of this determination the parties are to work
together to determine the final remaining aspects of the scope of works as set out in section
2.2. of this determination.
The insurer is to cash settle the remaining repair scope of works while parties work out the
final amounts, so repairs can commence in the meantime. Once a final figure is obtained, the
insurer is to also pay a 20% uplift on the final figure.
The insurer is to also pay the complainants:
$10,000 for temporary accommodation.
$4,000 compensation for non-financial loss.
Determination | Case number: 900991 Page 2 of 8
2 Reasons for determination
2.1 Should the insurer increase its cash settlement for repairs?
Yes. There are items not included in the final settlement offer. The insurer is to work with the
complainants to finalise the few remaining items. A 20% contingency is fair in the
circumstances.
Complainants say the cost of repairs should be increased to cover additional
items
The complainants submitted a scope of works from CH for repairs in the amount of
$712,646.00. This quote included items such as the landscaping and carpets (floor covering),
which were items the insurer had not agreed to cover. The complainants initially requested
their quote to be accepted by the insurer.
However, the insurer (on 13 January 2023) made an offer of $779,781.31. This was based on
its own quote prepared by its builder (AJ), which included a 15% uplift because it was being
made as a cash settlement.
The complainants initially requested a 20% contingency, however, reduced this to try and
negotiate with the insurer.
On 19 January 2023, the complainants advised of issues with the cash settlement, noting the
AJ scope of works excluded the following:
box guttering design and rebuild
pendant lights in the upstairs bathroom and sitting room
replacement of the stained-glass windows
replacement of glass doors to the game room
replacement of the external doors in the upstairs bedroom
an allowance for damaged landscape (as trades left materials on the existing garden)
replacement of fire place in game room.
The insurer addressed the above concerns in its response and the complainants accepted
the box guttering and replacement of the glass doors to the game room were included.
The complainants also accepted that the carpets were included in the CH quote in error
because carpets are considered contents. The complainants do not have contents cover.
AJ scope of works to be considered
The complainants say they would like the insurer to accept the CH quote and offer a
contingency amount.
In my view it is appropriate to consider the AJ quote, because:
the CH quote is not itemised
the complainants have agreed the CH quote was missing one item and included an item
not part of the claim
the CH quote was already determined as being less than what the insurer was offering.
Insurer to add additional items to the final cash settlement
The complainants accepted that the replacement of the external doors in the upstairs
bedroom were not accounted for in the CH scope of works. Based on the complainants‟
Determination | Case number: 900991 Page 3 of 8
submission, two sets of double glazed doors were unaccounted for. Given there is limited
information regarding this, the parties are to work together to review and determine whether
the two double glazed doors are required/were not included in the AJ or CH quotes. If this
was deemed to be damaged from the fire event, the parties are to work together to determine
a suitable cash settlement for this item
The insurer says the pendant lights were included in the final scope from AJ. However, the
complainants say the item is only for lighting in the stairwell. The insurer is to include
additional pendant lights in the upstairs bathroom and sitting room as there does not appear
to be a dispute these were damaged from the insured event.
The insurer says the CH scope of works refers to damage to the library bay window. The
complainants say the library and games room is the same. They say the stained-glass
window requires replacement and say AJ had boarded up this window after the event not
included this in its scope of works. The insurer and complainant are to work together to
review this window and determine a suitable cash settlement amount.
The insurer says the CH quote only includes a provision to inspect the chimney, it does not
include replacement of the fireplace/chimney. The complainants point to the CH quote which
states (on page 4) that an “allowance has been made to supply and install timber mantle
surround to lounge fireplace”. Given there is limited information regarding the extent of
damage to the fireplace/chimney and mantle, the parties are to work together to review and
determine a suitable cash settlement.
Insurer is obligated to cover landscaping
Regarding the landscaping, the complainants say they are not seeking additional costs to
landscape the gardens. Rather, when the trades attended the premises some construction
material was stored in the backyard and permanently killed off some of the grass.
The insurer says the policy does not allow coverage to landscaping. However, has not
provided a response to the allegation that the trades who attended the property left material
on the ground.
It is unclear what the backyard looked like before the event and the policy does not cover
damage to „grass or lawn‟ (unless part of a tennis court).
However, I am satisfied that the insurer is responsible for damage caused by its authorised
trades.
If the damage was caused by the authorised trades of the insurer, the complainants are to
obtain a quotation for the reasonable costs to repair this damage and cash settle the
complainants for this amount plus a 20% uplift for contingencies.
2.2 Should the insurer cover further temporary accommodation
costs?
Yes. It is fair the insurer pays for the temporary accommodation the complainants requested.
Insurer says complainants exhausted temporary accommodation
The complainants‟ policy includes an additional benefit for temporary accommodation if the
insurer agrees a property cannot be lived in because of an insured event. The relevant policy
wording is set out in section 3.2 of this determination.
Determination | Case number: 900991 Page 4 of 8
Temporary accommodation is payable for a maximum period of 12 months, up to 10% of the
building sum insured. The certificate of insurance shows the building sum insured as
$1,402,551. The maximum under the policy is therefore $140,255.10.
Following assessment of the claim, the insurer approved temporary accommodation on 2
August 2022 for $10,096. The remaining $130,000 was paid to the complainants on 8
September 2022, which the insurer says meets the 10% limit under the policy.
Having reviewed the exchanged material, there appears to be a shortfall of $159.10.
If there is such a shortfall, the insurer is to pay this additional amount to the complainants.
The complainants are seeking a further $10,000 in temporary accommodation.
However, the complainants ‟ right to temporary accommodation under the policy is now
exhausted. The insurer says it will not pay any further temporary accommodation. The insurer
denies liability for the delays. The complainants say no repair works have started.
Claim notes reveal delays
The claim notes reveal that by 16 December 2022, the insurer had sent a contract of works to
the complainants and they were told to sign off on the scope of works despite the scope being
incorrect.
Prior to this, around August 2022, the complainants were questioning whether an engineer
would be required to go over the scope of works.
When AFCA became involved on 19 December 2022, the complainants advised they were
unsure why a further site visit was being requested, especially as the insurer had tried to have
them sign off on a scope of works.
On 21 December 2022, there were still assessments being organised and restoration works
were still being completed.
On 13 January 2023, the insurer made its final offer to the complainants. The temporary
accommodation costs were still denied at this time because the insurer says:
the complainants ‟ builder advised the works would take five to seven months
the total benefit of $130,000, is sufficient for their timeframes.
It is acknowledged that the insurer says all communication regarding the temporary
accommodation benefit were discussed with the complainants either verbally or via email.
It is also acknowledged that the complainants sent a 12-month lease to the insurer, when
their own builder advised repairs would only take five to seven months.
Despite the insurer‟s own builder providing an amended quote on 11 January 2023, the
insurer says it has not delayed the claim.
Based on the submissions from the parties, had the complainants signed off on the scope of
works, they would have encountered further issues.
The insurer’s obligations extend to claim ’ s handling
In my view the insurers claim handling has not been satisfactory.
The insurer‟s obligations regarding claim‟s handling extends to notions of fairness,
reasonableness and community standards of decency and fair dealing.
Determination | Case number: 900991 Page 5 of 8
The insurer has not provided any valid explanation for delays regarding the scope of works or
why there was a delay in make safe works.
Questions by the complainants as to the scope of works should not have prevented repairs
progressing/cash settlement offer being made (even if it was partial). Rather, from the
chronology of events, in December 2022 the insurer requested an engineer to attend on site –
without offering temporary accommodation, despite knowing no works had commenced.
In my view, the insurer failed to properly manage the claim and failed to investigate the
delays. It did not take responsibility for its actions.
There is an absence of fairness and reasonableness in the insurer ‟ s handling of parts of the
claim. The insurer should have at least extended the temporary accommodation while these
discussions were ongoing.
Complainants entitled to the temporary accommodation they requested
I acknowledge that the complainants exhausted the policy requirements, however, the
complainants were not able to appoint another builder to privately complete the works until
the decision to make a cash settlement was made.
The insurer paid temporary accommodation costs totalling $10,096 for a reservation made by
the complainants between 3 August 2022 to 31 August 2022. Upon request, the insurer then
paid the remaining amount of $130,000 by 7 September 2022.
The complainants request an additional $10,000 in temporary accommodation costs. It is
unclear where the complainants are currently living or how they came to this figure. However,
this amount does not appear to be unreasonable considering the complainants exhausted the
policy limit before any works commenced. The complainants are not requesting more than
this and, to expedite a final cash settlement, also offered to remove the request for $10,000.
I accept the complainants could have agreed to a partial settlement and commenced some
repairs while the remaining items in the scope of work were in dispute.
I also accept the complainants could have continued to discuss the temporary
accommodation costs alongside the repair costs so there were minimal delays in repairs
commencing.
However, given the complainants have requested significantly less than the five to seven-
month accommodation costs, I consider it fair the insurer pay the $10,000 requested.
2.3 Should the complainants be awarded non-financial loss
compensation?
Yes. The insurer did delay the claim. It is fair the complainants are awarded $2,000 each.
AFCA may award compensation for non-financial loss
Under the AFCA Rules, we can award up to $5,400 compensation for non-financial loss. We
will only award this type of compensation if the complainants suffer an unusual degree of
physical inconvenience, or delay because the insurer mishandled the claim.
We recognise that making a claim can be stressful and time-consuming, even if the insurer
handles the claim correctly. We will not award compensation for the ordinary degree of
inconvenience that comes with making a claim.
Determination | Case number: 900991 Page 6 of 8
Non-financial loss compensation is warranted
Some of the main concerns raised by the complainants were as follows:
the insurer caused considerable stress to their family as a direct result of its poor claims
handling and delays
there was a delay in make safe works being conducted, leading to further mould concerns
the insurer breached its duty of utmost good faith.
I accept the complainants has other personal family stressors leading up to the fire event. The
complainants say the insurer did not take this into consideration and did not communicate
with them from the outset.
The insurer did correctly point out that AFCA does not award compensation for the normal
inconvenience of claims handling. Not every claim will be reviewed the same and considering
the level of damage and complexity of this complaint, it is expected that parties acknowledge
a degree of inconvenience will impact a claim.
As noted above, the complainants also could have accepted a partial cash settlement for the
approved amount back in January 2023, so works could have already been underway.
I accept the complainants have suffered an unusual degree of physical inconvenience and
time taken to resolve the claim because of the insurers handling of the claim. This has in turn
caused a considerable degree of stress. It is fair in the circumstances the insurer pays the
complainants $2,000 each in non-financial loss compensation.
Determination | Case number: 900991 Page 7 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 900991 Page 8 of 8
3.2 Relevant policy wording
Page 28
Page 60
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.