Insurer's cash settlement for defective fire repairs, refusal of additional repairs and loss of rent, and non-financial loss

FirmSuncorp Group
Decided2023-04-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$246
Non-financial loss$1,200
Amount claimed$20,000
SourceAFCA PDF

Summary

The complainant, who inherited an investment property, disputed the insurer's cash settlement for defective fire repairs and sought additional repairs, loss of rent and compensation. AFCA increased the contingency uplift to 25%, awarded $1,200 non-financial loss, and rejected additional repairs and loss of rent.

The complainant did not prove further damage resulted from the builder's poor workmanship or that the property was untenantable, but the old quotes warranted a higher uplift and poor claim handling justified greater compensation.

Issues

Subjects and remedies

home or building damagepay claimpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 894227 Financial firm AAI Limited Determination | Case number: 894227 Page 1 of 7 Case number: 894227 3 April 2023 1 Determination overview 1.1 Complaint GM held building and contents insurance with the financial firm (insurer) covering his investment property. In 2010, he lodged a fire damage claim. The insurer ’s builder, P, completed repairs in 2011. GM died in late 2020. The complainant inherited the property. In March 2022, the complainant notified the insurer of issues with P’s repairs. These included laying carpet over burnt floorboards, poorly installing a windowsill and not reinstating roofing. Based on quotes from its builder JL plus a 15% contingencies uplift, the insurer has offered $2,824.74 to cash settle the cost to replace the windowsill and a section of floorboards. It has also offered $500 in compensation for stress it has caused. It denies it is otherwise liable. The complainant says the offer is too low and does not address all of the required repairs. She also seeks payment for loss of rent (LOR) and $5,400 in compensation for stress. 1.2 Issues and key findings Is the insurer required to cover additional repairs? No. Based on the available information, the complainant has not shown that the additional repairs she seeks to be undertaken are the result of P’s poor workmanship. Is the insurer’s cash settlement offer reasonable ? No. JL’s quotes adequately address the works reasonably requi red. However, as those quotes are now about 12 months old, a reasonable contingencies uplift is 25%. Is LOR payable? No. The complainant has not proven P’s poor workmanship or the limited repairs required to rectify it has or will render the property unliveable or otherwise untenantable. Is more non-financial loss compensation payable? Yes. The insurer’s offer is not sufficient compensation for the stress and inconvenience its delays and poor claim handling have caused. It is to pay the complainant $1,200. Why is the outcome fair? It is fair that the insurer pays an increased contingencies uplift gi ven JL’s quotes are nearly a year old and that it pays more to adequately compensate the complainant for her stress. 1.3 Determination This determination is partially in favour of the complainant. Within 14 days of the complainant accepting the determination, the insurer is required to pay her $1,445.64, made up of:  $245.64 ($3,070.38, being JL’s quotes plus 25%, less $2,824.74 paid to date), and  $1,200.00 in non-financial loss compensation. Determination | Case number: 894227 Page 2 of 7 2 Reasons for determination The parties provided numerous submissions to AFCA. While this determination does not refer to them all, I have taken each submission into account in reaching my decision. 2.1 Is the insurer required to cover additional repairs? No. Based on the available information, the complainant has not shown that the additional repairs she seeks to be undertaken are the result of P’s poor workmanship. Complainant has raised numerous concerns about P’s repairs On 15 November 2010, GM lodged a claim for fire damage to the property. The insurer’s assessment established that the main damage was to bedroom one. The areas damaged included the ceiling, walls, window, carpets and curtains. Other rooms were smoke affected. P was appointed to attend to claim related repairs. Works were completed in late March 2011. On 3 March 2022, the complainant informed the insurer she had inherited the property and, on inspection, noticed a strong smell of smoke. She said on pulling up the carpet and underlay in bedroom one, she found charred floorboards. The complainant says on further investigation, she discovered that P did not or did not adequately undertake repairs, leaving the following issues to be addressed: Area Issue s Bedroom one flooring  Charring affecting eight floorboards, requiring full replacem ent  Potential fire damage to joists and bearers  Staining to underlay and carpet laid on top of charred floorboards Bedroom one window  Steel window frame replaced with inferior alu minium frame  Poorly installed brick window sill Bedroom one air vents  Removed and not replaced , leading to a risk of mould Bedroom three  Burn marks to floor at doorway Kitchen  Ineffective painting of cabinetry, with water paint not adhering to pre - existing oil paint Carpet ing  Old carpet staples not removed, causing damage to replacement underlay and shoes  Rubbish and debris left under carpet Roof  Roof tiles dislodged by fire service while extinguishing fire not reinstated The complainant has submitted numerous photos and a contemporaneous report from the fire service but did not provide any expert reports. She wanted the insurer to pay her $3,600 to obtain an engineering report but the insurer would not unconditionally agree to do so. She estimates the cost to attend to all rectification works would be $20,000. She is reluctantly willing to accept a cash settlement in that sum. Insurer says it is not liable for repairs beyond what it has offered to rectify The insurer says that after the complainant raised her initial concerns, it appointed builder JL. It says that on 28 March 2022, its internal assessor, internal building consultant and JL jointly undertook an assessment of the property. Determination | Case number: 894227 Page 3 of 7 I acknowledge that the complainant says that the assessment could not have taken place that day. However, as each of the assessor, building consultant and JL have provided reports, I am satisfied there was an assessment. Those reports indicate that:  the complainant was renovating the house, and in doing so had removed all carpeting and kitchen cabinetry  there were superficial scorch marks on some of the floorboards in bedroom one as well as paint marks. This damage was rectifiable by sanding back the floorboards  there was widespread seasonal ground movement damage, in cluding to bedroom one’s windowsill  the marking at the entrance to bedroom three was more in line with foot traffic related wear and tear than fire damage  there were carpet staples still in the floor, but it was unclear whether P had failed to remove them when it replaced the burnt carpet or if P had installed them and they remained in place after the complainant pulled up the new carpet  a street view image showed the roof’s condition was poor, but til es had not been disturbed  the property overall had been the subject of wear and tear and gradual deterioration. SP, the insurer’s roofing expert , inspected the property on 1 April 2022. SP confirmed there was water ingress damage to bedroom one. It said this was due to poorly moulded roof tiles above it rather than slipped or broken tiles. SP noted the roof was in a deteriorated condition. MC, the insurer’s expert engineer, inspected the proper ty on 11 May 2022. MC concluded:  sanding of the scorched floorboards would not remediate the damage. Instead, an area of floorboards approximately one metre 2 would need to be replaced  brickwork cracking was due to long term building settlement not associated with the fire  the windowsill misalignment was due to poor installation/workmanship  the floorboard discolouration at bedroom three’s doorway was not related to the fire  the property presented with no other fire event related damage. In relation to the bedroom one window frame, the insurer says it is unlikely that the original frame was steel. Further, it says if the frame was steel, replacing it with an aluminium frame amounts to an improvement given the propensity of steel to rust over time. The insurer acknowledges the complainant is concerned P removed two air vents from bedroom one and did not replace them. However, it says that neither GM before his death or any of the experts involved raised this as an issue. In the circumstances, the insurer has accepted that it is liable for the cost to replace the windowsill and the burnt area of floorboards. This is because the PDS includes a lifetime guarantee applying to workmanship and materials used in repairs performed by its trades. However, it says it has no liability for the remaining issues identified by the complainant. Insurer is not required to cover additional repairs I am not satisfied that the complainant has shown that the insurer is responsible for any of the damage claimed beyond the windowsill and burnt floorboards. This is because:  there is no expert evidence to support a conclusion that any of the additional damage should be attended to by the insurer under the lifetime repair guarantee  the available expert evidence is consistent in finding that the additional damage is not fire related, but is due to excluded factors such as wear and tear and gradual deterioration  the complainant’s renovation of the property means some of the issues she has identified in relation to P’s work, such as not properly painting the cabinetry and leaving rubbish under the carpet, are now irrelevant and/or cannot be properly assessed Determination | Case number: 894227 Page 4 of 7  there is no expert evidence to support a finding of ongoing smoke odour. Accordingly, the insurer is not required to cover the additional repairs sought. 2.2 Is the insurer’s cash settlement offer reasonable? No. JL’s quotes adequately address the works reasonably required. However, as those quotes are now about 12 months old, a reasonable contingencies uplift is 25%. Insurer has offered a cash settlement On 5 April 2022, JL provided a scope of works (SOW) and quote to sand back the floorboards in bedroom one, costing the work at $1,435.50. Following receipt of MC’s report, the insurer asked JL to prepare an SOW and quote to remove and replace the burnt area of the bedroom one floorboards and the windowsill. On 26 May 2022, JL provided the SOW and quote, totalling $1,020.80. The insurer has offered to pay the complainant a cash settlement of $2,824.74, being the combined total of JL’s quotes, plus a 15% uplift to take into account contingencies. On 25 January 2023, the insurer advised that JL ‘have confirmed that the scope of work is actionable to date – pricing is still relevant’. The insurer has paid the complainant the $2,824.74. Complainant says the offer is insufficient The complainant says that t he insurer’s cash settlement offer is insufficient to cover the cost of rectifying the floorboard and window sill damage. She says that JL has used ‘mate’s rates’ rather than market rates available to consumers, so its quotes are not actionable. In addition, she notes that labour and material prices have significantly increased since JL prepared its quotes in April/May 2022. The complainant says the eight fire damaged floorboards require replacement and that new boards will need to be machined (tongue and grooved). She says MC supports her position. She has provided a quote dated 16 October 2022 from OF, flooring supplier, totalling $7,150. Insurer must increase contingencies uplift I am satisfied that it is appropriate for the insurer to cash settle the repairs for which it has accepted liability given the amount of unrelated damage also affecting the property. To be entitled to a higher cash settlement amount, the complainant must demonstrate that the insurer ’s offer does not reasonably reflect the likely retail costs of repairs. This requires the complainant to show one or more of the following:  the SOWs the insurer relies on do not adequately encompass the required repairs  the quotes the insurer relies on are under priced  the insurer has failed to include a reasonable contingencies uplift. Based on the available information, I am satisfied that JL’s SOWs encompass the required repairs. MC does not support full replacement of the fire damaged floorboards. It clearly states that only a section of floorboards approximately one metre 2 requires replacement. There is no information to show that it would not be possible to replace only a section of floorboards. The policy requirement to provide a uniform floor covering appearance in a room Determination | Case number: 894227 Page 5 of 7 does not apply. The floorboards were covered by carpet so were not floor coverings. Further, the complainant was recarpeting so any lack of floorboard uniformity would be hidden. I am not satisfied that the complainant has established that JL’s quotes were under priced. While the complainant says that JL has used ‘mate’s rates’ rather than retail prices, the only quote she has provided is OF’s. That quote is for more work (full floorboard replacement) and provides a total rather than an itemised price. It is not comparable. However, I agree with the complainant that labour and material costs will have increased since JL prepared its quotes nearly 12 months ago. The insurer says that in January 2023, JL advised it that the pricing was still relevant. That is not necessarily the same as being fully competitive in the open market. Also, inflationary pressure has continued since January 2023. Accordingly, I consider that it is reasonable that an increased contingency uplift of 25% be applied to a cash settlement based on JL’s quotes. That takes the amount payable by the insurer to $3,070.38. After deducting the $2,824.74 previously paid, $245.64 is outstanding. 2.3 Is LOR payable? No. The complainant has not proven P’s poor workmanship or the limited repairs required to rectify it has or will render the property unliveable or otherwise untenantable. Complainant seeks payment for LOR The complainant seeks LOR of approximately $330 per week from 7 January 2022 until her claim/complaint is resolved. She has provided an email from the property’s managing agent confirming there were tenants ready to commence a six month lease from 7 January 2022, at $1,39 0 per month. The email says the tenancy did not proceed at the complainant’s request. According to the complainan t, MC’s report confirms the property was uninhabitable and unsuitable for renting . She says in addition, her ‘own conscience and excellent work ethics’ prevented her from renting the property in the state the insurer and P had left it in. Insurer says it is not liable for LOR The insurer says LOR is not payable because:  the property was not tenanted when the damaged floorboards were discovered  the complainant was already renovating the property at that time  there is no available evidence suggesting tenants had left prematurely due to issues it had caused and for which it was responsible. LOR is not payable I am not satisfied that LOR is payable by the insurer. MC’s report does not suggest the property was uninhabitable and unsuitable for renting. JL reported that the property was habitable at the time of its assessment and would be habitable during repairs. The property appears to have been consistently tenanted from when P completed repairs in March 2011 until December 2021. Further, in December 2021, new tenants had signed a lease agreement and paid a security deposit and the first month’s rent. This indicates the property was and continued to be habitable and tenantable. Determination | Case number: 894227 Page 6 of 7 I also note that JL has suggested the covered repairs would take approximately a day. I do consider that period sufficient to disrupt the complainant’s ability to rent the property out. 2.4 Is more non-financial loss compensation payable? Yes. The insurer’s offer is not sufficient compensation for the stress and inconvenience i ts delays and poor claim handling have caused. It is to pay the complainant $1,200. AFCA can award compensation for poor claim handling Under paragraph D.3.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $5,400) where the insurer’s actions have caused an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant’s expect ation of enjoyment or peace of mind. Insurer’s claim handling unre asonably caused stress and inconvenience The complainant says that the manner in which P completed the repairs was dishonest and unconscionable, causing her severe inconvenience in ‘having to pick up the pieces and correct the builder ’s shonky work and clean up after him’. She also says that her experience has been horrific and very distressing. She says the insurer’s conduct and delays have caused her major stress and anxiety, such that she should receive a maximum award of non-financial loss compensation. The insurer acknowledges that it must have been frustrating for the complainant to discover that some repairs were missed during the original assessment of the first claim. It also accepts that it was responsible for a two month unreasonable delay in assessing her claim. It has offered the complainant $500 in compensation. I am not satisfied that represents sufficient c ompensation for the complainant’s stress and inconvenience. I note that in addition to the claim handling issues the insurer acknowledges, the complainant had to go through two IDR processes before the insurer agreed to cover the windowsill repair and pay a cash settlement contingencies uplift. She should not have had to do so. On the available information, this is not a case for a maximum award. I am satisfied that in the circumstances, $1,200 represents fair and reasonable compensation payable by the insurer. 2.5 Why is the outcome fair? It is fair that the insurer pays an increased contingencies uplift given JL’s quotes are nearly a year old and that it pays more to adequately compensate the complainant for her stress. However, it would be unfair for the insurer to have pay anything more than that as the complainant has not established an entitlement to LOR or cover for additional repairs. Determination | Case number: 894227 Page 7 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.