Home / Hollard / Determination 898788
Determination 898788
Poor repair work by insurer's builder, delays and claim handling; contents and temporary accommodation limits
Summary
The insurer's builder made errors and delayed repairs after storm water damage to the complainant's home. AFCA found for the complainant, requiring a scoped cash settlement, temporary accommodation, contents settlement beyond limits and $5,400 non-financial loss, but rejected the lost income claim.
The insurer was responsible for its builder's defective and delayed work and mishandled the claim, so policy limits could not fairly apply to losses caused by that conduct.
Issues
- Repairs or contractors primary · upheld“Both parties accept there have been errors made by JL during the repair of the building.”
- Claim amount dispute secondary · upheld“not satisfied it is fair the insurer limits its liability to contents sum insured and gap cover; temporary accommodation limit not applied”
- Poor claim handling secondary · upheld“the panel is satisfied the insurer mishandled the claim resulting in an excessive level of non-financial loss”
- Delay secondary · upheld“Drying and scope of work delays are excessive; JL has not acted with due haste”
- Other secondary · not upheld“Complainant has not established lost income; no supporting information that she lost income”
- Third-party or outsourcing failure secondary · upheld“loss not stemming from the insured event, but due to errors by the insurer's tradesmen”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay non financial lossreassess claim
Related
Text of the determination
Determination
Case number 898788
Financial firm Hollard Insurance Partners Limited
Determination | Case number: 898788 Page 1 of 10
Case number: 898788 6 March 2023
1 Determination overview
1.1 Complaint
The complainant held a home and contents insurance policy with the financial firm (insurer).
She lodged a claim when storm water runoff caused damage to her home. The insurer
accepted the claim.
The complainant is not satisfied with the repair work completed by the insu rer’s builder (JL).
She says some repairs have been missed or done poorly, and these have not been rectified
in a timely fashion even after she complained about it.
She also says the insurer is liable to her for direct financial losses for contents and temporary
accommodation which likely exceed the policy limits due to the delays stemming from the
claim handling errors. She also seeks compensation from the insurer for loss of income and
avoidable stress.
The insurer says it is waiting on a scope of work from its builder after which it will offer a cash
settlement for the repair work. It also says it will cover the contents up to the sum insured plus
the 25% gap cover in the policy and pay $5,000 on a goodwill basis to resolve the complaint.
The complaina nt is not satisfied with the insurer’s offer and says it must:
rectify the incomplete or incorrect building repairs in a reasonable timeframe with a
different builder
pay her the cash settlement for the parts of the repair scope of work which the insurer
agreed to
pay for temporary accommodation until the repair works is complete
pay her the value of her contents loss to the policy sum insured, and compensation for the
contents loss resulting from the early claim delays
pay her $5,400 for loss of income
pay her $5,400 non-financial loss compensation.
1.2 Issues and key findings
Is the insurer’s settlement offer reasonable ?
No. The insurer must settle the claim in line with section 2.1 of this determination.
Is the complainant entitled to compensation for delays?
Yes. The insurer must pay the complainant $5,400 in non-financial loss.
1.3 Determination
The determination is in favour of the complainant.
If the complainant accepts the determination, the insurer must settle the claim in line with
section 2 of this determination.
Determination | Case number: 898788 Page 2 of 10
2 Reasons for determination
2.1 Is the insurer’s settlement offer reasonable ?
Evidence shows insurer has further building repair liability
Both parties accept there have been errors made by JL during the repair of the building.
The insurer verified the complainant’s concerns about the building work when it received the
report from its building consultant (SW). Details relevant to this can be found in section 3 of
this determination.
There are multiple items which are incomplete. This is expected when a repair is halted
midway through. Many of the items in SW’s list of corrections do not appear to be items of
major concern as they can be completed at a later date. They simply have not been
completed yet.
However, the panel is satisfied the complainant has reasonable grounds for concern about
the quality of the building work. SW’s report shows:
JL concreted the floor waste pipe in the shower recess without installing the flange
required by the relevant building standard
the bathtub frame shows insulation which should be in the wall cavity next to it is missing
images of another wall cavity show no insulation installed either
the shower recess has exposed reinforcing material penetrating the waterproof coating.
This evidence is consistent with the collected images the complainant supplied showing
multiple poor quality repairs and failures by JL to meet the scope of work requirements.
Given this, the panel is satisfied the complainant’s misgivings about JL’s repair work are
warranted, particularly when viewed in concert with her explanation about the confrontations
she had with the builder and the site supervisor.
Drying and scope of work delays are excessive
The panel notes the complainant first raised her concerns about JL’s strip out work on 28
June 2022 as the builder did not strip all walls to a height of 1200mm. This is supported by
the information in the insurer’s restorer (AR) report saying it did not complete its work until the
strip out was complete sometime before 26 July 2022.
The complainant provided video evidence on 20 July 2022 showing there was still mould in
the wall cavities noting the wall strip out did not occur in the first four months. Considering the
flood happened in February and AR recommended the 1200mm strip out on 3 March 2022,
the panel is satisfied JL has not acted with due haste resulting in a delay and additional loss.
Further, the panel notes the difficulty AR appeared to have drying the property given they
were not able to declare the property dried until 30 August 2022, approximately six months
after the flood.
Since then a further delay was confirmed by JL, meaning the repair work would not be
completed until November 2022, though this timeframe has not been met either. This
situation was not helped by the errors SW highlighted and the difficulty the complainant had
with getting her concerns investigated.
Determination | Case number: 898788 Page 3 of 10
Accordingly, the panel is satisfied the breakdown in trust is the result of how the claim has
been handled. Therefore, further repair work by JL is unlikely to effectively resolve the
dispute.
To date, no effective scope of work for the remaining repairs has been supplied by the
insurer. The complainant says JL advised it is waiting on further guidance from the insurer.
The onus is on the insurer to resolve the extent of rectification work. Accordingly, the lack of
progress which has resulted in the complainant expending excessive levels of effort to
progress the claim is not fair in the circumstances.
The panel is satisfied the insurer has had sufficient time to settle the scope of work and
motivate the repairer to correct their established errors. Co-ordination of the relevant trades is
the insurer’s obligation in these circumstances. As the panel is not satisfied the insurer and JL
are effectively managing the situation, it is necessary to establish how the parties move
forward from here.
Insurer to take the following actions to progress the building claim
The panel is not satisfied the building portion of the claim is sufficiently evidenced to allow a
full and final settlement at this time. Accordingly, the panel’s view is to set the parameters for
the parties to follow to expedite the claim outcome. The panel notes the insurer’s reluctance
to replace JL, and JL’s reluctance to replace the subcontrac tor responsible for the errors.
However, it is clear the complainant no longer trusts JL to complete the work adequately.
Given the history of the claim, the complainant’s position has substance.
The panel considers a cash settlement would offer the fairest solution. As stated before, there
has been a breakdown in the trust between the parties. Given the complainant’s claim history
to date, it is not clear if the insurer would be able to manage the claim expeditiously after the
determination is issued.
Therefore, the panel proposes the building claim be settled in the following way.
Within 14 days of the complainant accepting this determination, the insurer must organise to
have JL return any items it is holding to reuse in the repair, such as the missing doors. JL is
then to cease any further work on the property. JL is required to provide evidence of any
necessary certifications where relevant.
The parties are to then engage an independent structural engineer or a building consultant to
inspect the property and provide a full scope of works to complete the required repairs. The
engineer or building consultant should be one agreed to by the parties. This can be done by
the insurer providing a list of three engineers and/or building consultants the complainant can
choose from. The engineer or building consultant engaged should be appropriately licenced
and qualified to do this work.
These expert’s costs should be borne by the insurer.
The scoping of the works should include invasively testing various walls to identify if insulation
has been completed. The scope of works should at least address the following:
any outstanding repairs in the scope of work documents which have not been completed
any outstanding repairs which are documented in the images the complainant has taken
which the insurer’s trades have not yet corrected or is part of the claim repairs
correcting the errors and incomplete work highlighted by SW’s report
the cost of removing and replacing the exterior wall cavity plaster and any missing
insulation, and reinstatement of the plaster afterwards
Determination | Case number: 898788 Page 4 of 10
an allowance for a post mould repair clearance certificate
Once a scope of works has been complete, each party can obtain at least one, and no more
than two, actionable quotes based on that scope of works. The quotes should also include an
estimate of the likely repair timeframe.
If only one quote is obtained, then the insurer is to cash settle the claim based on that quote
plus a 20% contingency. If more than one quote is obtained, then the insurer is to cash settle
the claim based on the average of those quotations with a 20% contingency.
The contingency is to address the fact the risks of the works are passing to the complainant
and the likely possibility that there may be variations required during t he works.
Insurer must pay temporary accommodation
The panel acknowledges the policy contains a 52-week limit for temporary accommodation.
However, the panel does not accept this limit applies in circumstances when these costs have
been incurred due to the insurer’s conduct rather than as a result of the losses claimed. The
panel considers the former applies because:
the claims history set out above – this includes the issues with the repairs identified, and
the complainant has spent a fair amount of time in temporary accommodation whilst
challenging the insurer’s position (and ultimately done so successfully).
Therefore, the panel considers it fair the temporary accommodation limit should only apply
once the expert has completed a scope of works to repair the claim related damage as set
out in this determination.
Given this, the insurer must pay temporary accommodation costs for the estimated time to
complete repairs, plus a further 14 days to allow the complainant time to return to the property
and refurnish it. This is subject to the overall timeframe not exceeding 52 weeks. To clarify,
the 52 weeks commences from the time the expert completes the scope of works.
The estimated time to complete repairs should be based on the relevant quotes obtained for
the scope of works (i.e. those contractors should be estimating the likely timeframe for
repairs). If more than one estimate is provided, then the average is to be applied.
For any temporary accommodation costs incurred by the complainant up to the time the claim
is cash settled pursuant to this determination, the insurer is to reimburse this subject to proof
of payment.
Insurer to settle the complainant’s contents loss
The panel notes there is no dispute the complainant is entitled to claim for her damaged
contents. There is also no dispute the value of the contents loss will exceed her policy sum
insured limit. What is disputed is whether the insurer can apply the sum insured and the gap
cover limits when settling the claim.
The panel is not satisfied it is fair in the circumstances the insurer limits its liability as
described.
Firstly, the panel notes the insurer has yet to provide the correct policy document showing the
sum insured limit it relies on. The document which has been supplied is for a subsequent
period after the storm which only includes portable contents. The panel is satisfied the insurer
has the onus to establish an entitlement to limit the value of the settlement on a valid claim.
The insurer has not done so despite being asked for the relevant document on more than one
occasion.
Determination | Case number: 898788 Page 5 of 10
Secondly, the panel notes the efforts the complainant and her neighbours went to attempting
to mitigate the contents loss. AR made recommendations about stripping out the property
which were only partially completed by the builder and not fully completed for four months.
The information from AR does not establish the contents sum insured was breached until the
update from the complainant on 26 April 2022.
Further, AR’s timeline of events shows restorable contents were moved to the garage and
treated a second time with anti-microbial agents on 6 April 2022. This indicates at this point in
time, there was still an opportunity to restore these items and potentially settle the claim
below the contents sum insured.
The complainant has shown multiple images of the contents stored in her garage which had
not been further protected by AR after attending and treating with anti-mould agents. The
complainant also supplied a text message from her neighbour suggesting her contents of the
garage were being substantially mishandled by JL.
None of the insurer’s evidence has shown mould controls were put into place.
When viewed holistically with the timeline of the strip out and the exceptionally long drying
period, it supports the complainant’s position that the additional loss was not the result of the
insured event, but by mishandling of the repair process.
Accordingly, the panel is satisfied the complainant is entitled to a remedy exceeding the
policy limit. This is because the complainant’s loss is not stemming from the insured event,
but due to errors by the insurer’s tradesmen. The complainant is to provide the insurer with
evidence showing the value of her full contents loss inclusive of storage of any restorable
contents during the repair which she has been able to salvage. The insurer is to assess this
and pay her the fair and reasonable value to settle its liability within 14 days of the
complainant supplying the relevant proof of the value of her loss.
2.2 Is the complainant entitled to compensation for delays?
An award of non-financial loss compensation is warranted
Under AFCA’s rules, we may award a complainant up to $5,400 non -financial loss
compensation if a claim was mishandled by the insurer. We will only award non-financial loss
compensation when a complainant experiences an unusual level of physical inconvenience,
time taken to resolve a matter, or interference with their reasonable expectation of peace of
mind.
The panel is satisfied the insurer mishandled the claim resulting in an excessive level of non-
financial loss impact to the complainant. Accordingly, the panel is satisfied it is fair to award
the full value of $5,400 in these circumstances.
The complainant has had to manage the repair process because the ins urer’s repairers were
not following the scope of work and the insurer has not effectively corrected this.
This led to exceptional physical inconvenience as she was regularly having to contact the
insurer and convince them the builder was not meeting their requirements. The images
supplied show this clearly.
The panel is satisfied the outcome of her efforts has been to prove repair work would not
have been completed to the Australian standard by the builder, had she not objected.
Determination | Case number: 898788 Page 6 of 10
Additionally, the complainant has lost most of her household possessions, including items of
great sentimental value which cannot be replaced. This is despite her reasonable efforts to
protect the items up to her own capacity.
The complainant has also been operating under the concern she will be without temporary
accommodation cover despite the delays. The panel considers this had a serious impact on
the complainant’s peace of mind.
Finally, the situation has evolved to the point it is not reasonable for the insurer to continue
the repair. This means the complainant will continue to experience difficulty as she now must
effectively take over organisation of the repair work.
Accordingly, the panel is satisfied the full amount of $5,400 is warranted.
Complainant has not established lost income
Whilst the panel accepts the complainant has spent time on this claim and complaint, there is
no supporting information to show that she lost income because of the insurer’s claims
handling.
For instance, whilst she says she had to take numerous days off work to manage her case,
no proof of this was provided. It is also not clear if this time off work can be distinguished from
the expected inconvenience a significant claim like this would give rise to as opposed to being
caused by the insurer’s poor claims handling. If it is the former, then this is not payable given
the policy contains an exclusion for consequential loss.
Given this, the panel does not accept there is sufficient basis to make an award for lost
income.
Determination | Case number: 898788 Page 7 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 898788 Page 8 of 10
3.2 Expert and witness evidence summary
Record Key points
Insurer ’s re storer (A R )
Report
16 March 2022
Storm event caused ground water runoff to ent er the property.
Affected carpets removed from the building, applied anti - microbial
treatment and installed dryers due to elevated moisture readings.
Electrician completed make safe on power outlets
Dryers at site from 3 March 2022, and technician returned on 8
March 2022 , 10 March 2022, and 16 March 2022.
Recommends 1200mm of wall needs to be stripped by the builder.
Insurer’s builder ( JL )
Report
8 April 2022
Discussions with the complainant initially confirmed too much
water came through to prevent it entering the hous e.
Water level reported is up to 100mm from the floor.
Complainant tried to remove the water from the house as quickly
as possible.
Damage consistent with the insured event to walls, skirting,
architraves, internal and external doors, cabinetry, GPOs, and
floor tiles.
Recommends replacing wet areas due to damage to waterproof
membranes from the insured event.
Insurer’s re storer (AR)
Report
30 August 2022
Elevated moisture levels still present on 6 April 2022. Drying
equipment installed.
Restorable contents relocated to the garage.
Anti - microbial treatment reapplied to the restorable contents and
moisture affected areas.
Strip out not complete at this stage.
Cont ents loss exceeds policy limit at 26 April 2022 meaning total
loss result.
Returned to the property on 26 July 2022 following strip out to
complete HEPA vacuum of the affected areas.
Returned to the property to install more drying equipment and
apply anti - microbial again on 2 August 2022.
Returned to the property to reposition drying equipment and apply
anti - microbial again on 18 August 2022.
Returned to the property to reposition drying equipment and apply
anti - microbial again on 25 August 2022.
Dry standard ac hieved on 30 August 2022.
Insurer’s building consultant
(SW)
Repo rt
29 November 2022
Instructions were to review the repair work completed to dat e.
Insulation not installed to all external walls.
Wet area drains have grout and rubbish which must be cleaned
out.
Ensuite 2 shower has exposed reinforcing.
No puddle flange installed on concrete slab flooring sewer drain
junction as required by AS 3740 - 2010.
Internal garage door frame damaged.
Front door and internal doors not on site.
Determination | Case number: 898788 Page 9 of 10
Record Key points
Mirrored sliding doors not on site.
Wardrobe joinery not installed.
Plasterboard walls to be sanded ready for pre - paint.
Kitchen joinery doors not aligning as designed and are binding.
Kitchen rangehood not operating.
There is outstanding work, but the work performed to date is of an
acceptable standard.
Builder to provide proof of insulation work, waterproof certificates,
evidence of shower repairs being complet ed before tiling, and
returning all doors to site.
Complainant’s neighbour
(SC)
Witness statement
30 November 2022
Arrived at the property around 11am on 27 February 2022 to assist
the complainant along with others.
The whole house had tide marks up the walls and all rooms had
water damage.
Bedroom carpets were sodden and furniture was already swelling.
Clothes in the wardrobe were totally soaked and/or damp.
Moved furniture and p ersonal into the garage which was the least
affected place in the house and raised furniture off the floor if it
was too heavy to move or needed to be dismantled.
Filled 15 garbage bags with water affected clothes and took them
home to wash and dry, then r eturned them two days later to store
with other contents in the garage.
Complainant’s neighbour
(MV)
Witness statement
4 December 2022
We live directly opposite the complainant and had a call from her
on 26 February 2022 saying her house was flooded.
As sisted the complainant with sandbagging and trenc hes to divert
water from the house.
Assisted with sweeping and squeegeeing water and mud out of
the house.
Assisted with picking up furniture and other belongings off the floor
to try and save what could be saved.
Complainant says the insurer told her to leave everything where it
was until someone could inspect it all.
Weeks later we assisted her to move what we could into the shed,
so the walls could be removed. Substantial mould present by then.
My husband witnessed a team of people throwing out all sorts of
the complainant’s furniture including items she intended to keep as
they were items she was trying to save wit h her efforts.
Complainant’s neighbour
(SS)
Witness statement
5 December 2022
A woke on 26 February 2022 to a large amount of water running
through my yard, so texted the complainant who said her house
was flooded.
Helped the complainant remove items from her home, sand
bagged, dug trenches, mopped and directed water away from the
ho me.
Raised furniture off the floor using bricks and blocks and moved
other furniture to dry areas.
Determination | Case number: 898788 Page 10 of 10
Record Key points
Helped care for the complainant’s daughter while she tried to
mitigate the flood damage and contact the insurer.
Complainant was on the phone for several hours to the insurer.
Assisted the complainant with storing some of her contents and
cleaning her flood affected clothes, linen, soft toys.
Assisted with washing clothes which became affected by the damp
conditions in the building over time, even when they were not flood
affected directly.
Overwhelming smell of mould and damp in the house which has
impacted the contents being stored in the ga rage.
Complainant checked cont ents storage was water tight, and
cleaned furnit ure with vinegar on the day of the flood.