Home / Suncorp Group / Determination 900979

Determination 900979

Partial denial of storm damage claim (pool, fence, retaining wall, pillars, debris) and claim delay

FirmSuncorp Group
Decided2023-06-21
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for storm damage to her home including the pool, fence, retaining wall, pillars and debris removal; the insurer accepted only part of the fence. AFCA required the insurer to cash settle the pool and debris removal with interest, upheld the denial of other items, and awarded $3,000 for non-financial loss.

The storm could not be excluded as the proximate cause of the pool damage because the insurer did not establish the leak's cause, while the other items were excluded or not shown to be storm-caused, and claim delays warranted non-financial loss compensation.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 900979 Financial firm AAI Limited Determination | Case number: 900979 Page 1 of 9 Case number: 900979 16 June 2023 1 Determination overview 1.1 Complaint This complaint relates to a claim by the complainant under her home and contents insurance policy held with the financial firm (insurer), for damage to the insured property. The insurer accepted the claim for a small part of the fence but denies that part of the claim that relates to several other matters including the pool, removal of debris, damage to garden beds, the retaining wall, paving, pillars, the post-box and the remainder of the fence. The complainant also says that the insurer has delayed and poorly handled the claim. 1.2 Issues and key findings Is the insurer entitled to deny the complainant’s claim? Given the terms and conditions of the policy, together with the circumstances of the loss, the insurer is required to pay the claim for the pool and removal of debris but is entitled to deny the claim for damage to the remaining items. Is the complainant entitled to non-financial loss compensation? Yes. Given the insurer‟s handling of the claim, the complainant is entitled to non -financial loss compensation of $3,000. Why is the outcome fair? Given the terms and conditions of the policy and the circumstances of the loss it would not be fair for the insurer to deny all the claim. 1.3 Determination This determination is partially in favour of the complainant. The insurer is required to comply with the provisions of this determination. Determination | Case number: 900979 Page 2 of 9 2 Reasons for determination There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address all issues. This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions where applicable. While the parties have raised numerous issues in their submissions, for the purposes of this determination commentary has been restricted to those issues considered directly relevant to the outcome only. 2.1 Is the insurer entitled to deny the complainant’s claim? Coverage of the policy The complainant‟s home and co ntents insurance policy covers loss or damage to the home at the insured address caused by an insured event in the period of insurance. The coverage provided by the policy is subject to conditions, limitations, and exclusions. This means that not all loss and damage is automatically covered. Rather, only loss and damage caused by an insured event, during the period of insurance and subject to the conditions, limitations and exclusions, is covered. The full details of the policy coverage, conditions, limitations, and exclusions are contained within the Product Disclosure Statement (PDS) and Certificate of Insurance (COI). I am satisfied that the PDS and COI have been provided to the complainant. Therefore, the insurer is entitled to rely upon the terms of the policy, including its conditions, limitations, and exclusions, to determine its obligations to the complainant. Insured events (at page 42 of the PDS) include “Storm”. The COI confirms that the optional cover for “Accidental damage at home” is incl uded in the policy coverage. However, the policy coverage for Accidental damage at home (page 77 of the PDS) has a specific exclusion for; loss or damage that is covered under an insured event listed on pages 41 to 48, as you can make a claim for loss or damage under the applicable insured event I am satisfied that it is appropriate that the insurer‟s liability for the complainant‟s claim be considered under the insured event of storm. It is accepted insurance law that the complainant carries the initial onus to establish, on the balance of probabilities (that is, more likely than not), a loss which is covered by the terms and conditions of the policy. Once the complainant has established a loss which is covered under the policy, the onus transfers to the insurer to establish the application of a condition, limitation or exclusion upon which it seeks to rely, to limit its obligations regarding the claim, or to deny the claim. Determination | Case number: 900979 Page 3 of 9 Circumstances of the loss The complainant lodged her claim with the insurer on 4 March 2022, advising that the property had been damaged by a storm, said to have occurred on 26 February 2022. The exchanged material confirms that the insurer engaged a restoration company (AR) who appears to have attended at the property on 28 June 2022. I note the complainant says this attendance occurred on 30 June 2022. AR‟s report is dated 30 June 2022 and the report details, “Report Date: 28/06/2022”. While the small difference in the two dates is likely insignificant, what is of significance is that AR‟s attendance was the first at the property by a representative of the insurer. I am satisfied that it was a significant weather event in late February 2022, and it would have tested the insurer‟s resources, but four months is a long time a nd much can happen in that time. Reports AR‟s report includes several photographs and conc ludes; Based on our site inspection and information obtained AR believe damages are the result of a storm resulting in a tree to fall and come into contact with multiple fence panels. AR believe the damages to the pool is from hydrostatic pressure causing the walls to collapse. The damages to the front concrete is from multiple concrete slabs not being joined together resulting in cracking to the decorative coating over the top. The damages to the front pillars and retaining wall has been caused by run off water building up behind the area resulting in cracks in the render and the pillars to dislodge from there original position. AR believe if the pillars were connected to a footing the damages would not have occurred The insurer‟s assessor (DA) attended on site on 21 July 2022 and provided a report of the same date. DA recommended the appointment of an engineer to provide expert review and a causation report for the pool. The insurer engaged consulting engineers (KM), who inspected the property on 9 August 2022 and provided a report dated 20 August 2022. The report contains numerous photographs. The claim The complainant says that there are several outstanding matters;  The pool,  Fence repairs,  Retaining wall,  Garden beds,  Collapsed pillars/letter box,  Removal of debris, and  The insurer‟s handling of the claim. The insurer says that it has accepted the complainant‟s claim for the resultant damage to the boundary fence. Determination | Case number: 900979 Page 4 of 9 Based on the exchanged material, I am satisfied that the complainant has established a valid claim for damage at the property because of the storm that occurred on 26 February 2022. However, the complainant still carries the onus to show that the specific items for which she claims are covered by the terms and conditions of the policy and in the circumstances of the insured event of storm. The insurer has denied the balance of the complainant‟s claim. The insurer says that there is a combination of causes of the damage, including;  Inadequate construction and lack of appropriate foundations and drainage to the pool,  Long-term ongoing natural ground movement of the foundations soils due to seasonal and environmental factors to the driveway/concrete slab,  Concrete shrinkage to the retaining wall and  Lack of reinforcement and control joints and inadequate construction of the front pillars. Further, the insurer seeks to rely upon the general exclusions for loss or damage that is caused by or arises from, or involves;  Wear, tear or gradual deterioration,  Seepage of water or  Water seeping or running through the earth. Finally, the insurer says that damage to retaining walls or cracking to sealed driveways caused by storm is specifically excluded under that insured event. The pool KM reported; The conclusion from our Structural Engineering investigation is that the damages to the swimming pool, cracking to the concrete slab and blockwork retaining wall and failure of the front pillars are not attributed to the February 2022 flooding event. The source of the previous leak to the swimming pool liner is not evident and cannot be attributed to the February 2022 flooding event. The damages to the swimming pool can be attributed to the construction methods used. The swimming pool relies on the pool being full of water to resist the horizontal earth pressure. As the pool continued to leak, this would have allowed the earth pressure to overcome the resistance provided by the swimming pool water. The heavy rainfall event in March would have exacerbated the pressure behind the pool as the soil became saturated and placed additional hydrostatic pressure on the pool walls. This has resulted in the southern swimming pool liner detaching from the steel pool frame and collapsing in There are a lack of subsoil drains visible and the backfill does not appear to be set cement stabilised sand. There is also a lack of a hydrostatic pressure relief valve in the pool base. A combination of the above pool construction issues would have contributed to the failure of the swimming pool by allowing excessive hydrostatic water pressure to build up behind the pool, which has contributed to the pool liner failing. Good building practice is to provide hydrostatic relief valves at the base of swimming pools, subsoil drains behind the swimming pool walls and cement stabilised sand Determination | Case number: 900979 Page 5 of 9 backfill to minimise the risk of water/hydrostatic pressure building up behind the pool walls. The exchanged material confirms that the complainant had only recently purchased the prope rty. Further, there is no evidence to challenge the complainant‟s statement that after they moved into the home (24 December 2021) she and her family regularly used the pool over the holiday period. The complainant says that no damage or issues were noted and that the pool was professionally maintained, tested and cleaned on an ongoing regular basis. Significantly, the complainant says that the pool had water in it at the time of lodging the claim and only after that time did the water level drop. There is no evidence to challenge these statements. On 17 April 2023, the complainant contacted the insurer to advise that debris was blown into the pool from the storm. Five and a half months after the storm event and, notwithstanding that KM was unable to determine the source of the leak from the pool, he was prepared to say that the source of the leak cannot be attributable to the „February 2022 floo ding event, and that the damage to the swimming pool can be attributed to the construction methods used. In my view this is pure speculation that ignores the available evidence;  Up until the time of the storm the pool was regularly used and maintained with no problems,  There was a significant weather event on 26 February 2022, and  Debris created by the storm was blown into the pool. As the insurer has chosen not to ascertain the cause of the leak, it cannot exclude the storm as the proximate cause of the leak and damage to the pool. Further, despite the evidence of KM, I prefer the evidence presented by the complainant regarding the construction of the pool, given that there were no problems prior to the storm and the problems commence from the date of the storm. The result is that I am satisfied that insurer is required to meet the complainant‟s claim for the pool under the terms and conditions of the policy. The exchanged material confirms for me that the pool required replacement. I understand that the pool has been replaced by the complainant. The insurer is to cash settle the complainant based upon the amount paid by the complainant for the cost to replace the pool. The complainant is to provide proof of payment To the cash settlement, the insurer is to add interest, calculated in accordance with the Insurance Contracts Act 1984 (the Act), from the date the complainant took out the loan to replace the pool, until the date of payment by the insurer. The complainant is to update the loan details previously provided. Determination | Case number: 900979 Page 6 of 9 Fence repairs and cracking concrete The insurer has partial accepted the claim for fence repairs and a quotation in the amount of $2,717.55, for two boundary fence panels (reduced by 50% for the boundary) and three other fence panels has been provided by AR. The complainant says that she has paid for fence repairs and has provided a quotation, dated 11 June 2022, in the amount of $38,080.00. In his report, KM details; The cracking to the concrete slab can be attributed to natural ground movement and the construction joints between the pathway and infill slab not being reflected through the spray finish. Natural ground movement occurs as the reactive clay soils shrink and swell due to seasonal moisture variations over the life of the structure. The infill slab has been poured after the previous pathway slab. The construction joint should have been reflected through the spray finish. Any differential movement between the two slabs would result in cracking occurring along this joint. The cracking to the blockwork retaining wall render can be attributed to concrete shrinkage over the life of the structure. The pattern of cracking around all of the blocks are consistent with shrinkage cracks. There are no visible control joints in the retaining wall. There is likely a lack of horizontal steel reinforcement to the retaining wall to resist shrinkage. This has resulted in shrinkage cracks in the retaining wall mortar reflecting through the render finish and the render to detach in multiple locations. I am not satisfied that the complainant has provided sufficient evidence to establish that the remaining damage to the fences or the cracking to the concrete was caused by storm. Based on the available evidence, including the photographs, I am of the view that it is more likely that the damage to fences is due to wear, tear and gradual deterioration and the cracking of the concrete paths and driveways is due to natural ground movement, together with wear, tear and gradual deterioration. In this regard, I also note the exclusion (at page 42 of the PDS), for resultant damage to sealed paths and sealed driveways, caused by storm. The insurer is entitled to deny the balance of the claim for the fences and concrete cracking of paths and driveways. Retaining wall The PDS (also at page 42) has an exclusion for loss or damage to retaining walls. This exclusion relates specifically to loss or damage caused by the insured event of storm. The insurer is entitled to deny this aspect of the claim. Garden beds Page 21 of the PDS confirms that plants, trees, shrubs and hedges in the ground are not covered as part of the home, unless covered under the additional cover for Damage to gardens and plants. Page 61 of the PDS confirms that the cost of replacing trees, shrubs, plants, hedges or garden beds, is not covered if the loss or damage is caused by the insured event of storm. I am satisfied that the insurer is entitled to deny this aspect of the claim. Determination | Case number: 900979 Page 7 of 9 Collapsed pillars/letterbox KM advised; The pillars were already removed at the time of our inspection. No footing or reinforcement was visible at the base of the previous location of the pillars. The pillars were likely not installed in accordance with good building practices and likely did not have a sufficient connection at the base to allow the pillars to cantilever. The complainant has not provided evidence to challenge KM‟s position. The complainant carries the onus to establish that the damage to the pillars and letter box is covered under the terms of the policy. I am not satisfied that she has met this onus. The insurer is entitled to deny this aspect of the claim. Removal of debris Page 57 of the PDS includes the additional cover for removal of debris; When we cover loss or damage to the home, we will also cover the reasonable and necessary costs of: — demolishing and removing the damaged parts of the home from the insured address; — removing debris, including fallen trees or branches, where: — the debris has damaged the home; — removal of the debris is required in order to repair the home. I am satisfied that this additional cover relates to the aspects of the claim that the insurer is required to cover, in this case, a portion of the fence claim and the pool claim. Given it was a storm and debris was blown into the pool and likely other areas, then general debris at the property would be expected. The complainant‟s level of cover (Classic) entitles her to an amount for removal of debris of up to 10% of the home sum insured. The insurer is to cash settle the complainant for the reasonable costs incurred in the removal of debris, relating to the aspects of the claim that are covered under the policy. I understand that the removal of debris has been completed. The complainant is to provide details and proof of reasonable expenses incurred in the removal of debris. This does not include the time and labour expended by the complainant and her family. The insurer is to pay interest, in accordance with the Act, from the date the complainant paid for the removal of debris, until the settlement is paid. 2.2 Is the complainant entitled to compensation? Under AFCA‟s Rules, we may award compensation (capped at $5,400) for non -financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, Determination | Case number: 900979 Page 8 of 9 time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. However, we adopt a conservative approach to the award of compensation for non-financial loss. We expect complainants to be moderately robust and bear the usual stress and inconvenience associated with an insurance claim. Moreover, non-financial loss is not intended to be a punishment for any wrongdoing on the part of the insurer The onus is on the complainant to establish she has suffered a loss because the insurer mishandled the claim. The complainant has exchanged a detailed timeline of events. I accept this timeline as accurate. I am satisfied that there are significant delays in the insurer‟s handling of the claim that have not only contributed to the time taken to resolve the claim but also added stress and inconvenience to the complainant and her family. In the circumstances it is fair that the insurer pays the complainant $3,000 in non-financial loss compensation. 2.3 Why is the outcome fair? Given the terms and conditions of the policy and the circumstances of the loss it would not be fair for the insurer to deny all the claim. Determination | Case number: 900979 Page 9 of 9 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.