Home / Suncorp Group / Determination 892266

Determination 892266

Storm damage claim: extent of cover accepted and cash settlement amount, plus claim management and delay

FirmSuncorp Group
Decided2023-04-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,000
Amount claimed$118,263
SourceAFCA PDF

Summary

The insurer accepted a storm claim and offered a $29,102.98 cash settlement, while the complainant sought $118,263. AFCA upheld the insurer's limit on liability but required settlement using CE's quote for J's final scope plus 15%, reimbursement of quote costs and curtains, and $2,000 non-financial loss.

The insurer could limit liability to storm damage on the more persuasive engineering evidence, but its preferred consultant's quotes were unreliable and its claim management caused unusual delay and inconvenience.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 892266 Financial firm AAI Limited Case number: 892266 18 April 2023 1 Determination overview 1.1 Complaint The complainant holds a home building and contents policy (policy) with the financial firm (insurer). On 4 November 2021, a claim was lodged for storm damage to the insured building and contents on or about 28 October 2021. The insurer has accepted the claim and offered a cash settlement of $29,102.98 for damage it has assessed to be due to the storm . The complainant is dissatisfied with the insurer‟s assessment of its liability and the overall management of the claim. The complainant is seeking a settlement of $118,263 and non-financial loss compensation, given his poor experience over the life of the claim. 1.2 Issues and key findings Is the insurer’s assessment of its liability under the claim fair? Yes. The insurer‟s assessment of the damage to be accepted under the claim is fair and consistent with the available information. However, it would not be fair for the insurer to settle the claim based on the quote from its preferred consultants „J‟. The claim is to be settled as outlined in section 2.1 of this determination. Is the complainant entitled to non-financial loss compensation (NFL)? Yes. The insurer is required to pay the complainant $2,000 in NFL arising from its poor management of the claim and associated delays. The complainant has experienced unreasonable levels of stress, inconvenience and delays over the life of the claim. Why is the outcome fair? This outcome is fair because it acknowledges the insurer‟s entitlement to limit its liability based on the more persuasive information. However, that the insurer is to increase its claim settlement offer based on the more current and actionable repair costs presented by „ CE ‟ . It is fair that the insurer pay the complainant NFL in the circumstances. 1.3 Determination This determination is partially in favour of the complainant. The insurer is to increase its final claim settlement as set out in section 2.1 of this determination and pay $2,000 in NFL to the complainant. Determination | Case number: 730453 Page 2 of 8 2 Reasons for determination 2.1 Is the insurer’s assessment of its liability fair? Yes. The insurer‟s assessment of the damage to be accepted under the claim is fair and consistent with the available information. The insurer is entitled to limit its liability under the claim. The policy is an insured events contract of insurance The insurer provided the complainant with the relevant policy documentation including the product disclosure statement (PDS) and certificate of insurance (COI). I accept the insurer is entitled to rely on the policy provisions to assess its liability under the claim The policy covers the insured property against loss or damage caused by one or more of the listed insured events, including „ Storm ‟. Cover under these benefits is subject to the conditions, limitations and exclusions specified in the PDS. The complainant has established a valid claim There is no dispute a storm event took place on 28 October 2021. Further, that the insured building and contents suffered stormwater ingress damage, which triggers cover under the policy. I note, since lodgement of this complainant with AFCA, the contents damage has been accepted and cash settled under the claim. This determination is limited to considering the buildi ng damage component and the insurer‟s management of the claim . The insurer says the complainant has not established all the damage claimed is due to the storm event. With respect to the main issues in contention, the insurer says:  the claimed cracking damage is due to long term general ground movement, which is excluded under the policy  the extent of insulation works being claimed are excessive and include areas not damaged by the stormwater ingress  it is reasonable to store furniture from the two rooms accepted under the claim onsite while repairs are completed. The parties have each provided information from their appointed consultants The insurer appointed consultant ‟s „J‟ to assess the cause and extent of the damage . J arranged for plumbing consultant‟s „SP‟ to provide a roof report and subsequently completed a site visit on 22 November 2021. In report dated 11 November 2021, SP provides the opinion that the damage was caused in a one-off storm event because of water overflowing back into the property due to a blocked/backed-up stormwater drainage system. J‟s report accepts SP‟s opinion regarding the condition of the roof and stormw ater drainage system. J says the insured building did not present with any event related damage, storm or otherwise. J provided the opinion that damage noted was due to natural house movement. J says there was no need to appoint an engineer and provided a scope of works and repair quote in the amount of $2,118.88. This insurer presented its original claim settlement offer to the complainant on this quote. The complainant declined the insurer‟s offer and obtained his own scope of works and repair quote from consultants „EB‟, which was significantly higher than J‟s quote. The insurer arranged a second assessment by its internal assessor which confirmed not all the damage claimed as covered. However, accepted there were works J had failed to include in its scope Determination | Case number: 730453 Page 3 of 8 of works. J was asked to provide an amended quote, which increased the cost of repairs to approximately $20,000. The insurer increased it cash settlement offer to the complainant, which was declined. The complainant sourced and updated quote from EB which estimates the cost of repairs at approximately $67,000. The insurer says the complainant‟s quotes are excessive, both in terms of the scope of works and costing/rates applied to complete the repairs. The insurer appointed engineering consultant ‟s „JE‟ which has provided an assessment report dated 5 August 2022. Having carefully considered this report, I accept it concludes:  the reported storm event is considered to be insufficient to be the causal mechanism of damage. The building would have been able to cope with the rainfall which occurred at the time of reported damage  the floor level survey was indicative of long-term differential foundation settlement, mainly about the rear of the dwelling. Generalised movement is reasonably expected for a dwelling constructed on reactive soil, with the site assessed as being reactive soil  the proximity of the trees and vegetation mostly at the rear section of the property could have participated in the process of foundation movement, to a certain extent  no significant or slight moisture was noted about the damaged water-stained walls and ceiling linings at the time of inspection  inspection of the roof area found blocked downpipes and inadequate drainage of the roof gutters at the left-hand side of the dwelling  It is recommended for the complainant to engage a roof specialist to address the drainage issues of the roof gutters and blocked downpipes around this property as well as the deteriorated flashing to the roof  there has been a history of foundation movement and damage at this property as evidenced by noted pre-existing cracking and previous attempts to repair this damage. On receiving JE‟s report, the insurer again instructed J to review its scope of works and quote. J again increased its estimated cost of repairs to $29,102.98 and this is what forms the basis of the insurer‟s final claim settlement offer. The complainant has declined this offer and provided a further detailed scope of works and repair quote dated 14 March 2023 from consultants CE in the amount of $93,148.00. AFCA forwarded CE‟s quote to the insurer for consideration and comment, however, it has elected not to provide any comment. Information from the insurer is more persuasive The complainant says the insurer‟s continued reference to “plaster cracking” is inaccurate. The cracking damage is more accurately considered expulsion of the plaster (plaster coming away from the wall). Further, that all the expulsions in dispute are at or near ceiling height, not floor level. This indicates that ground movement is a less likely a source of the damage. There is no cracking under these expulsions. I acknowledge the complainant‟s position, however, he has not provided any qualified and independent supporting information. The scopes of works and quotes that he has provided do not include any comment or opinion on the cause for the damage. This information does not assist in considering the issue of what damage is to be accepted under the claim. In saying that, they did assist in establi shing J‟s initial assessments and associated quotes were not fair and reasonable. I am satisfied the information from the insurer is more persuasive. I accept after the multiple assessments and appointment JE, the insurer has shown, on balance, it is not liable for all Determination | Case number: 730453 Page 4 of 8 the claimed damage. The insurer is entitled to limit its liability to only that damage which it has assessed to be due to storm event in 2021. I accept the complainant‟s concerns regarding the reliability of J‟s costings as a basis for sett ling the claim, which I will consider in more detail below. Cash settlement to be based on J’s final scope of works and CE’s quote Having considered J‟s assessment and associated quotes, I find it concerning that the cost of repairs went from $2,100 to close to $30,000. J‟s initial assessment noted no event related damage and recommended no further investigation was needed. The available information shows each time a different professional assessed the dwelling, J was required to increase the scope of works and therefore its quote. I believe J‟s assessments and quotes appear to try and minimise the cost of repairs to be covered by the insurer. This is especially concerning given these are not actionable quotes with J advising it would not be undertaking the repairs. I also find it concerning that the insurer continued to go back to J, despite it being clear its quotes were not fair, and there was no attempt at getting another builder to provide a comparative quote. This is especially so, when noting the significantly different estimated cost of repairs from J and EB. I note the insurer has repeatedly referred to the quotes from EB not being fair and reasonable, both in terms of the scope of works and costing. However, the insurer has not provided any information to show the costings are excessive or inconsistent with acceptable industry pricing. The insurer has not provided any comment regarding the quote from CE. I note CE‟s quote is the only current and actionable quote before me at the time of providin g this determination. I also note the complainant‟s concerns regarding the delays experienced under the claim and the impact the unavailability of the rooms within the home is having on the family. Accordingly, given the concerns discussed above regarding J‟s information and considering what it fair and will help bring finality to this dispute, the insurer is to:  calculate its liability under the claim based on the final scope of works completed by J after JE‟s assessment of the dwelling  calculate the cash settlement based on what the cost of these works as provided in CE‟s quote (i.e. what CE has quoted for the works to be accepted under the claim in line with this determination)  increase this cash settlement by a further 15% uplift to allow for possible additional costs and the transfer of risk associated with arranging the works  cover the complainant for the cost to move and store the furniture for the reasonable time it will take to complete the repairs accepted under the claim  subject to being provided with proof of payment, reimburse the complainant for expenses incurred in arranging the scopes of work and quotes from EB and CE up to $5,000  reimburse the complainant $764.50 based on his invoice for the cost to remove, clean and re-install curtains. I acknowledge the complainant‟s concerns regarding the insurer‟s decision to cash settle the claim and that this is different to previous claims it has accepted. However, I am satisfied the insurer is entitled to choose the option to cash settle the claim in line with the policy provisions. Further, in the circumstances, I accept choosing this option is not unreasonable. The fact it has chosen to authorise repairs under previous claims does not mean it obliged to exercise the same option for all future claims. The insurer is to arrange the cash settlement in line with the above within 14 days of receiving notice of the complainant‟s acceptance of this determination. The insurer is not required to Determination | Case number: 730453 Page 5 of 8 cover the claimed supervisor costs/complainant‟s time, as th is is clearly excluded under the policy. 2.2 Is the complainant entitled to NFL? Yes. The insurer ‟s overall management of the claim has not been reasonable and has caused delays, stress and inconvenience to the complainant. It is fair that the insurer pays the complainant $2,000 in NFL. AFCA Rules allows for an award of NFL The Rules (Rule D 3.3) allow for an award of up to $5,400 for non-financial loss compensation, if the insurer caused the complainant to suffer an unusual degree or extent of inconvenience, delay or interference. AFCA takes a conservative approach when considering any award of compensation. It is fair the insurer pays the complainant $2,000 in NFL Having considered the all the information, I am satisfied it is fair the insurer be required to pay the complainant $2,000 in NFL. This is because I am satisfied the insurer‟s management of the claim was not to the level expected and contrary to its advertising, as raised by the complainant. I believe had J‟s approach to the assessment and quoting been fair and consistent with the damage noted, the claim would have progressed to conclusion much earlier. It is well known that the costs of repairs have increased significantly over the period relevant to the claim. Also, had the insurer considered bringing in a second builder for comparison and not continually going back to J, this would also have assisted in a possibly earlier resolution and settlement of the claim. The available information shows it took almost 10 months for the insurer to settle the contents damage aspect of the claim. There is no information to show why this was the case or that this delay was reasonable/unavoidable. With respect to the insurer ruling out the complainant‟s quotes, it has failed to provide any persuasive information to support its position. This is despite the complainant having raised this concern and asked the insurer to explain its position regarding his quotes. I am satisfied it is fair to accept the complainant did experience an undue level of stress, inconvenience and delays over the life of the claim. Accordingly, the insurer is to pay the complainant $2,000 in NFL within 14 days of receiving notice of the complain ant‟s acceptance of this determination. 2.3 Why is the outcome fair? This outcome is fair because it acknowledges the insurer‟s entitlement to limit its liability based on the more persuasive information. However, that the insurer is to increase its claim settlement offer based on the more current and actionable repair costs presented by CE. Further, that the insurer ‟s management of the claim resulted in delays and the complainant experiencing stress and inconvenience, so it should pay NFL. Determination | Case number: 730453 Page 6 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 The AFCA process D.3.3 An AFCA Decision Maker may decide that the Financial Firm is to compensate the Complainant for non-financial loss: a) for a complaint relating to an individual‟s privacy rights - injury has occurred to the Complainant‟s feelings or humiliation h as been suffered by the Complainant; or b) for other complaints – an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Complainant‟s expectation of enjoyment or peace of mind has occurred. Determination | Case number: 730453 Page 7 of 8 3.3 Relevant policy wording How we settle building claims We will aim to use a member of our supplier network to repair or rebuild the damage to the building. Sometimes, this is not always possible e.g. if there is pre- existing damage. This will determine how the building claim will be settled. ... When a me mber of our supplier network is unable to complete the repair or rebuild and you have a building sum insured When your claim for loss or damage to the building is covered and a member of our supplier network is unable to complete the repair or rebuild, we will ask you to engage a builder to provide a scope of works and provide a quote on the cost to repair or rebuild the bui lding on a „new for old‟ basis. Once the scope of works and quote is provided to us, we will arrange for it to be assessed. This will involve reviewing the quote to determine it is appropriate and reasonable for the scope of works. This includes a consideration of the appropriateness of materials, repair method, labour and material costs and overall cost effectiveness. If the quote is appropriate and reasonable for the scope of works, we will then pay you the assessed amount. If it is not, the quote may be adjusted. This may include, adjusting the scope of works or the quote. We will then pay you the adjusted amount of the quote. If we pay you for the repair or rebuild, the Lifetime guarantee on building repairs does not apply, ... ... Things we don’t cover Loss or damage to, or caused by, connected with or arising from, or liability caused by, connected with or arising from: Ground movement erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover landslide or subsidence that is specifically covered under the following insured events: ... Wear, tear and gradual deterioration Determination | Case number: 730453 Page 8 of 8 any part of the building that has wear, tear, rust, fading, rising damp, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration such as, but not limited to: • tiles and their adhesive or grouting breaking down; • weathering of roof tiles or roof ridge capping; • gradual weathering and breakdown of bricks, mortar or concrete.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.