Poor repair work by insurer's builder, delays and claim handling; contents and temporary accommodation limits

FirmHollard
Decided2023-03-13
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss$5,400
Amount claimed—
SourceAFCA PDF

Summary

The insurer's builder made errors and delayed repairs after storm water damage to the complainant's home. AFCA found for the complainant, requiring a scoped cash settlement, temporary accommodation, contents settlement beyond limits and $5,400 non-financial loss, but rejected the lost income claim.

The insurer was responsible for its builder's defective and delayed work and mishandled the claim, so policy limits could not fairly apply to losses caused by that conduct.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial lossreassess claim

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 898788 Financial firm Hollard Insurance Partners Limited Determination | Case number: 898788 Page 1 of 10 Case number: 898788 6 March 2023 1 Determination overview 1.1 Complaint The complainant held a home and contents insurance policy with the financial firm (insurer). She lodged a claim when storm water runoff caused damage to her home. The insurer accepted the claim. The complainant is not satisfied with the repair work completed by the insu rer’s builder (JL). She says some repairs have been missed or done poorly, and these have not been rectified in a timely fashion even after she complained about it. She also says the insurer is liable to her for direct financial losses for contents and temporary accommodation which likely exceed the policy limits due to the delays stemming from the claim handling errors. She also seeks compensation from the insurer for loss of income and avoidable stress. The insurer says it is waiting on a scope of work from its builder after which it will offer a cash settlement for the repair work. It also says it will cover the contents up to the sum insured plus the 25% gap cover in the policy and pay $5,000 on a goodwill basis to resolve the complaint. The complaina nt is not satisfied with the insurer’s offer and says it must:  rectify the incomplete or incorrect building repairs in a reasonable timeframe with a different builder  pay her the cash settlement for the parts of the repair scope of work which the insurer agreed to  pay for temporary accommodation until the repair works is complete  pay her the value of her contents loss to the policy sum insured, and compensation for the contents loss resulting from the early claim delays  pay her $5,400 for loss of income  pay her $5,400 non-financial loss compensation. 1.2 Issues and key findings Is the insurer’s settlement offer reasonable ? No. The insurer must settle the claim in line with section 2.1 of this determination. Is the complainant entitled to compensation for delays? Yes. The insurer must pay the complainant $5,400 in non-financial loss. 1.3 Determination The determination is in favour of the complainant. If the complainant accepts the determination, the insurer must settle the claim in line with section 2 of this determination. Determination | Case number: 898788 Page 2 of 10 2 Reasons for determination 2.1 Is the insurer’s settlement offer reasonable ? Evidence shows insurer has further building repair liability Both parties accept there have been errors made by JL during the repair of the building. The insurer verified the complainant’s concerns about the building work when it received the report from its building consultant (SW). Details relevant to this can be found in section 3 of this determination. There are multiple items which are incomplete. This is expected when a repair is halted midway through. Many of the items in SW’s list of corrections do not appear to be items of major concern as they can be completed at a later date. They simply have not been completed yet. However, the panel is satisfied the complainant has reasonable grounds for concern about the quality of the building work. SW’s report shows:  JL concreted the floor waste pipe in the shower recess without installing the flange required by the relevant building standard  the bathtub frame shows insulation which should be in the wall cavity next to it is missing  images of another wall cavity show no insulation installed either  the shower recess has exposed reinforcing material penetrating the waterproof coating. This evidence is consistent with the collected images the complainant supplied showing multiple poor quality repairs and failures by JL to meet the scope of work requirements. Given this, the panel is satisfied the complainant’s misgivings about JL’s repair work are warranted, particularly when viewed in concert with her explanation about the confrontations she had with the builder and the site supervisor. Drying and scope of work delays are excessive The panel notes the complainant first raised her concerns about JL’s strip out work on 28 June 2022 as the builder did not strip all walls to a height of 1200mm. This is supported by the information in the insurer’s restorer (AR) report saying it did not complete its work until the strip out was complete sometime before 26 July 2022. The complainant provided video evidence on 20 July 2022 showing there was still mould in the wall cavities noting the wall strip out did not occur in the first four months. Considering the flood happened in February and AR recommended the 1200mm strip out on 3 March 2022, the panel is satisfied JL has not acted with due haste resulting in a delay and additional loss. Further, the panel notes the difficulty AR appeared to have drying the property given they were not able to declare the property dried until 30 August 2022, approximately six months after the flood. Since then a further delay was confirmed by JL, meaning the repair work would not be completed until November 2022, though this timeframe has not been met either. This situation was not helped by the errors SW highlighted and the difficulty the complainant had with getting her concerns investigated. Determination | Case number: 898788 Page 3 of 10 Accordingly, the panel is satisfied the breakdown in trust is the result of how the claim has been handled. Therefore, further repair work by JL is unlikely to effectively resolve the dispute. To date, no effective scope of work for the remaining repairs has been supplied by the insurer. The complainant says JL advised it is waiting on further guidance from the insurer. The onus is on the insurer to resolve the extent of rectification work. Accordingly, the lack of progress which has resulted in the complainant expending excessive levels of effort to progress the claim is not fair in the circumstances. The panel is satisfied the insurer has had sufficient time to settle the scope of work and motivate the repairer to correct their established errors. Co-ordination of the relevant trades is the insurer’s obligation in these circumstances. As the panel is not satisfied the insurer and JL are effectively managing the situation, it is necessary to establish how the parties move forward from here. Insurer to take the following actions to progress the building claim The panel is not satisfied the building portion of the claim is sufficiently evidenced to allow a full and final settlement at this time. Accordingly, the panel’s view is to set the parameters for the parties to follow to expedite the claim outcome. The panel notes the insurer’s reluctance to replace JL, and JL’s reluctance to replace the subcontrac tor responsible for the errors. However, it is clear the complainant no longer trusts JL to complete the work adequately. Given the history of the claim, the complainant’s position has substance. The panel considers a cash settlement would offer the fairest solution. As stated before, there has been a breakdown in the trust between the parties. Given the complainant’s claim history to date, it is not clear if the insurer would be able to manage the claim expeditiously after the determination is issued. Therefore, the panel proposes the building claim be settled in the following way. Within 14 days of the complainant accepting this determination, the insurer must organise to have JL return any items it is holding to reuse in the repair, such as the missing doors. JL is then to cease any further work on the property. JL is required to provide evidence of any necessary certifications where relevant. The parties are to then engage an independent structural engineer or a building consultant to inspect the property and provide a full scope of works to complete the required repairs. The engineer or building consultant should be one agreed to by the parties. This can be done by the insurer providing a list of three engineers and/or building consultants the complainant can choose from. The engineer or building consultant engaged should be appropriately licenced and qualified to do this work. These expert’s costs should be borne by the insurer. The scoping of the works should include invasively testing various walls to identify if insulation has been completed. The scope of works should at least address the following:  any outstanding repairs in the scope of work documents which have not been completed  any outstanding repairs which are documented in the images the complainant has taken which the insurer’s trades have not yet corrected or is part of the claim repairs  correcting the errors and incomplete work highlighted by SW’s report  the cost of removing and replacing the exterior wall cavity plaster and any missing insulation, and reinstatement of the plaster afterwards Determination | Case number: 898788 Page 4 of 10  an allowance for a post mould repair clearance certificate Once a scope of works has been complete, each party can obtain at least one, and no more than two, actionable quotes based on that scope of works. The quotes should also include an estimate of the likely repair timeframe. If only one quote is obtained, then the insurer is to cash settle the claim based on that quote plus a 20% contingency. If more than one quote is obtained, then the insurer is to cash settle the claim based on the average of those quotations with a 20% contingency. The contingency is to address the fact the risks of the works are passing to the complainant and the likely possibility that there may be variations required during t he works. Insurer must pay temporary accommodation The panel acknowledges the policy contains a 52-week limit for temporary accommodation. However, the panel does not accept this limit applies in circumstances when these costs have been incurred due to the insurer’s conduct rather than as a result of the losses claimed. The panel considers the former applies because:  the claims history set out above – this includes the issues with the repairs identified, and  the complainant has spent a fair amount of time in temporary accommodation whilst challenging the insurer’s position (and ultimately done so successfully). Therefore, the panel considers it fair the temporary accommodation limit should only apply once the expert has completed a scope of works to repair the claim related damage as set out in this determination. Given this, the insurer must pay temporary accommodation costs for the estimated time to complete repairs, plus a further 14 days to allow the complainant time to return to the property and refurnish it. This is subject to the overall timeframe not exceeding 52 weeks. To clarify, the 52 weeks commences from the time the expert completes the scope of works. The estimated time to complete repairs should be based on the relevant quotes obtained for the scope of works (i.e. those contractors should be estimating the likely timeframe for repairs). If more than one estimate is provided, then the average is to be applied. For any temporary accommodation costs incurred by the complainant up to the time the claim is cash settled pursuant to this determination, the insurer is to reimburse this subject to proof of payment. Insurer to settle the complainant’s contents loss The panel notes there is no dispute the complainant is entitled to claim for her damaged contents. There is also no dispute the value of the contents loss will exceed her policy sum insured limit. What is disputed is whether the insurer can apply the sum insured and the gap cover limits when settling the claim. The panel is not satisfied it is fair in the circumstances the insurer limits its liability as described. Firstly, the panel notes the insurer has yet to provide the correct policy document showing the sum insured limit it relies on. The document which has been supplied is for a subsequent period after the storm which only includes portable contents. The panel is satisfied the insurer has the onus to establish an entitlement to limit the value of the settlement on a valid claim. The insurer has not done so despite being asked for the relevant document on more than one occasion. Determination | Case number: 898788 Page 5 of 10 Secondly, the panel notes the efforts the complainant and her neighbours went to attempting to mitigate the contents loss. AR made recommendations about stripping out the property which were only partially completed by the builder and not fully completed for four months. The information from AR does not establish the contents sum insured was breached until the update from the complainant on 26 April 2022. Further, AR’s timeline of events shows restorable contents were moved to the garage and treated a second time with anti-microbial agents on 6 April 2022. This indicates at this point in time, there was still an opportunity to restore these items and potentially settle the claim below the contents sum insured. The complainant has shown multiple images of the contents stored in her garage which had not been further protected by AR after attending and treating with anti-mould agents. The complainant also supplied a text message from her neighbour suggesting her contents of the garage were being substantially mishandled by JL. None of the insurer’s evidence has shown mould controls were put into place. When viewed holistically with the timeline of the strip out and the exceptionally long drying period, it supports the complainant’s position that the additional loss was not the result of the insured event, but by mishandling of the repair process. Accordingly, the panel is satisfied the complainant is entitled to a remedy exceeding the policy limit. This is because the complainant’s loss is not stemming from the insured event, but due to errors by the insurer’s tradesmen. The complainant is to provide the insurer with evidence showing the value of her full contents loss inclusive of storage of any restorable contents during the repair which she has been able to salvage. The insurer is to assess this and pay her the fair and reasonable value to settle its liability within 14 days of the complainant supplying the relevant proof of the value of her loss. 2.2 Is the complainant entitled to compensation for delays? An award of non-financial loss compensation is warranted Under AFCA’s rules, we may award a complainant up to $5,400 non -financial loss compensation if a claim was mishandled by the insurer. We will only award non-financial loss compensation when a complainant experiences an unusual level of physical inconvenience, time taken to resolve a matter, or interference with their reasonable expectation of peace of mind. The panel is satisfied the insurer mishandled the claim resulting in an excessive level of non- financial loss impact to the complainant. Accordingly, the panel is satisfied it is fair to award the full value of $5,400 in these circumstances. The complainant has had to manage the repair process because the ins urer’s repairers were not following the scope of work and the insurer has not effectively corrected this. This led to exceptional physical inconvenience as she was regularly having to contact the insurer and convince them the builder was not meeting their requirements. The images supplied show this clearly. The panel is satisfied the outcome of her efforts has been to prove repair work would not have been completed to the Australian standard by the builder, had she not objected. Determination | Case number: 898788 Page 6 of 10 Additionally, the complainant has lost most of her household possessions, including items of great sentimental value which cannot be replaced. This is despite her reasonable efforts to protect the items up to her own capacity. The complainant has also been operating under the concern she will be without temporary accommodation cover despite the delays. The panel considers this had a serious impact on the complainant’s peace of mind. Finally, the situation has evolved to the point it is not reasonable for the insurer to continue the repair. This means the complainant will continue to experience difficulty as she now must effectively take over organisation of the repair work. Accordingly, the panel is satisfied the full amount of $5,400 is warranted. Complainant has not established lost income Whilst the panel accepts the complainant has spent time on this claim and complaint, there is no supporting information to show that she lost income because of the insurer’s claims handling. For instance, whilst she says she had to take numerous days off work to manage her case, no proof of this was provided. It is also not clear if this time off work can be distinguished from the expected inconvenience a significant claim like this would give rise to as opposed to being caused by the insurer’s poor claims handling. If it is the former, then this is not payable given the policy contains an exclusion for consequential loss. Given this, the panel does not accept there is sufficient basis to make an award for lost income. Determination | Case number: 898788 Page 7 of 10 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 898788 Page 8 of 10 3.2 Expert and witness evidence summary Record Key points Insurer ’s re storer (A R ) Report 16 March 2022  Storm event caused ground water runoff to ent er the property.  Affected carpets removed from the building, applied anti - microbial treatment and installed dryers due to elevated moisture readings.  Electrician completed make safe on power outlets  Dryers at site from 3 March 2022, and technician returned on 8 March 2022 , 10 March 2022, and 16 March 2022.  Recommends 1200mm of wall needs to be stripped by the builder. Insurer’s builder ( JL ) Report 8 April 2022  Discussions with the complainant initially confirmed too much water came through to prevent it entering the hous e.  Water level reported is up to 100mm from the floor.  Complainant tried to remove the water from the house as quickly as possible.  Damage consistent with the insured event to walls, skirting, architraves, internal and external doors, cabinetry, GPOs, and floor tiles.  Recommends replacing wet areas due to damage to waterproof membranes from the insured event. Insurer’s re storer (AR) Report 30 August 2022  Elevated moisture levels still present on 6 April 2022. Drying equipment installed.  Restorable contents relocated to the garage.  Anti - microbial treatment reapplied to the restorable contents and moisture affected areas.  Strip out not complete at this stage.  Cont ents loss exceeds policy limit at 26 April 2022 meaning total loss result.  Returned to the property on 26 July 2022 following strip out to complete HEPA vacuum of the affected areas.  Returned to the property to install more drying equipment and apply anti - microbial again on 2 August 2022.  Returned to the property to reposition drying equipment and apply anti - microbial again on 18 August 2022.  Returned to the property to reposition drying equipment and apply anti - microbial again on 25 August 2022.  Dry standard ac hieved on 30 August 2022. Insurer’s building consultant (SW) Repo rt 29 November 2022  Instructions were to review the repair work completed to dat e.  Insulation not installed to all external walls.  Wet area drains have grout and rubbish which must be cleaned out.  Ensuite 2 shower has exposed reinforcing.  No puddle flange installed on concrete slab flooring sewer drain junction as required by AS 3740 - 2010.  Internal garage door frame damaged.  Front door and internal doors not on site. Determination | Case number: 898788 Page 9 of 10 Record Key points  Mirrored sliding doors not on site.  Wardrobe joinery not installed.  Plasterboard walls to be sanded ready for pre - paint.  Kitchen joinery doors not aligning as designed and are binding.  Kitchen rangehood not operating.  There is outstanding work, but the work performed to date is of an acceptable standard.  Builder to provide proof of insulation work, waterproof certificates, evidence of shower repairs being complet ed before tiling, and returning all doors to site. Complainant’s neighbour (SC) Witness statement 30 November 2022  Arrived at the property around 11am on 27 February 2022 to assist the complainant along with others.  The whole house had tide marks up the walls and all rooms had water damage.  Bedroom carpets were sodden and furniture was already swelling.  Clothes in the wardrobe were totally soaked and/or damp.  Moved furniture and p ersonal into the garage which was the least affected place in the house and raised furniture off the floor if it was too heavy to move or needed to be dismantled.  Filled 15 garbage bags with water affected clothes and took them home to wash and dry, then r eturned them two days later to store with other contents in the garage. Complainant’s neighbour (MV) Witness statement 4 December 2022  We live directly opposite the complainant and had a call from her on 26 February 2022 saying her house was flooded.  As sisted the complainant with sandbagging and trenc hes to divert water from the house.  Assisted with sweeping and squeegeeing water and mud out of the house.  Assisted with picking up furniture and other belongings off the floor to try and save what could be saved.  Complainant says the insurer told her to leave everything where it was until someone could inspect it all.  Weeks later we assisted her to move what we could into the shed, so the walls could be removed. Substantial mould present by then.  My husband witnessed a team of people throwing out all sorts of the complainant’s furniture including items she intended to keep as they were items she was trying to save wit h her efforts. Complainant’s neighbour (SS) Witness statement 5 December 2022  A woke on 26 February 2022 to a large amount of water running through my yard, so texted the complainant who said her house was flooded.  Helped the complainant remove items from her home, sand bagged, dug trenches, mopped and directed water away from the ho me.  Raised furniture off the floor using bricks and blocks and moved other furniture to dry areas. Determination | Case number: 898788 Page 10 of 10 Record Key points  Helped care for the complainant’s daughter while she tried to mitigate the flood damage and contact the insurer.  Complainant was on the phone for several hours to the insurer.  Assisted the complainant with storing some of her contents and cleaning her flood affected clothes, linen, soft toys.  Assisted with washing clothes which became affected by the damp conditions in the building over time, even when they were not flood affected directly.  Overwhelming smell of mould and damp in the house which has impacted the contents being stored in the ga rage.  Complainant checked cont ents storage was water tight, and cleaned furnit ure with vinegar on the day of the flood.