Home / Hollard / Determination 891389

Determination 891389

Denial of storm damage claim for Cyclone Debbie; delay in responding to engineer's report

FirmHollard
Decided2023-06-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,000
Amount claimed$103,667
SourceAFCA PDF

Summary

Complainants claimed $103,666.89 for cyclone damage to their home; the insurer denied the claim. AFCA upheld the denial but ordered $1,000 for non-financial loss due to the insurer's delay responding to the engineer's report.

No storm-created opening or storm damage was shown, so the policy exclusion applied, but the insurer exceeded the 30-day Code timeframe in reviewing the engineer's report.

Issues

Subjects and remedies

home or building damagenatural disasterpay non financial loss

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 891389 Financial firm Hollard Insurance Partners Limited Determination | Case number: 891389 Page 2 of 8 Case number: 891389 20 June 2023 1 Determination overview 1.1 Complaint The complainants hold a home insurance policy with the financial firm (the insurer). They lodged a claim for damage they say was caused by Cyclone Debbie. The insurer said the cyclone damaged a fence, which could be replaced for less than the excess. It said the cyclone did not cause any other damage to the property. It denied the claim. The complainants say the cyclone caused extensive damage to the property. They have provided a repair quote totalling $103,666.89. 1.2 Issues and key findings Is the damage covered under the policy? No. The insured property (excluding the fence) was not damaged by Cyclone Debbie, or any other storm. The claimed damage was caused by rain entering the building through openings that were not created by a storm. The policy excludes cover for damage that occurs this way. Are the complainants entitled to compensation? Yes. The insurer took an unreasonably long time to respond to this complaint. It caused a delay of about three months. This warrants compensation for non-financial loss in the sum of $1,000. 1.3 Determination This determination is mostly in favour of the insurer. The insurer is entitled to deny the claim. The insurer must pay the complainants $1,000 compensation for non-financial loss. Determination | Case number: 891389 Page 3 of 8 2 Reasons for determination 2.1 Is the damage covered under the policy? No. The claimed damage was caused by rain entering the building through openings that were not created by a storm. The policy excludes cover for damage that occurs this way. Policy covers storm damage The cover provided by the policy is set out in the certificate of insurance and the product disclosure statement. Relevant policy terms are quoted in section 3.2 of this determination. The policy covers damage caused by:  storm  an accident. The policy excludes cover for damage caused by:  storm water entering the building through an opening not created by the storm  faulty workmanship or design  wear and tear and lack of maintenance. The policy covers storm damage, but excludes cover for wear and tear. Wear and tear is the deterioration of an object caused by its ordinary use, and the ordinary effects of natural forces such as weather. Therefore, the policy covers damage caused by a single storm, but does not cover damage that occurs gradually every time it rains. Complainants lodged claim for storm damage In March 2017, Cyclone Debbie made landfall near the insured property. The complainants called their property manager, who told them the cyclone had not damaged the property. In 2018, the complainants say they got a new property manager, who identified damage the complainants were unaware of, and said the damage was caused by the cyclone. On 10 August 2018, the complainants lodged a claim saying the property had been damaged by the cyclone. Experts said there was no storm-created opening The insurer appointed a builder, who inspected the property on 11 September 2018. The builder said there was water damage inside the property, but there was no storm-created opening. The builder concluded water had entered the property due to inadequate roof flashings and weathered roof sheets. The builder said a fence on the property appeared to have been damaged by strong winds, but did not identify any other storm damage. The cost of replacing the fence ($4,400, according to the complainants’ quote) would be less than the excess ($5,000). The complainants appointed an engineer, who inspected the property on 12 November 2021. The engineer said:  they inspected the roof sheeting and roof battens, but found no signs of movement  there was water damage inside the building, but no storm-created opening above the damaged areas  the damage appeared to have occurred because ‘ the original ridge flashing allowed water ingress into the roof space which ran down the inside of the walls and ceiling’ . Determination | Case number: 891389 Page 4 of 8 The complainants’ engineer said water h ad entered the building due to ‘ high wind forces and driving rain ’. They did not say whether this had occurred during a single storm, or during many storms over a long period of time. They did not attribute any damage to Cyclone Debbie, or any other specific storm. Insurer entitled to deny claim The available information does not show the insured property (excluding the fence) was damaged by Cyclone Debbie, or any other storm. The available information indicates the claimed damage was caused by rain entering the building through openings that was not created by a storm. The policy excludes cover for damage that occurs this way. Therefore, the insurer is entitled to deny the claim. 2.2 Are the complainants entitled to compensation? Yes. The insurer took too long to respond to the complainants’ engineer’s report. This warrants compensation for non-financial loss in the sum of $1,000. AFCA can award compensation for non-financial loss Under the AFCA Rules, we can award up to $5,400 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim. We will only award this type of compensation if there has been an unusual degree of stress, inconvenience, or delay. We will not award compensation for the usual amount of inconvenience involved in making a claim. We will not award compensation for delays caused by a complainant, or other factors outside the insurer’s control. Complaint has taken years to resolve On 10 August 2018, the complainants lodged the claim. On 11 September 2018, the insurer’s builder inspected the property. On 14 December 2018, based on the builder’s report, the insurer denied the claim. On 26 February 2019, the complainants told the insurer they would obtain their own expert reports and provide them to the insurer. On 4 March 2019, the insurer wrote to the complainants saying they could provide their own expert report for the insurer’s consideration. On 18 November 2019, the complainants asked the insurer why the claim had been denied when other people on the same street had insurance claims accepted. On 22 January 2020, the complainants told the insurer they wanted the claim reopened. On 20 April 2020, the complainants told the insurer they were considering appointing an engineer. The insurer said the complainants were welcome to provide a report for the insurer to consider, and the claim would remain closed in the meantime. On 7 March 2022, the complainants provided the insurer with a copy of their engineer’s report. The complainants said they were very upset with the delay. Determination | Case number: 891389 Page 5 of 8 On 7 April 2022, the insurer said it had completed its review of the new information (the complainants’ engineer’s report), and would contact the complainants to discuss the outcome of its review. On 28 June 2022, the complainants lodged this AFCA complaint. The insurer told AFCA it was ‘still reviewing the customer's report’ and had not made a decision. On 25 July 2022, the insurer emailed the complainants saying it maintained its decision to deny the claim. Insurer acted reasonably before receiving engineer’s report The General Insurance Code of Practice (to which the insurer subscribes) sets out how insurers will respond to complaints. The Code says that when an insurer receives a customer’s complaint, it will:  acknowledge the complaint  update the customer about the complaint at least every 10 business days  make a decision about the complaint (or explain why it cannot make a decision) within 30 days. The Code defines ‘complaint’ as ‘ an expression of dissatisfaction … where a response or resolution is explicitly or implicitly expected …’ The complainants expressed dissatisfaction in 2019 and 2020. The insurer made a decision about these complaints: it said the claim would remain closed while it waited for the complainants’ expert report. This was a reasonable decision. The complainants said they were going to provide an expert report, so it was reasonable for the insurer to wait to receive the report before reviewing its decision. In March 2022, when the complainants provided their expert report, they said they were very upset with the delay. However, the delay to that point was caused by the complainants’ delay in providing their expert report. Insurer took too long to respond to enginee r’s report The complainants provided their engineer’s report on 7 March 2022. The insurer should have reviewed the report and decided how to respond to it within 30 days (i.e. by 6 April 2022). However, it did not make a decision until 25 July 2022. The co mplainants’ engineer’s report was not especially complex. It should not have taken long to review. The insurer said it was experiencing ‘unprecedented delays’ due to floods in Queensland and New South Wales. It did not give any other explanation for why it was taking so long to make a decision. The insurer took too long to respond to the complainants’ engineer’s report. This caused frustration and annoyance for the complainants for about three months. The panel believes this warrants compensation for non-financial loss in the sum of $1,000. Determination | Case number: 891389 Page 6 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with extensive experience in consumer and small business advocacy  a member with extensive experience in insurance. Complainants represented by consumer advocate The complainants were represented by a consumer advocate. In this determination, statements by the complainants’ representative are treated as if they were made by the complainants. 3.2 Relevant policy terms Certificate of Insurance Your Building Cover (page 4 ) Insured Events and Optional Cover Am I Covered? Insured Events … Storm … … Yes … Optional Cover Accidental damage Yes Determination | Case number: 891389 Page 7 of 8 Product Disclosure Statement Glossary (pages 5 – 6 ) The words and phrases appearing in bold and italic print throughout this PDS have special meanings as set out in the g lossary below: … … Storm  A violent wind including a tornado or named cyclone; or  rain, hail or snow of unusual volume, force or duration. It is not persistent bad weather or heavy or persistent rain by itself. … … Insured Events (pages 36 – 54) We will provide cover for the following Insured Events if they occur during the Period of Insurance … Storm What is covered Your building and/or contents are covered for loss or damage caused by storm . What is not covered Your building and/or contents are not covered under this Insured Event for: …  loss or damage caus ed by wind, rain, hail or snow which ent ered an ordinarily fully enclosed p art of your building through an opening not created by the storm . This includes but is not limited to: ‒ an open window or door; and ‒ any opening made for the purpose of any renovation, repair or maintenance work, including where tarpaulins or other fixings h ave been set up. … Optional Covers (pages 68 – 74) Accidental damage What is covered You are covered for loss or damage to your building and/or contents caused by an accident at your insured address . What is not covered … If the cause of the loss or damage falls under an Insured Event in the policy, the loss or damage will be assessed under that Insured Event. … Determination | Case number: 891389 Page 8 of 8 General Exclusions (pages 75 – 78) Under this policy there is no cover provided for any loss, damage or liability caused directly or indirectly by or in any way connected with: 1. d efects, structural or design faults, faulty workmanship or faulty design; … 4. w ear and tear and lack of maint enance, including ru st, corrosion and deterioration… … We will also not cover … 35. g radual loss or damage of any kind; …

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.