Home / Allianz Australia / Determination 891331
Determination 891331
Dispute over how defective shed repairs are rectified (insurer's contractor or cash settlement) and claim handling
Summary
After a hailstorm claim, the insurer's builders' shed repairs were defective and the complainant refused to let the insurer's contractors return. AFCA required the insurer to let him choose between MK rectifying under warranty or a $38,030.50 cash settlement, plus $1,000 non-financial loss.
The insurer must act reasonably and in utmost good faith (s13 Insurance Contracts Act) when electing to repair or cash settle, so given the complainant's justified concerns he should have a choice of settlement.
Issues
- Repairs or contractors primary · upheld
“Parties agree NI's repairs require rectification; complainant raised serious concerns about MK and NI; insurer's insistence on MK was unreasonable.”
- Poor claim handling secondary · upheld
“Insurer's continuing insistence MK attend to repairs despite the complainant's concerns unreasonably caused stress and inconvenience.”
- Delay secondary · upheld
“Failure to view complainant's preferences empathetically led to avoidable delay and stress and inconvenience.”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial lossrepair or rectify
Text of the determination
Determination
Case number 891331
Financial firm Allianz Australia General Insurance Limited
Determination | Case number: 891331 Page 1 of 6
Case number: 891331 4 May 2023
1 Determination overview
1.1 Complaint
The complainant holds home and contents insurance with the financial firm (insurer). He
lodged a claim after a hailstorm on 31 October 2020 damaged his home and a large shed.
The insurer had the damage assessed by builder MK. It accepted the claim and repairs were
competed by its builder, NI. The complainant was dissatisfied with the shed repairs. MK has
agreed that rectification work is required. The insurer proposes that MK attend to that work.
The complainant does not want MK or NI to attend to the shed rectification work because he
has lost confidence in them. He wants the insurer to appoint a competent contractor to do the
work or pay him a cash settlement. He is also dissatisfied with the insurer’s claim handling .
1.2 Issues and key findings
Is the insure r’s position on rectification reasonable ?
No. The insurer must act reasonably in exercising its policy entitlement to elect whether to
attend to repairs or pay a cash settlement. The complainant has raised serious concerns
about MK and NI. It is therefore reasonable that the insurer gives him the choice between its
trades performing warrantable work or receiving a cash settlement with no warranty.
Is non-financial loss compensation payable?
Yes. The insurer’s continuing insistence MK attend to repairs despite the complainant’s
concerns unreasonably caused stress and inconvenience. It is to pay him $1,000.
Why is the outcome fair?
The policy is a contract based on the utmost good fait h, meaning the parties must act
reasonably towards each other. It is therefore fair that the complainant has the option to
choose how the rectification claim is to be settled on the proviso the insurer’s rights under the
policy are not compromised. It is fair the insurer pays compensation for stress it caused.
1.3 Determination
This determination is partially in favour of the complainant.
If the complainant accepts this determination, he is to choose one of the following options:
MK arranging the rectification work, meaning it is subject to a warranty under the policy
receiving a cash settlement of $38,030.50 (the combined total of the complain ant’s quotes
plus a contingencies uplift of 15%) on the proviso that no insurer warranty will apply in
relation to the shed.
The insurer is to action the complainant’s choice within 21 days of being notified of it.
The insurer is also to pay the complainant $1,000 in non-financial loss compensation within
14 days of the complainant accepting this determination.
Determination | Case number: 891331 Page 2 of 6
2 Reasons for determination
2.1 Is the insurer’s position on rectification reasonable?
No. The insurer must act reasonably in exercising its policy entitlement to elect whether to
attend to repairs or pay a cash settlement. The complainant has raised serious concerns
about MK and NI. It is therefore reasonable that the insurer gives him the choice between its
trades performing warrantable work or receiving a cash settlement with no warranty.
Policy allows the insurer to choose whether to repair or cash settle
The complainant and KB hold home building and contents insurance issued by the insurer.
Subject to the terms and conditions set out in the product disclosure statement (PDS), their
policy covers damage caused by a listed insured event. On e of the listed events is ‘Storm’ .
Page 50 of the PDS sets out how the insurer will settle a claim. The insurer may choose to
attend to repairs or pay an insured (cash settle) the reasonable cost of repairs.
The PDS also confirms that if the insurer attends to repairs, a guarantee will apply as follows:
We will guarantee the repairs to your building and contents when we provide or
recommend a repairer for you. However we won’t guarantee any repairs if you
choose your own repairer.
In exercising its right to choose whether to attend to repairs or pay a cash settlement, an
insurer is required to act reasonably.
Parties agree that insurer’s repairs require rectification
The complainant lodged a claim after a hailstorm on 31 October 2020 damaged his home and
a large Colorbond shed. Following assessment by MK, the insurer accepted the claim and,
through MK, arranged for NI to undertake the required repairs.
NI completed its repairs in December 2021. In relation to the shed, the repairs involved
replacing the entire roof and all wall cladding as well as the perimeter guttering.
The insurer says that in February 2022, the complainant contacted it expressing concerns
about the quality of NI’s work. The complainant wanted the insurer to appoint a competent
contractor to attend to rectification or pay him a cash settlement. A dispute then developed as
to whether it was appropriate for MK to reinspect the property.
The complainant obtained a report dated 29 July 2022, from KA, the builders that had
constructed the shed in late 2020. KA identified the following issues with NI’s repairs:
sheeting screws overtightened (causing warping in sheets)
ridge capping not screwed off correctly (causing warping in sheets)
roughly competed flashings around roller door and window (enabling water ingress)
roof and wall top hat purlins need to be replaced (too many screw holes from previous
attempts, some screws completely miss purlin)
eve purlins need replacing (screw holes from previous attempts, allow water ingress)
ridge line not screwed off on every second rib. KA said this was an engineering
requirement, without which the structure would not be up to Code.
Determination | Case number: 891331 Page 3 of 6
KA recommended removal and replacement of all sheeting, flashings, top hat purlins, eve
purlins, ridge capping, gutters and whirlybirds. It provided a quote dated 24 July 2022,
estimating the cost of the recommended works at $24,596.
On 8 August 2022, the complainant obtained a quote from FE, electricians, totalling $8,474,
for the following work:
decommission and remove electrical power in the shed for safe work purposes
reinstate electrical power on completion
remove and reinstall air conditioning
remove and dispose of old sarking, supply and install new sarking
remove and reinstall rainwater tank.
After the complainant lodged his AFCA complaint, he agreed to MK re-inspecting the shed.
On 18 August 2022, the insurer requested MK do so. However, further issues with access to
the insured property occurred so the inspection did not place until 20 October 2022.
MK reported on 24 October 2022 that:
the complainant had identified loose foil sarking paper inside the shed, but this had been
an issue since construction as shown by the complainant’s photos
nevertheless, in good faith, it had informed the complainant it would install custom metal
flashings to the top batten with adhesive to strengthen the sarking paper on both sides of
the shed. NI had made the flashings but they were yet to be installed
the complainant said afternoon sunshine on the shed’s south -eastern elevation revealed
ripples in the cladding. MK could not identify the ripples and said it did not consider the
cladding defective. However, it offered to carry out alterations to improve aesthetics
‘ We believe the items listed by the Insured are acceptable for warranty repairs. However, if
the Insured does not want to allow access for the repairs to be carried out, we are unable
to complete the repairs ’ .
In the circumstances, the insurer has accepted that rectification work is required.
Parties disagree on whether insurer should attend to rectification work
The insurer does not dispute rectification work is required and says that it has made attempts
to have the work completed by MK. It says it has ‘the right to rectify any repair quality or
warranty concerns for repairs completed under a claim’ but has been unable to exercise its
right due to the co mplainant’s refusal to permit access.
According to the insurer, it remains ready and able to have MK arrange for the rectification
work to be completed. It notes that any such work would then be subject to the repair
guarantee set out in the PDS.
The complainant says that in September 2021, he informed MK that NI had left holes in the
purlins, loose and sagging sarking, and dented wall sheets. On 28 October 2021, NI returned
but only closed most of the holes in the purlins.
The complainant says he followed up about the remaining repair issues numerous times, but
it was not until 22 January 2022 that he was told NI would contact him again. NI did not do so
until 8 March 2022. NI informed him it had been told to return to ‘back off’ a couple of screws
that were slightly over screwed and install flashings to stop the sarking paper falling.
The complainant regarded the proposed works inadequate. He says he tried to contact MK
but was unable to do so. Additionally, after NI suggested in mid March 2002 a site meeting
involving MK, he did not hear anything further.
Determination | Case number: 891331 Page 4 of 6
The complainant submits that:
Due to all the drama and lack of interest on their part to rectify the issues, I have
no trust that [MK] will fix the shed under warranty to my satisfaction. I have not
once been given a detailed scope of works on the rectification and assurance that
the recommendations outlined by KA will definitely be followed…
Therefore I do not believe it is fair that we have to accept [the insurer’s] appoi nted
contractor as they have not been able to fix our shed to be compliant and I do not
believe that they will honour any warranty they issue after completion.
It is reasonable that complainant has a choice of settlement options
The policy entitles the insurer to choose whether to attend to repairs or pay a cash
settlement. I am satisfied that choice applies to rectification work under the repair guarantee,
as well as claim related damage.
Pursuant to section 13 of the Insurance Contracts Act,1984 (Cth), each party owes a duty of
utmost good faith to the other in respect of any matter arising under or in relation to the policy.
This means they must each act reasonably in dealing with the required rectification work.
The complainant has provided screenshots of text messages that support his summary of the
interactions with MK and NI from late September 2021 to mid March 2022. He has also
provided photos of the issues with the repairs NI performed. KA says the defects are so
serious that a substantial amount of NI’s work will need to be removed and replaced.
MK says the loose sarking paper was pre-existing (strongly denied by the complainant, noting
all photos he provided were taken post claim event) and that it could not identify ripples in the
wall cladding. However, it has offered to rectify these matters and believes ‘ the items listed by
the Insured are acceptable for warranty repairs ’ .
It is important to note that the insurer and, presumably, MK had KA’s report and quote and
FE’s quote before MK was enga ged to reinspect the property. Further, the insurer has not
provided any scope of works or quotes of its own.
I am satisfied that while the insurer does have a choice to repair or cash settle, the
complainant has justifiably raised serious concerns about MK and NI. The insurer saying it is
ready and able to have MK arrange for the rectification work to be completed does not
adequately address those concerns.
In the circumstances, balancing the rights and obligations of both parties under the policy and
taking into account the duty of utmost good faith each owes to the other, it is reasonable that
the complainant be allowed to choose one of the following two methods to settle the dispute:
MK arranging the rectification work as listed by KA and FE in their respective quotes,
meaning that work will be subject to the repair guarantee set out in the PDS
receiving a cash settlement of $38,030.50 (the total of the quotes of KA and FE plus a 15%
contingencies uplift, given the quotes are eight months old and KA’s included an ‘at cost’
item) on the proviso that no insurer warranty will apply in relation to the shed repairs after
the cash settlement is paid.
Determination | Case number: 891331 Page 5 of 6
2.2 Is non-financial loss compensation payable?
Yes. The insurer’s continuing insistence MK attend to repairs despite the complainant’s
concerns unreasonably caused stress and inconvenience. It is to pay him $1,000.
AFCA can award compensation for poor claim handling
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(c apped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
Insurer unreasonably caused stress and inconvenience
The complainant says that the insurer has unreasonably delayed resolving the dispute about
how rectification of NI’s unsatisfactory workmanship was to proceed. He says this delay has
caused tremendous stress and frustration.
Based on the information provided, it appears that both parties contributed to the delays
experienced. However, once MK confirmed in late October 2022 that NI’s repairs required
significant rectification, the insurer should have viewed the complainant’s preferences mor e
empathetically.
I am satisfied that the insurer’s failure to do so was unreasonable, leading to avoidable delay
and stress and inconvenience. The insurer is to pay the complainant $1,000 in non-financial
loss compensation.
2.3 Why is the outcome fair?
The policy is a contract based on the utmost good faith, meaning the parties must act
reasonably towards each other. It is therefore fair that the complainant has the option to
choose how the rectification claim is to be settled on the proviso the insurer’s ri ghts under the
policy are not compromised. It is fair the insurer pays compensation for stress it caused.
Determination | Case number: 891331 Page 6 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.