Home / Suncorp Group / Determination 891139
Determination 891139
Cash settlement amount for storm water damage building claim and claim handling delays
Summary
The complainant disputed the insurer's cash settlement offer for storm damage to his home and its claim handling. AFCA found the complainant's builder's quote better reflected repair costs, applied a 15% uplift, and ordered a further $14,070.55 plus $1,500 non-financial loss.
A cash settlement should be based on the quote most likely to reflect actual retail repair costs plus a reasonable contingency uplift, and the insurer's delay and poor communication caused unreasonable stress.
Issues
- Claim amount dispute primary · upheld
“SN's quote is more likely to accurately reflect the cost of repairs than MC's estimate; 15% uplift appropriate; insurer to pay further $14,070.55.”
- Delay secondary · upheld
“The insurer took seven months to make a claim decision on the building claim. Even allowing for weather events, that is too long.”
- Poor communication secondary · upheld
“I also agree with the complainant that the insurer should have better communicated with him.”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial loss
Text of the determination
Determination
Case number 891139
Financial firm AAI Limited
Determination | Case number: 891139 Page 1 of 5
Case number: 891139 24 March 2023
1 Determination overview
1.1 Complaint
The complainant holds home and contents insurance with the financial firm (insurer). On 7
March 2022, he lodged a water damage claim following a storm event on 5 March 2022.
By early October 2022, the insurer had finalised its cash settlement of the contents claim and
had accepted that the storm event had caused damage to the complainant’s home. The
insurer had also notified the complainant there were maintenance issues he would need to
attend to before claim related repairs could be undertaken by its builder, MC.
The insurer then made offers to cash settle the building damage claim, culminating in
$76,187.78 being offered on 25 November 2022. That figure was based on a costing from the
MC plus a 20% contingencies uplift.
The complainant says the insurer ’s cash settlement offer is inadequate to cover the claim
related building repair costs. He wants the insurer to pay him the $78,485.50 his builder (SN)
quoted on 28 November 2022, plus a 20% uplift. The complainant is also dissatisfied with the
insurer’s cl aim handling, which he says has caused him stress and inconvenience.
Pending resolution of the dispute, in early February 2023, the insurer paid the complainant
the $76,187.78 it had offered.
1.2 Issues and key findings
Is the insurer required to pay any additional amount?
Yes. SN’s quote is more likely to accurately reflect the cost of repairs than MC’s estimate. A
reasonable contingencies uplift to be applied is 15% given SN’s qu ote was prepared relatively
recently. Allowing for its previous payment, the insurer is to pay a further $14,070.55.
Is the insurer to pay non-financial loss compensation?
Yes. The insurer has acknowledged there have been delays and service issues causing
undue frustration and inconvenience to the complainant. It is to pay $1,500 in compensation.
Why is the outcome fair?
It is fair that the insurer cash settles the building claim based on the quote that best reflects
the likely repair costs and pays a reasonable contingencies uplift. It is also fair that the insurer
pays the complainant non-financial loss compensation for the stress it unreasonably caused.
1.3 Determination
This determination is in favour of the complainant.
Within 14 days of the complainant accepting this determination, the insurer is to pay him:
$14,070.55, being the outstanding component of the cash settlement amount, and
$1,500.00 in non-financial loss compensation.
Determination | Case number: 891139 Page 2 of 5
2 Reasons for determination
2.1 Is the insurer required to pay any additional amount?
Yes. SN’s quote is more likely to accurately reflect the cost of repairs than MC’s estimate. A
reasonable contingencies uplift to be applied is 15% given SN’s quote was prepared relatively
recently. Allowing for its previous payment, the insurer is to pay a further $14,070.55.
Insurer relies on costing by MC
The insurer engaged MC to determine the repair costs relating to the building damage. In mid
October 2022, the insurer provided a spreadsheet on its letterhead, setting out MC’s final
scope of work (SOW) and a $54,144.82 repair costs estimate.
MC’s estimate did not include any allowance for replacement of the kitchen. However, the
insurer accepts that that may be necessary. Accordingly, it has allowed a further $9,345 for
the associated potential costs. That figure was provided by SN.
Noting the unrelated maintenance issues to be attended to, the insurer has offered to cash
settle the building claim for the combined amounts of the figures set out above ($63,489.82),
plus a 20% uplift ($12,697.96), being a total of $76,187.78.
The insurer submits that MC’s SOW ‘is consistent with the loss and has been costed in line
with their contracted rates’. It notes MC would be willin g to undertake the repairs, on the basis
that its repair warranty would not apply to ‘ events arising from water ingress from the property
exterior to the interior, irrespective of the level of improvements made by the Insured ’ .
In December 2022, the insurer said that any settlement would be subject to the complainant
signing a release including a notation relating to MC’s warranty limitation . However, it also
said it was:
committed to considering any variations if event related damages are found
during the repairs. The scope of works reflect the value of claim related repairs,
however; if during the repairs the Customer discovers additional event related
damages, they can submit a variation quote and report along with photos and
detailed reasons for the additional cost for review.
Complainant says SN’s quote is more realistic
The complainant engaged builder SN. He says that SN is ‘a long standing and very
experienced local builder with direct knowledge and experience in the drainage difficulties in
rocky substrates’ in his location.
On 28 November 2022, SN provided a detailed quote for work required to rectify claim related
damage. The quote amounts to $69,140.50. In addition, SN provided a fixed price of $9,345
to replace the kitchen. The total of these figures is $78,485.50.
The complainant says the insurer should cash settle the building claim based on SN’s quote
and still pay the 20% contingencies uplift. He submits that:
[SN’s] fixed price quotation, 28/11/22 is detailed and priced as far as possible
because of the increases in material costs and labour costs. The quotation details
unit prices for each room, including all elements of works, which is in accordance
Determination | Case number: 891139 Page 3 of 5
with the Master Builders Contract. This quotation was finalized on 28/11/22, 8
months after the [MC] estimate was finalised and includes price increases to that
date. During this period of time from the [MC] estimate material and labour costs
have risen 30%. The 20% contingency will cover further price increases and any
variations to the works until the finalisation of the contract. [SN] provides building
warranty and all insurance.
SN’s quote was stated as being valid for three months, that is, until 29 January 2023. The
complainant wanted SN to undertake the works and was anxious not to allow SN’s quote to
expire. Accordingly, the insurer has paid him the $76,187.78 on the basis the payment may
not represent his full entitlement.
Insurer is to pay an additional amount to the complainant
A cash settlement must be based on a quote that is actionable by a retail customer and must
allow an uplift for contingencies and the loss of the lifetime guarantee applying to insurer
authorised repairs.
I am satisfied that SN’s quote is more likely to accurately reflect the cost of repairs than MC’s
estimate. The reasons for my finding include:
SN’s quote is more recent than MC’s estimate (even allowing for the fact that the
complainant is mistaken in suggesting MC’s estimate wa s finalised in early April 2022)
SN’s quote provides more detail than MC’s estimate
SN provided a binding quote on its letterhead, valid for three months. MC’s estimate was
not a quotation, did not refer to a validity period and was not on its letterhead
MC’s estimate was based on rates it had agre ed with the insurer, which are typically
discounted when compared with retail rates
SN has in depth knowledge of local conditions while MC is based approximately 100km
from the complainant’s locati on.
The parties are proceeding by way of cash settlement and SN has been engaged by the
complainant to undertake the works. Therefore , MC’s indication it would be willing to provi de
a (limited) repair warranty is not relevant.
Further, a cash settlement is intended to provide finality. Accordingly, the insurer’s previous
indication it would be willing to consider potential SOW variations once repairs commence is
not relevant either.
The uplift to be applied to a cash settlement is to cover the loss of the lifetime guarantee that
would otherwise apply to insurer approved repairs and to allow for contingencies. The latter
relates to the possibility the quote does not reflect all repairs actually required and the chance
labour or material prices increase.
SN’s quote was prepared four months ago, on 28 November 2022, and was valid until 29
January 2023. The complainant accepted the quote before it expired. In the circumstances,
even allowing for the caveat on the quote that ‘prices are subject to change’, I cons ider it
more likely than not that the quote ’s pricing has remained accurate.
Therefore, I consider an uplift of 20% to be too high. Bearing in mind the other factors an
uplift is intended to allow for, I am satisfied that a 15% uplift is appropriate.
Accordingly, the cash settlement payable is $90,258.33. After deducting the insurer’s
previous payment of $76,187.78, the outstanding amount is $14,070.55.
Determination | Case number: 891139 Page 4 of 5
AFCA can award compensation for poor claim handling
Under paragraph D.3.3 of the AFCA Rules, we may award compensation for non-financial
loss (capped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
Insurer has unreasonably caused stress and inconvenience
The complainant is a pensioner. He says that the insurer unduly delayed progression of the
claim and that it inadequately communicated with him. He says these issues caused him
financial difficulty, stress and inconvenience.
The insurer accepts that delays were experienced, particularly during the first few months of
the claim given the volume of claims it received due to extreme weather events at the time. It
has acknowledged that the delays and other service issues have caused the complainant
undue frustration and inconvenience. It has apologised and offered $1,000 in compensation.
The insurer took seven months to make a claim decision on the building claim. Even allowing
for the challenges associated with the weather events in the first half of 2022, that is too long.
It is much longer than the standard four month period referred to in the General Insurance
Code of Practice.
I also agree with the complainant that the insurer should have better communicated with him.
It is clear that the insurer’s claim handling has unreasonably caused the complainant stress
and inconvenience beyond the norm. I am satisfied that it is reasonable to require the insurer
to pay $1,500 to the complainant in non-financial loss compensation.
2.2 Why is the outcome fair?
It is fair that the insurer cash settles the building claim based on the quote that best reflects
the likely repair costs and pays a reasonable contingencies uplift. It is also fair that the insurer
pays the complainant non-financial loss compensation for the stress it unreasonably caused.
Determination | Case number: 891139 Page 5 of 5
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.