Whether the insurer's cash settlement represents the reasonable cost of repairs after flood damage, with part of the damage declined as pre-existing
Summary
The complainant disputed the insurer's cash settlement for flood damage to his home, having claimed $378,520 under his builder's quote. AFCA accepted the insurer's scope and quote but required the contingency uplift to rise from 15% to 20%, with interest.
The insurer's expert evidence of pre-existing damage was uncontested and its quote was reasonable, but a 20% contingency uplift was fairer given the transfer of risk.
Issues
- Claim amount dispute primary · not upheld“insurer's scope of work and quote represents the reasonable cost of repair; complainant's quote not itemised”
- Claim denial secondary · not upheld“I accept not all the damage was caused by the flood event; pre-existing damage excluded”
Subjects and remedies
home or building damagenatural disasterpay claimpay interest
Related
Text of the determination
Determination
Case number 900962
Financial firm RACQ Insurance Limited
Determination | Case number: 900962 Page 2 of 6
Case number: 900962 11 January 2024
1 Determination overview
1.1 Complaint
The complainant holds a home insurance policy (the policy) with the financial firm (the
insurer)
On 10 March 2022, the complainant lodged a claim for damage to his property and contents
following a flood event.
Upon assessing the claim, the insurer accepted part of the claim but denied some of the
damage on the basis that pre-existing and unrelated water damage and mould was identified
throughout various parts of the property. A dispute continues regarding the final scope of
works and settlement offer for damage to the home.
The complainant says the insurer’s offer of settlement does not adequately compensate him
for damage caused to his property following the flood events of February 2022 and will not
allow him to restore his property to its pre-loss condition.
1.2 Issues and key findings
Does the proposed cash settlement represent the reasonable costs of repairs?
Yes. While the insurer’s final scope of work and quote represents the reasonable cost of
repair, it is to increase its cash settlement with a 20% uplift for contingencies and the transfer
of risk and pay interest in accordance with the provisions of this determination.
Why is the outcome fair?
The outcome is fair because the exchanged material established the insurer is entitled to
cash settle the claim but increase the uplift.
1.3 Determination
This determination is substantially in favour of the insurer.
Within 14 days of the determination being accepted by the complainant, the insurer is to
comply with the provisions of this determination.
Determination | Case number: 900962 Page 3 of 6
2 Reasons for determination
2.1 Does the proposed cash settlement represent the
reasonable cost of repairs?
Insurer obtained a new scope of work and quote
On 31 May 2022, the insurer partially declined the claim and says there is pre-existing and
non-event related damage. The insurer offered a cash settlement of $20,5858.60. It noted, it
would cash settle the claim due to the extent of pre-existing damage, as it would impact its
builder’s ability to warrant repairs.
The initial cash settlement was no accepted by the complainant as it did not include all items
which he says occurred during previous flood events. He also stated, he was unware of the
water ingress through the weep holes.
Following a conciliation conference at AFCA, the complainant and insurer agreed that the
complainant would directly submit his own builder ’s quote for the insurer’s consideration.
The complainant submitted a quote from builder (FBC) on 22 December 2022, for a total of
$378,520.00.
Insurer says its cash settlement is fair and reasonable
After assessing the complainants’ scope of work and quote, the insurer offered a second cash
settlement of $54,752.18 for the cost of repair. It also agreed to provide a contingency uplift of
15%, raising the final settlement amount to $62,965.01 for the building repairs. The insurer
reviewed all quotes and determined the quote from PR was aligned with acceptable market
rates.
Insurer says part of the claimed damage was due to pre-existing factors
The insurer says the quote from FBC is not itemised and some of the quoted items were for
damage that was declined and considered pre-existing under the policy.
To support its position, the insurer relied on its engineer’s report (CRD), dated 22 March
2023, which it says confirmed the following:
external brickwork of the home revealed that weep holes have been installed to the two
lower courses of bricks. The lowest appears to be below the internal slab height with the
course above this also having a weep hole installed with a damp course installed between
the two courses.
flood water line was approximately ¾ of the height of the first course of bricks, this is how
the water appears to have entered the internal areas of the home.
Water did not enter above this course therefore flood water was confined to the cavities of
the walls between the main house slab and internal floor linings.
fascia and gutters on the external wall of the garage appeared to be in poor condition prior
to the event and had leaf debris build up, causing the gutter to hold a significant amount of
water during the rain event.
Damage to kitchen cabinetry is pre-existing and had not be shown to be caused by the
flood event
damage to the toilet and bathroom area to the left side of the home was due to a long-term
leak from a shower recess. This in turn caused damage to the ensuite and walk in robe of
the master bedroom.
Determination | Case number: 900962 Page 4 of 6
As such, the insurer relied on its general exclusions for wear and tear, rust and mould to deny
part of the damage, noting it was not caused by the flood event itself but rather due to pre-
existing factors.
The complainant has not provided any independent reports to refute the insur er’s expert’s
conclusions.
I am satisfied that the reports pro vided by the insurer’s experts are logical, thorough,
compelling and supported by helpful photographs. In the absence of expert evidence to the
contrary, I accept not all the damage was caused by the flood event.
Complainant has not shown his preferred quote is fair and reasonable
The complainant says the insurer ’ s offer is not sufficient to ensure his home is returned to its
pre-loss condition. The complainant has also stated that the insurer’s expert assessments
were conducted sometime after the actual water damage occurred. Whilst the complainant
acknowledged some previous damage to the bathrooms, he requested that the insurer
remediate the mould which he says was not pre-existing and was due to the flood event. The
complainant also says that the damage to a kitchen of such age is impossible.
The complainant also stated that the reason his quote has more significant values is due to
the amount of water received during the weather event, noting the water level went above the
weep holes for the entire perimeter of the property. The complainant relies on photographs
and video to support. The complainant, therefore, maintains the internal walls need to be
removed for the entire perimeter of the house. He states, to do this, it will be very unlikely that
the four bathrooms, toilets and kitchen cabinets can be removed and returned back to original
condition.
In comparing the quotes, it is evident the complainant’s quote includes items which the
insurer has denied liability for. For example, supplying and installing kitchen bench tops, all
joinery and allowance for overhead cupboards and appliances.
In comparing the rationales for the quotes, I am satisfied the insurer has provided a detailed
explanation to substantiate its costing. It confirmed it used current pricing and assessed the
area to be repaired. Unfortunately, the complainant ’s quote from FB C is not itemised, lacks
explanation for the different areas or a detailed breakdown of pricing.
Further, the complainant’s quote is reflective of all the works which are to be completed to
bring the home back to its original condition. However, without further independent evidence
from the complainant to refute the insurer’s position that part of the damage was pre -existing
and that the water did in fact reach above the weep holes of the bricks , I accept the insurer’s
costings are reflective of its liability under the policy.
Therefore, I accept after the recent assessment the insurer has shown, on balance, its quote
is fair and reasonable.
Cash settlement to be based on PR ’s final scope of work and quote
Given the pre-existing issues identified by CRD and t he issues with the complainant’s scope
of work and quote, I accept there is sufficient cause to determine a fair cash settlement based
on PR’s final quote.
The insurer is to cash settle the claim based on PR ’s quote.
However, I note that PR’s quote is dated 11 April 2023 and valid for 30 days.
Determination | Case number: 900962 Page 5 of 6
Should the complainant accept this determination the insurer is to pay interest in accordance
with the Insurance Contracts Act 1984, from the 30 May 2023 to the date of the cash
settlement.
In addition, the insurer it to increase its contingency uplift from 15% to 20%. This is to address
the risks of the work passing to the complainant and the likely possibility that there may be
variations required during the works.
The interest calculation is to be made based upon PR’s quote, plus the contingency uplift.
Within 21 days of the determination being accepted by the complainant, the insurer is to cash
settle the claim based on PR’s quote, plus a 20% contingency, plus interest.
2.2 Why is the outcome fair?
The outcome is fair because the insurer’s scope of work and quote represents the reasonable
cost of repair. However, the 10% uplift should be increased to 20%, being a fairer allowance
for contingencies and the transfer of risk in the circumstances.
Determination | Case number: 900962 Page 6 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.