Insurer declined cover for damage to concrete stairs and pathway after a landslide, citing gradual deterioration and pre-existing damage exclusions
Text of the determination
Determination
Case number 895647
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 895647 Page 2 of 9
Case number: 895647 13 April 2023
1 Determination overview
1.1 Complaint
The complainants hold a home building and contents policy (policy) with the financial firm
(insurer). A claim was lodged for damage to the insured property caused by a landslide event
following a significant storm on 8 March 2022.
The insured has partially accepted the claim. The insurer says the complainants have not
shown the damage to the concrete stairs and pathway is due to the event. Rather, it says the
damage has been occurring gradually over an extended period of time due to several
contributing factors.
The compl ainants dispute the insurer’s position and say there was no pre -existing damage to
the stairs and pathway. The damage is due to the landslide event and should be covered.
They have provided a repair estimate from builder ’s ‘H’ at around $89,000.
1.2 Issues and key findings
Is the insurer’s assessment of its liability reasonable?
Yes. The insurer is entitled to limit its liability under the claim. The available information
shows it is more likely that the stairs and pathway had pre-existing damage which has been
developing gradually over time. The landslide event may have exacerbated the damage, but it
has not been shown to be the dominant cause for the damage.
Accordingly, it is fair in the circumstances that the insurer be permitted to decline cover for the
stairs and pathway under the claim.
Why is the outcome fair?
The complainants have not shown, on balance, the damage to the stairs and pathway is due
to the landslide event. The damage to the stairs and pathway is more likely to have existed
before the event and is due to several contributing factors. It would not be f air to require the
insurer to cover this damage in line with the policy provisions.
1.3 Determination
This determination is in favour of the insurer.
The insurer is entitled to limit its liability under the claim. It is fair in the circumstances that the
insurer be permitted to decline cover for the stairs and pathway under the claim.
Determination | Case number: 895647 Page 3 of 9
2 Reasons for determination
The available information shows that the insurer has partially accepted the claim. The insurer
accepts the landslide event has caused damage to a retaining wall and which also required
immediate make safe works. The complainants have been covered for the make safe works
and cash settled around $53,000 for the damage to the retaining wall.
Given the above, consideration of this complaint will be limited to the damage to the stairs
and pathway, this being the damage which remains in dispute between the parties.
2.1 Is the insurer’s assessment of its liability fair ?
Yes. The damage to the stairs and pathway has not been shown to be due to the storm or
associated landslide event. Rather, this damage has been occurring gradually over time due
to circumstances excluded under the policy.
Policy covers damage at property subject to conditions and exclusions
There is no dispute the insurer provided the complainants with the relevant policy
documentation including the certificate of insurance (COI) and product disclosure statement
(PDS). I am satisfied it is fair that the insurer be permitted to rely on the policy provisions to
assess its liability under the claim.
The policy, although an insured events policy, also includes the optional benefit covering
accidental damage to the insured building and contents. Given this, in addition to the listed
insured events, the policy also extends cover to any unexpected and unintended loss or
damage. Cover under these benefits is subject to the conditions, limitations and exclusions
provided in the PDS.
Complainants have established a valid claim
The complainants are first required to show, it is more likely than not, that the loss or damage
claimed triggers cover under the policy. Only if the complainants can do this, will the duty shift
to the insurer to show, on balance, it is entitled to decline cover in line with the policy wording
or otherwise.
The insurer does not dispute an event covered under the policy occurred and which caused
damage to the insured property. However, it says the complainants have not shown the
damage to the stairs and pathway is due to an insured event.
Given the optional accidental damage benefit, I accept the complainants are not required to
show the damage is because of the said event but only that the damage was unexpected and
unintended. There is no suggestion that the damage to the stairs and pathway was intended
or expected, so I accept it is accidental damage. The insurer bears the onus to show it is
entitled to limit its liability under the claim in line with the policy provisions.
The parties have provided conflicting information
The insurer appointed engineering consultant ’s ‘EN’ to investigate the cause and extent of the
damage. EN attended the insured property on or about 14 March 2022 to complete its
investigations. It has provided a forensic engineering investigations and causation report
dated 16 March 2022. In this report EN assumes the front of property faces north with a steep
slope from the north to the south side of the property.
Determination | Case number: 895647 Page 4 of 9
EN, relevant to the areas of damage in dispute, notes:
movement has been sustained within the concrete footpath laid across the rear of the
property
the concrete footpath has been constructed across the slope of the land in which general
rainfall activity would erode and undermine the concrete pavement as noted
there were horizontal gaps between concrete pavement of up to 80mm
the edges of the cracks within with the concrete footpath pavement were rounded and
appeared to be pre-existing
the concrete footpath has been laid on inadequate foundation base material which would
not be sufficient to support the pavement.
EN says the damage to the pathway is due to several causes including the inadequate
construction of the pavement on unsuitable foundation. EN accepts the pathway may have
been constructed prior to the inception of the building codes. However, it says the damage is
not consistent with being the result of a one-off event.
EN says the damage had been occurring over an extended period of time due to it being
constructed on an inadequate foundation base material and long-term erosion of the
foundation materials. It notes edges of the cracking damage are rounded which indicates long
term damage i.e. it is pre-existing damage. EN provides photos in support of its position.
The complainants appointed geotechnical consultant ’s ‘C’ to complete investigati ons into the
landslide and associated damage. C provided a geotechnical inspection report dated 19 April
2022 after attending the site on 9 March 2022 and 31 March 2022. I note that C refers to the
south side of the property as being the front which I note EN refers to as the rear. I am
satisfied, despite the different approaches, both consultants have assessed and reported on
the same areas of damage.
C says it is evident that a landslide has occurred across the south-west corner of the site
extending across the entire lawn area at the front of the dwelling. It then passed adjacent to
the south-west corner of the lower ground floor area and then striking down towards the road
reserve to the south/south-east corner of the property.
The slide has resulted in most of the front of the site being displaced down slope with all
trees/garden and structures within this zone. C says this includes the concrete block retaining
wall, pathway and plumbing. C says the slide occurred because of saturation and subsequent
mass increase of the surficial soils. This includes the large mass of retained soil adjacent to
the dwelling, within a steeply south dipping slope.
C notes deformation within the slope is most significant at the crest of the slide, impacting
where it intersects structures and also towards the base where ground surface heave has
impacted the stairs and pathway. C has provided a second report dated 31 May 2022 titled
Geotechnical investigation into landslide . In this report. C says the landslide covers
approximately 40% of the site. It notes soil and vegetation had passed over the concrete
gutter and had begun encroaching onto H Road (south of the property).
The geotechnical engineer completed a walkover inspection and mapping of the site. Four
auger boreholes were drilled to investigate the sub-surface geology. DCP testing was carried
out from the ground surface adjacent to boreholes and at nine separate locations to estimate
near surface soil conditions and depth to bedrock.
The insurer sought comment from EN regarding the information from C, which it has provided
in a supplementary report dated 21 July 2022. EN says the geotechnical report reference to
the site being covered by topsoil is consistent with EN findings. Further that topsoil is not a
Determination | Case number: 895647 Page 5 of 9
suitable foundation material to be constructed on with movement to any building elements
constructed over such material expected. EN says this corroborates its finding that the
concrete footpath had been laid on an inadequate foundation base material which would not
adequately support the pavement.
EN says it also concurs with C’s report that the landslide has occurred from the intensity of
the rainfall . EN says the geotechnical reports do not dispute with EN’s opinion that:
the concrete footpath has been constructed across the slope of the land in which general
rainfall activity would erode and undermine the concrete pavement as noted
the concrete footpath has been laid on inadequate foundation base material in which
would not be adequate to support the pavement.
the crack edges are rounded and appeared to be pre-existing of the claimed storm event.
Given this, EN is of the opinion it is reasonable to maintain the position that the damage to
the stairs and pathway is not attributed to a single storm event.
The complainants have also provided a letter from C dated 6 June 2022 and two statements
from individuals in support of the position there was no damage to the stairs and pathway
before the landslide event. In its final letter (6 June 2022), C essentially reiterates its key
findings and says movement caused by the landslide undermined the existing concrete
pathway damaging it in multiple locations.
C noted further movement with most of the south side impacted by the landslide on returning
to the site on 31 March 2022. C reconfirms its opinion the catalyst for this landslide can be
attributed to the intense rainfall event on the 8 March 2022, and the preceding prolonged
rainfall period. C also confirms its recommendation provided in previous reports relating to
remedial measures to stabilise the slide/site.
The statement from ‘AG’ dated June 2022 says they h ave visited the site regularly over the
previous 20 years, accessing the property via the stairs and pathway. AG says the stairs and
pathway were in order and not misplaced or broken before the storm event. The statement
from ‘TH’ dated 20 June 2022 says T H can confirm the footpath moved after the landslide
with there being no cracks or gaps before this event.
EN in its report dated 21 July 2022 has provided historical photos (September 2019 and
November 2020) which is says show pre-existing damage to stairs and which it says is
contrary to the statements from AG and TH.
Information shows it is fair for the insurer to limit its liability under the claim
I have carefully considered all the information and find the insurer’s position to be more
persuasive. I accept the complainants have shown there is damage to the insured property to
which the policy responds, however, not that this damage extends to all the damage claimed.
I am satisfied it is reasonable to accept the damage to the stairs and pathway has been
developing over an extended period of time because of multiple contributing factors. It may
well be that the landslide further exacerbated and/or highlighted damage but in my opinion, it
is not the dominant cause.
I accept the damage is accidental to which triggers cover under the policy. However, as noted
above this benefit is subject to the policy limitations and exclusions. The policy excludes
damage caused by or arising from:
wear, tear, depreciation, rust, oxidisation, corrosion, fading;
defect, structural fault, design fault or faulty workmanship
previous damag e that hasn’t been repaired; or
Determination | Case number: 895647 Page 6 of 9
gradual deterioration due to action of atmospheric or climate conditions.
There are examples in the PDS regarding gradual deterioration which include the gradual
weathering of bricks, mortar or concrete and the breakdown of grouting of tile adhesive over
time.
With respect to the information from C, I accept it is detailed and well-reasoned. However, the
information for the most part relate to the mechanics of the landslide event and
recommendations regarding how the site can be stabilised following the event. I accept this
information provides a good understanding of what occurred, why it occurred and what
measures are now required to prevent it occurring again.
However, C’s information lacks details and supporting information in terms of showing the
damage to the stairs and pathway were due to the landslide event. I note C says the damage
is due to the landslide event, however, C has not provided any persuasive information
supporting/showing:
how the event has caused damage to the stairs or pathway
the extent or degree of such damage, if it was caused by the event.
I am satisfied the information from EN is more persuasive with respect to the damage in
dispute. Whilst C’s reports are more focused in the geotechnical aspects and mechanics of
the event, EN’s information is more focused on the damage and the reasons for the damage.
I accept the landslide event will have exacerbated the damage to an extent. However, in my
opinion, the information supports the view that the damage to the stairs and pathway had
been developing gradually over an extended period due to multiple contributing factors.
These being:
their method of construction given the location (across and down a slope of the land)
the location and method of construction being susceptible to rainfall activity which has over
time eroded and undermined the foundations. I note this is supported in C’s reports as well
which refer to the impact of the prolonged and intense rainfall events experienced by the
east coast of Australia throughout 2022
the photos of the gaps between the concrete do not appear recent i.e. not from the
landslide event. Rather, this damage appears weathered and consistent with long term
movement
the photos show there is clearly long-term erosion and undermining of the supporting
foundations for the pathway
the edges of the cracks within with the concrete footpath and pavement are rounded and
appear to be pre-existing
there are historical photos showing damage to the stairs from 2019 and 2020, in a similar
location to that noted in the consultants’ reports i.e. pre -existing damage.
I note the complainants’ concerns regarding the insurer’s reference to the Australian
Standards, and that these do not apply to the construction of the stairs and pathway (given
the time of their construction). However, I accept the insurer’s explanation t hat it has not
relied on these standards as a basis to decline the claim. Rather, it has provided this
information to assist in explaining how and why the stairs and pathway were more susceptible
to gradual deterioration and damage.
Without persuasive information to the contrary, I am satisfied it is fair that the insurer be
allowed to rely on the policy provisions to limit its liability under the claim. I am satisfied the
insurer has shown it is more likely the damage to the stairs and pathway is because of
gradual deterioration over time due to climatic conditions, wear and tear and has existed for
Determination | Case number: 895647 Page 7 of 9
quite some time. The policy excludes such loss or damage and I note even provides specific
examples of such damage including gradual weathering of mortar or concrete .
Accordingly, I am satisfied it is fair that the insurer decline cover for the cost to repair/rebuild
the stairs and pathway under the claim.
2.2 Why is the outcome fair?
The complainants have not shown, on balance, the damage to the stairs and pathway is due
to the landslide event. The damage to the stairs and pathway is more likely to have existed
before the event and is due to several contributing factors. It would not be fair to require the
insurer to cover this damage in line with the policy provisions.
Determination | Case number: 895647 Page 8 of 9
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Relevant policy wording
General exclusions
The general exclusions apply to sections of this Policy
...
Condition of your buildings
There is no cover under any section of your Policy for any claim, loss, costs,
damage, injury, death or legal liability caused by or arising from:
...
Determination | Case number: 895647 Page 9 of 9
There is no cover under any section of your Policy for any:
Wear, tear, depreciation, rust, oxidisation, corrosion, fading;
Defect, structural fault, design fault or faulty workmanship
...
Previous damage that hasn’t been repaired; or
Gradual deterioration due to action of light, air, sand, sea salt, sea water,
or atmospheric or climate conditions.
For example, the gradual weathering of brick, mortar or concrete or the
breakdown of grouting of tile adhesive over time.