Home / Lloyd's / Determination 897320

Determination 897320

Dispute over cash settlement amount for building works and loss of rent after water damage claim

FirmLloyd's
Decided2023-05-22
ProductGeneral Insurance · Landlord
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A landlord complained that the insurer's cash settlement for building repairs and loss of rent after water damage was too low. AFCA found the settlement, including an extra 15 per cent offer of $5,458.77, was fair and ordered nothing further.

The complainant did not establish the actual repair costs paid, that extra items were caused by the insured event, or when the property became habitable, so the insurer's assessment was fair.

Issues

Subjects and remedies

home or building damagesmall businessno remedy

Related

All Lloyd's determinations · Find similar determinations

Text of the determination

Determination Case number 897320 Financial firm Lloyd's Australia Limited Determination | Case number: 897320 Page 1 of 6 Case number: 897320 12 May 2023 1 Determination overview 1.1 Complaint The complainant holds a shared accommodation insurance policy with the financial firm (insurer). The c omplainant’s representative is a trustee. Any reference to the complainant is a reference to both the complainant and the representative. The complainant lodged a claim for water damage to the insured property. The claim was accepted for repairs to the property and loss of rent. However, a dispute has arisen over the claim amount. 1.2 Issues and key findings Has the insurer fairly cash settled the building works? Yes. The complainant has not established it is entitled to further payment. The insurer ’s cash settlement offer is fair in the circumstances. Has the insurer paid the correct loss of rent costs? Yes. The complainant has not established why further loss of rent is payable. Why is the outcome fair? The complainant has not established the amounts it actually paid for the building works. It is unfair to provide a further cash settlement when the complainant has not shown, on balance, it incurred an additional cost to the amount offered. It is also fair for the insurer to limit its liability for the loss of rent because the complainant has not established, on balance, when the units became habitable. The insurer’s assessment of the loss of rent entitlement is therefore fair in the circumstances. 1.3 Determination This determination is in favour of the insurer. The insurer ’s cash settlement offer, including the additional 15 per cent ($5,458.77) on the amount already provided for the building settlement, is fair in the circumstances. It is not required to pay the complainant any further amount on the claim. Determination | Case number: 897320 Page 2 of 6 2 Reasons for determination 2.1 Has the insurer fairly cash settled the building works? Yes. The complainant has not established it is entitled to further payment. The insurer offered an additional 15 per cent on the amount already provided for the building settlement, which amounted to $5,458.77. It is fair for the insurer to pay this amount in addition to its previous cash settlement offer. Insurer accepted claim and offered a cash settlement On or about 31 January 2022, the complainant lodged a claim for storm damage. The insurer accepted the claim for several areas of damage. It arranged a quote from its builder, PI, for $36,391.80. The complainant provided two repair quotations for the same scope of works covered under PI’s quote , one for $90,314.40 and one for $75,823. The insurer says the total cash settlement made to the complainant is $68,886.30, which included the following:  $24,498.80 for building repairs  $137.50 for anti-slip mats  $3,500 allowance for drying  $17,350 for contents  $24,400 in loss of rent  Less excess of $1,000. The insurer later offered an additional 15 per cent to the building settlement, which amounted to $5,458.77. The complainant says the insurer should accept its quotes The complainant says there are several reasons the insurer should increase its settlement amount:  there was almost a two-month delay in the claim being assessed, leading to further building damage  the quote from PI appeared severely deflated  PI refused to carry out the works, so the complainant offered two quotes for the insurer to choose from  PI claims to not be able to conduct works due to the water damaged floor not being dry, however, sought to settle the loss of rent on an estimated time for the floor to dry, showing the insurer used contradictory reasons to deny or limit the two different covers  there is structural damage and roof damage due to the same insured event that has not been covered  the policy wording does not require the policyholder to keep up with the changing building standards/codes and the complainant says this is impossible and impractical. Cash settlement fair in the circumstances The complainant initially wanted the insurer to undertake repairs. I understand the complainant has now completed repairs, which means it is not necessary to determine whether the insurer is entitled to cash settle the claim. Determination | Case number: 897320 Page 3 of 6 However, for completeness, I do not consider the insurer made an error in cash settling the claim. The product disclosure statement (PDS) outlines how the insurer will settle a claim, which includes, at the insurer’s option, whether to repair, replace or rebuild the property, or paying the insured the reasonable cost to repair, replace or rebuild the damaged part of the building. I accept the insurer has discretion under the policy on whether to cash settle a claim. Such discretion should be exercised fairly and reasonably and consistent with its duty of utmost good faith. The insurer says there are underlying maintenance issues and defects with the property which are not covered under the policy. It says its builder was therefore unable to warrant the works. I accept in circumstances where there are maintenance issues not related to the claim and the insurer’s builder cannot warrant the works, that it is fair for the insurer to cash settle the claim. Insurer is not required to increase the settlement amount The insurer obtained a comparison quote from a different builder, CS, which quoted $35,020.91 based on the scope of works. It says this shows PI’s quote was reasonable. The insurer says the amounts quoted in the complainant’s quotes are inflated, such as for carpet costs being $245 per square metre when the normal rate for a rental room would be $85 to $90 at most. It also says one of the quotes does not provide a breakdown, making it difficult to quantify. I acknowledge the complainant’s concerns that the insurer’s builders would not complete the works privately. However, I do not consider this means the quotes are not fair and reasonable. The insurer has provided an explanation that its builder was willing to complete the accepted works once maintenance repairs were completed, but in the absence of this being done, it was unable to warrant the works. This is understandable. There is insufficient information available to show the quotes PI and CS provided were insufficient to complete the accepted repairs. I acknowledge the complainant has two other quotes. However, it says the repairs have been completed and has not confirmed the actual amounts paid for the repairs. It is therefore unclear whether the quotes provided reflect the actual loss to the complainant. It would be unfair to require the insurer to pay more than the actual loss incurred. In the absence of sufficiently compelling information from the complainant to show the amount cash settled was insufficient to complete the accepted repairs, I consider the amount the insurer paid was fair and reasonable. The complainant also paid an additional $220 for fixing a roof leak and $2,574 to rectify wall cracks which appeared after the storm. The complainant says both of those areas were caused by the insured event. The invoice for room four states it was to ‘F ix roof leak and block hole where possums were entering’ . This invoice is dated 5 October 2022, when the date of loss was 30 January 2022. The wall cracks in room nine were not listed in the other quotes. It is unclear how the cracks only appeared in one room and why it was not reported by the time the quotes were Determination | Case number: 897320 Page 4 of 6 prepared. It also is unclear how long after the event the cracks appeared or what the wall looked like before the event. I acknowledge the complainant’s request to have the two above item s included. However, the complainant has not provided persuasive information to show these were damaged in the same insured event. This means I consider it fair for the insurer to limit its liability to the amount already offered for cash settlement, including the additional $5,458.77 for building works. 2.2 Has the insurer paid the correct loss of rent costs? Yes. The complainant has not established why further loss of rent is payable. Policy only allows for loss of rent cover in specific circumstances The PDS states: 5.1 Loss of Rent for Tenanted Properties When the Building, as defined below, is a tenanted property under a Lease and becomes uninhabitable following physical loss or damage caused to the Building or to the Building of which it forms part, which occurs during the Period of Insurance and that loss or damage is: (a) covered under an insurance policy; and (b) not excluded by the General Exclusions section. We will pay You rent for the period during which the Building remains uninhabitable because of that loss or damage, up to a maximum period of 12 calendar months, limited to $15,000 or the amount specified in the Schedule. There is no dispute the insurer has already covered some loss of rent applicable to the claim. However, the insurer has limited its liability for loss of rent and the complainant disputes this assessment. The insurer calculated loss of rent as $24,400, saying the upstairs rooms were unaffected by the water damage, but allowed one week’s rent for restriction of access. It says the loss of rent has been limited to six months. It says repairs were not able to be immediately undertaken due to a lack of ventilation to the subfloor, which is not related to the claim. It says if ventilation had not been impeded, six months would be ample time for the subfloor to have dried out, therefore it is entitled to limit loss of rent to six months. It also says it is not liable for loss of rent for upstairs rooms that were not affected. The insurer says PI advised the insured repairs would take no more than three weeks to complete. The insurer says the policy allows for loss of rent while the building remains uninhabitable, however the complainant has not provided evidence of when the building became habitable. It says the complainant has re-tenanted some rooms but has not supplied information on the building costs incurred and when these took place. It also says the information from the Determination | Case number: 897320 Page 5 of 6 complainant shows one of the units was re-tenanted during a period the complainant says the building was uninhabitable. The insurer also says some of the most recent calculations from the complainant contradict the information from the property manager, who advised different dates for when the tenants moved out. Complainant says further loss of rent is payable The complainant says the loss of rent cover should increase because:  the ground flood facilities such as the hallway, kitchen, bathroom, and dining form part of the lease and were unusable to tenants renting rooms on the first floor  the policy wording states the maximum loss of rent is for 12 months  the entire building could not be rented out because the claim was delayed following the insured event and subsequent repairs. The complainant submitted a letter from its managing agents (IR), dated 25 November 2022. IR stated the ground floor suffered extensive water damage. The tenants were issued a termination notice. The letter from IR does state there were five rooms on the first floor which were undamaged, but the ground floor disruptions (such as the damaged staircase) meant the rooms could not be leased. The complainant submitted a summary of the rooms vacated and re-tenanted. The complainant says the carpeting for the ground hallway was completed on 2 September 2022 and the painting and skirting boards of the communal kitchen and dining area was completed on 30 November 2022. On balance, insurer correctly settled the loss of rent portion of the claim I do not consider the complainant has provided sufficient information to show the insured event was the cause of all rooms becoming uninhabitable, as some tenants moved out after the event. I also cannot be satisfied, on balance, on what date the property became habitable based on the complainant’s information. The complainant, as noted above, has confirmed that repair works were completed. However, there is no clear explanation of all the works completed and the dates this occurred. The limited information regarding the carpeting and painting is not sufficient to show this. The policy is not designed to cover a policyholder because it cannot re-tenant the rooms. The insurer is also not liable to cover loss of rent because the loss of rent amount listed in the policy was $120,000. Further, AFCA must be satisfied the insured event was the cause of the rooms being uninhabitable. The complainant, on balance, has not established the rooms were uninhabitable for the entire period claimed. I consider it fair in all the circumstances, given the lack of information and sometimes conflicting information from the complainant, for the insurer to limit its liability for loss of rent to the amount offered. Determination | Case number: 897320 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.