Adequacy of cash settlement for flood damage, temporary accommodation, roof payment delay and claim handling
Text of the determination
Determination
Case number 891584
Financial firm Insurance Australia Limited
Determination | Case number: 891584 Page 1 of 8
Case number: 891584 20 January 2023
1 Determination overview
1.1 Complaint
On 27 February 2022, the complainant lodged a claim on his home and contents insurance
policy following a flood event. The financial firm (the insurer) accepted the claim, but the
adequacy of some of its settlement proposals is in dispute.
The complainant says the insurer’s offer s to cash settle the cost of building repairs and carpet
replacement are inadequate. Further, he says he will need temporary accommodation (TA)
during repairs and that the insurer has unreasonably delayed paying an agreed amount for
roof damage. He also seeks compensation for stress caused by the insurer’s claim handling.
1.2 Issues and key findings
Are th e insurer’s cash settlement offer reasonable?
Yes. On balance, the complainant has not established the quotes relied on by the insurer are
inadequate. The insurer’s proposed 20% contingencies uplift on its building quote is
reasonable. Given the insurer’s carpet quote is older, a 30% uplift is to apply to it.
Is the insurer required to pay for TA?
Yes. The complainant’s submission that his family will need TA during the demolition phase of
the required works is reasonable. The insurer is to pay the complainant one week of TA
costs.
Has the insurer unreasonably delayed paying the roof claim settlement?
Yes. On 12 July 2022, the parties agreed to resolve the roofing claim for $3,410. Allowing for
a reasonable processing period, that amount should have been paid by 1 August 2022.
Is non-financial loss compensation payable?
Yes. The i nsurer’s delays and other claim handling issues have contributed to the
complainant ’s stress and inconvenience. The insurer is to pay him $1,500 in compensation.
Why is the outcome fair?
While the insurer’s settlement offers are generally reasonable, it is fair that the insurer pays a
TA allowance as the insured property will be unliveable during demolition. It is also fair that
the insurer pays interest on the roof settlement figure and compensation for stress it caused.
1.3 Determination
This determination is partially in favour of the insurer.
Within 21 days of the complainant accepting this determination the insurer is to pay him:
$101,993.05 for the building damage (UB’s quote plus 20%)
$4,330.26 for carpet replacement (FX’s quote plus 30 %)
Determination | Case number: 891584 Page 2 of 8
one week of TA costs based on averaging the rent payable for three suitable rental
properties currently available within two kilometres from the insured property
$3,410 for the roof repairs, plus interest pursuant to section 57 of the Insurance Contracts
Act, 1984 (Cth) from 1 August 2022 to the date payment is made
$1,500 in non-financial loss compensation.
Determination | Case number: 891584 Page 3 of 8
2 Reasons for determination
2.1 Are the insurer’s cash settlement offers reasonable ?
Yes. On balance, the complainant has not established the quotes relied on by the insurer are
inadequate . The insurer’s proposed 20% contingencies uplift on its building quote is
reasonable. Given the insurer’s carpet quote is older, a 30% uplift is to apply to it.
It is reasonable for the claim to be cash settled
Initially, the complainant ’s preference was that the insu rer’s builder (UB) attend to claim
related repairs. However, due to dissatisfaction with the conduct of the insurer and UB, the
complainant subsequently stated he wanted the claim to be cash settled.
For its part, the insurer is willing to pay the complainant a cash settlement amount or arrange
for UB to undertake the repairs.
Given that both parties are willing to cash settle and allowing for their deteriorating
relationship, I am satisfied it is reasonable that the claim be cash settled.
A cash settlement must be based on a quote that would be actionable by a retail customer
and must allow an uplift for contingencies and the loss of warranty applying to insurer
authorised repairs.
Insurer has made cash settlement offers
On 11 March 2022, UB inspected the insured property. It confirmed that the lower level of the
property had sustained damage due to flood and that the sunroom had been damaged in the
associated storm.
UB’s report was accompanied by its scope of works (SOW) and quote totalling $69,634.36.
On 6 June 2022, UB updated/varied its SOW and quote, resulting in estimated building repair
costs of $82,834.36.
In its IDR letter dated 6 July 2022 to the complainant, the insurer advised that its technical
assessor considered the UB quote to be fair and reasonable. The insurer also noted that the
quote was actionable by the complainant as UB was prepared to undertake the quoted works.
As the complainant had asked for a cash settlement, the insurer offered to pay $82,834.36.
In its EDR response to AFCA dated 29 August 2022, the insurer increased its cash settlement
offer by applying a 20% contingency uplift. While the final figure stated in the EDR response
was incorrect, the insurer corrected the mistake in an email dated 6 September 2022. The
amount offered was $99,401.23.
In a further response to AFCA dated 22 September 2022, the insurer confirme d that UB’s
SOW/quote did not include carpet replacement because UB is a builder. The insurer provided
a carpet replacement quote dated 28 March 2022 from FX, flooring supplier, totalling
$3,330.97. It is apparent the insurer was willing to pay the complainant that amount.
On 11 October 2022, the insurer submitted a further EDR response. The insurer advised that
it had requested FX and UB to provide updated SOWs/quotes. FX was yet to respond. UB
had provided an updated/varied SOW and quote dated 11 October 2022, in which it:
stated there had been no price increases for materials and labour since it provided its last
SOW/quote
Determination | Case number: 891584 Page 4 of 8
included an allowance for a hygienist to assess the property and provide a clearance
certificate
estimated repair costs at $84,994.21
confirmed the SOW/quote was actionable, noting it was prepared to undertake the works.
Allowing a 20% contingency uplift on UB’s updated quote amoun t, the insurer offered to cash
settle the building damage claim for $101,993.05.
Complainant says the offers are inadequate
The complainant maintains that the insurer’s cash settlement offers are manifestly
inadequate.
In relation to carpet replacement, on 12 July 2022, the complainant provided a quote dated 10
June 2022 from his local FX store, totalling $8,714. The complainant emphasised that the
carpeting component amounted to $3,460 (the remaining work related to the installation of
hybrid flooring in other rooms).
In his subsequent submissions to AFCA, the complainant has not referred to the FX quote
dated 10 June 2022. However, in his submission dated 1 October 2022, the complainant said
the FX quote dated 28 March 2022 relied on by the insurer was ‘now more than 6 months out
of date’.
The complainant considers that UB’s SOWs and quotes have all been ‘materially deficient
and factually incorrect’. He says the latest iteration uses out of date pricings, fails to allow for
temporary relocation of a piano within the home and does not allow for additional restoration
and hygiene costs.
In relation to the piano relocation, the complainant refers to a quote dated 14 June 2022
totalling $2,400 from BP, piano removalist.
For the building repair work, the complainant has provided the following quotes:
quote dated 14 June 2022 from BD, totalling $132,591.81
quote dated 8 September 2022 from RV, totalling $154,183.55
quote dated 12 September 2022 from EB, totalling $145,804.93
quote dated 12 September 2022 from CB, totalling $139,581.
The complainant submits that these quotes more accurately represent the true cost of
claimed related building repairs. He has indicated he would be willing to base a cash
settlement for the building damage claim on CB’s quote.
Insurer’s cash settlement offers are reasonable
To be entitled to a higher cash settlement amount, the complainant must demonstrate that the
insurer’s offer s do not reasonably reflect the likely retail costs of repairs. This requires the
complainant to show one or more of the following:
the SOWs the insurer relies on do not adequately encompass the required repairs
the quotes the insurer relies on are under priced
the insurer has failed to include a reasonable contingencies uplift.
In relation to the building repairs, the complainant considers that UB has not (or not
sufficiently) allowed for some work items. He particularly identifies piano relocation and
restoration/hygiene.
However, UB’s SOW/quote dated 11 October 2022 includes:
Determination | Case number: 891584 Page 5 of 8
as part of the initial SOW - ‘Allowance for piano to be contained for the duration of the
repairs’ by furniture removalists for $1,600 plus GST
variation two (15 June 2022) – restoration work by a restorer for $10,214.17 plus GST
variation three (11 October 2022) – sampling and clearance certification by hygienists for
$1,650 plus GST.
Given that the work concerning the piano is to be undertaken by furniture removalists, I
consider it more likely than not that it will involve relocation within the insured property.
The complainant’s preferred builder, CB, has also suggested that it will be necessary to
replace the bathroom vanities at a total cost of $24,196 (rather than removing and reusing the
existing units). The complainant says he understands that CB has allowed for the vanities to
be removed and replaced due to mould spores growing underneath and behind the units.
However, there is nothing to confirm the complainant has corre ctly understood CB’s
reasoning, that the mould is present or that any such mould would preclude remediation and
reuse of the existing units.
On 11 October 2022, UB confirmed that its pricing remained current and that it was prepared
to undertake the work in accordance with its latest SOW/quote. Accordingly, I am not satisfied
it has been established that UB’ s quote is under priced. That other builders have quoted
amounts higher than UB does not of itself establish that U B’s quote has failed to reasonably
price the cost of the works.
The complainant has submitted that the insurer’s proposed application of a 20% uplift ‘seems
arbitrary and misleading, and totally unrealistic’. The complainant has not provide d detailed
reasoning. In any event, I regard the proposed uplift to be within a reasonable range and fair
in the circumstances.
In relation to the cash settlement for carpet replacement, the complainant’s quote is slightly
more recent than the insurer’s quote and has been provided by the local FX store. However,
the two quotes are not ‘like for like’. Notably, the quote the complainant relies on includes
amounts for hybrid flooring (which UB has allowed for in its quotes). Further, the rooms
identified for carpeting in the two quotes do not match.
In the circumstances, I am not satisfied that the complainant has established it is more likely
than not that the insurer’s quote does not cover the required claim related repairs or is under
priced.
However, as neither quote is particularly detailed and the quote the insurer relies on is now
approximately ten months old, it is reasonable to apply a higher contingency uplift of 30%.
2.2 Is the insurer required to pay for TA?
Yes. The complainant’s submission that his family will need TA during the demolition phase of
the required works is reasonable. The insurer is to pay the complainant one week of TA
costs.
Policy provides TA cover in certain circumstances
The policy includes as an additional TA benefit where an insured event causes damage,
rendering the insured property unliveable pending repair. The insurer will pay the cost of TA it
agrees is reasonable and appropriate for an insured, their family and their pets.
Determination | Case number: 891584 Page 6 of 8
The insurer is to pay such costs for the reasonable time it agrees it should take to repair the
property (to a point where it would be liveable), subject to a 12 month cap.
Insurer is required to pay the complainant the cost of one week of TA
The parties disagree on various matters concerning an early offer to pay for TA made by the
insurer. In any event, the complainant and his family were (with difficulty) able to continue to
reside at the insured property by only occupying the upper level.
Accordingly, it is arguable that the property was not rendered unliveable by the flood event.
Regardless, the complainant has not incurred any TA costs.
However, he says that his family will need TA during the demolition phase of the required
works. The complainant has suggested that phase will take three to five days. This appears to
be based on time estimates provided in the SOWs from his four quoting builders.
I am satisfied that it is more likely than not that the insured property will be unliveable during
the demolition phase. As the insurer is to cash settle the cost of building repairs, it should do
so in relation to TA costs as well. In doing so, an uplift is to be applied. I consider it sensible
to allow for an uplift by rounding up the TA period to seven days.
Accordingly, the insurer is to pay the complainant one week of TA costs, based on averaging
the rent payable for three suitable rental properties currently available within two kilometres
from the insured property.
2.3 Has the insurer unreasonably delayed paying the roof claim
settlement?
Yes. On 12 July 2022, the parties agreed to resolve the roofing claim for $3,410. Allowing for
a reasonable processing period, that amount should have been paid by 1 August 2022.
Insurer has unreasonably delayed paying the roof claim settlement amount
On 6 July 2022, the insurer offered to pay the complainant a $3,410 cash settlement for the
cost of claim related roof repairs. The offer was based on a quote the complainant had
submitted.
On 12 July 2022, the complainant accepted the insurer’s offer.
On 6 September 2022, the insurer advised for the first time that it intended to pay the $3,410
only upon resolution of all aspects of the dispute with the complainant. This was not stipulated
as a condition when it made its roof claim settlement offer.
The insurer is yet to pay the agreed roof claim settlement figure. It has sought to unilaterally
impose a condition as to when it is to pay that figure, well after the complainant accepted the
settlement offer. In doing so, and in failing to pay the settlement amount for over six months,
the insurer has acted unreasonably.
Under the AFCA Rules, AFCA may require an insurer to pay interest from the date from
which it was unreasonable for an insurer to have withheld payment of an amount it was liable
to pay. Allow ing a reasonable processing period after the complainant’s acceptance of the
insurer’s roof claim settlement offer, that amount should have been paid by 1 August 2022.
Determination | Case number: 891584 Page 7 of 8
Accordingly, the insurer is to pay the complainant $3,410 for the roof repairs, plus interest
pursuant to section 57 of the Insurance Contracts Act, 1984 (Cth) from 1 August 2022 to the
date payment is made.
2.4 Is non-financial loss compensation payable?
Yes. The insurer’s delays and other claim handling issues have contributed to the
complaina nt’s stress and inconvenience. The insurer is to pay him $1,500 in compensation.
AFCA can award compensation for poor claim handling
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400) where the insur er’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
Insurer’s claim handling has caused the complainant stress and inconvenience
The complainant says that the insurer has caused his entire family enormous stress and
inconvenience. He says that it has unnecessarily delayed progression and finalisation of the
claim, has failed to adequately communicate and has acted in an unprofessional manner.
The complainant considers that the insurer has failed to act in accordance with the General
Insurance Code of Practice (the Code).
The insurer has acknowledged that ‘delays beyond expected occurred’ , for which it has
apologised. However, it says that the delays were largely due to the challenges presented to
insurers and their service providers by recent significant natural disasters.
I acknowledge that insurers have been placed under considerable strain due to natural
disasters, including the subject flood event. However, having reviewed the insurer’s claim
notes, there have been occasions when the insurer could have acted more promptly.
I also consider that some of the insurer’s communications were unclear or contradictory.
These issues have contributed to the stress and inconvenience experienced by the
complainant, who was already having to deal with the consequences of a major flood.
I am not satisfied that the insurer’s apology to the complainant is a suffic ient response to his
concerns. In the circumstances, it is reasonable that the insurer pays the complainant $1,500
in non-financial loss compensation.
2.5 Why is the outcome fair?
While the insurer’s settlement offers are generally reasonable, it is fair that the insurer pays a
TA allowance as the insured property will be unliveable during demolition. It is also fair that
the insurer pays interest on the roof settlement figure and compensation for stress it caused.
Determination | Case number: 891584 Page 8 of 8
3 Supporting information
3.1 The AFCA process
AFCA ’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.