Home / Suncorp Group / Determination 889815
Determination 889815
Insurer limited liability for storm damage, declining subfloor and pier damage as long-term and disputing scope and cost of repairs and make safe invoice
Summary
Complainant's storm damage claim was accepted by the insurer but it declined subfloor and pier damage as long-term. AFCA upheld that decline but required the scope of works be amended with missing items, a 15% contingency added, and the make safe invoice partly reimbursed with interest.
Expert evidence of packing, moss and efflorescence showed the subfloor damage was long-term rather than storm-caused, but the insurer's scope omitted some storm-related items and make safe costs.
Issues
- Claim denial primary · not upheld
“The insurer is not liable for the damage to the subfloor. This includes the piers.”
- Claim amount dispute secondary · upheld
“The insurer's assessment missed some items which should be included; scope of works should be amended and a 15% contingency added.”
- Inadequate claim investigation secondary · not upheld
“Complainant said insurer failed to consider his engineer's report; AFCA preferred the insurer's expert evidence (JHA) on causation.”
Subjects and remedies
home or building damagenatural disasterpay claimpay interest
Text of the determination
Determination
Case number 889815
Financial firm AAI Limited
Determination | Case number: 889815 Page 1 of 6
Case number: 889815 31 January 2023
1 Determination overview
1.1 Complaint
The complainant lodged a claim on 12 March 2022 under his home and contents insurance
policy with the financial firm (insurer). This was for damage to his property due to a storm
event said to have occurred on or about 8 March 2022.
The insurer accepted the claim. However, it has limited its liability to damage it accepts to be
consistent with the insured event. The complainant is dissatisfied with the insurer’s
assessment of its liability and seeks further cover under the claim.
1.2 Issues and key findings
Is the insurer’s assess ment for the damage fair?
Mostly. The insurer’s assessment missed some items which should be included. The insurer
should also contribute to some of the make safe costs being claimed. Therefore, the insurer
should settle the claim in the manner set out in section 2.1.
1.3 Determination
This determination is mostly in favour of the insurer.
The insurer should settle the claim in the manner set out in section 2.1.
Determination | Case number: 889815 Page 2 of 6
2 Reasons for determination
2.1 Is the insurer’s assessment for the damage fair?
The policy is an insured events contract of insurance
The initial onus is with the complainant to establish on the balance of probabilities (that is
more likely than not) that the loss or damage claimed falls within the terms of the policy. This
is known as a valid (or prima facie ) claim.
The policy covers the insured property against loss or damage caused by one or more the
listed insured events, including storm, during the period of insurance.
There is no dispute the complainant’s home suffered damage because of a storm on 8 March
2022. Storm is an insured event under the policy. However, the parties dispute whether this
event caused all of the damage claimed. The complainant must be able to show the disputed
damage was caused by the storm.
Reports indicate damage to the subfloor and piers to be long term
There is no dispute storm water has entered through the roof or the house suffered water
damage. This includes damage to several parts of the house.
The insurer has accepted liability for the resultant damages to the property and contents. It
has cash settled the complainant for the contents damage. The insurer has made an offer for
the property damage.
The insurer has declined cover for damage to the subfloor area and piers. The insurer said
this is due to long term issues and not caused by the storm.
The complainant denies any pre-existing and long-term issues with the house. He says the
insurer’s assessment of the subfloor and piers is incorrect and this damage should be
covered. He says the insurer has failed to consider the damage report from his engineer
(GCE).
GCE concluded:
external review shows heavy scouring and erosion of garden and foundation materials
from flowing water
the brick retaining wall to the west shows a major tilt and a horizontal crack protruding
approximately 10mm
the retaining wall has failed and poses a significant risk of collapse causing potential
further asset damage to the downhill neighbouring properties
existing drainage appears to be installed correctly to a good standard but has failed due to
rainfall
masonry piers below the house are moderately tilted
flooding water has scoured out beneath the masonry piers
the stability of these piers cannot be assured under their current loading conditions
temporary propping has been installed as a make safe option.
The complainant also provided a drainage report from AC which states in summary:
In conclusion, we feel there is now sufficient drainage around the house to protect
the ground floor of this property. Given the work that has been done, it is clear to
Determination | Case number: 889815 Page 3 of 6
us that the flood damage to the structure of the property, was caused by the
previous drainage failing due to the sheer volume of water from the storm cell on
the 8 th of March.
Conversely, the insurer says it is not responsible for the damage to the subfloor piers and
relies on its expert report by JHA.
During inspection, JHA noted the following:
subfloor displayed significant efflorescence and dampness
the piers appeared to have eroded
packing was identified between stumps and bearers that pre-existed the event
water staining to bearers was also noted
the site displayed inadequate arrangements for surface drainage
dampness and moss/mould growths were noted specifically on the left-hand side of the
property
the surface is graded toward the dwelling, allowing water to pond and seep into the ground
and possibly enter the subfloor.
JHA also noted that the interior of the dwelling was undergoing renovation works, as some of
the building elements have been removed by the insured.
In addressing causation, in summary, JHA says a level survey taken within the dwelling
indicates evidence of long-term differential foundation settlement due to the presence of
reactive clay founding soils and influence of tree roots within the footing and slab. JHA says
this has been exacerbated by poor site drainage.
JHA says due to no stormwater drainage system being in place, extensive soil erosion has
occurred in the dwelling sub-floor. It says this is a long-term issue stemming from non-
compliance of the drainage system.
It concludes that the erosion and movement damage to the subfloor piers are not considered
to have been caused by a single storm event on 8 March 2022, rather due to long-term
processes.
Subfloor is not covered
Having carefully considered the expert evidence, as well as all the other information, I note
the following.
Of significance is JHA’s identification of packing between the stumps and evidence of long-
term water entry. This included moss/mould growth to elements and significant efflorescence
in the floor. This physical evidence is consistent with pre-existing issues with the piers and
subfloor. It is also consistent with the floor variation of 67mm.
GCE’s evidence about the drainage being adequate is not persuasive given there is no detail
supporting this conclusion. Regarding AC’s testing , no videos or photos were provided to
confirm the results. Further, neither AC nor GCE talk about the drainage arrangements in
place to protect the subfloor. Given the slope of the surrounding ground, and JHA’s
observations that there was inadequate drainage and grading, AC’s report is inconsistent with
this. Further, AC’s conclusion is inconsistent with the physical evidence that there are pre -
existing issues with the subfloor (e.g. packing, moss/mould and efflorescence).
Determination | Case number: 889815 Page 4 of 6
Given all this, I am not persuaded the available information shows the damage was caused
by the claimed storm event. Instead, the damage is consistent with long term issues related to
site drainage and nearby trees.
Therefore, the insurer is not liable for the damage to the subfloor. This includes the piers.
Insurer’s offer is missing items
The insurer has made an offer based on two scopes of works and quotations from J dated 9
December 2022:
one for $28,901.40 for repairs J is willing to undertake
another for $11,350.28 for cash settlement as J is unable to warrant the repairs due to pre-
existing conditions.
The complainant, in his email dated 12 December 2022, raised various concerns with this
offer beyond the subfloor. This includes the following:
the scope of works does not reflect the cost of materials and works – for example, his
quotes were around $5,000 each for the costs of floating floor and joinery but J’s quoted
amounts were substantively less than this
the scope of works is missing the following items:
> repair and replacement of the floating floor at front door entrance
> front door to ground floor area
> remove and replace sliding door unit to bathroom
> render and paint external brickwork once it is replaced
> any other external damage caused by works
the make safe invoice he incurred remains unpaid
The insurer has provided an email from J confirming the quotes are actionable and current.
Whilst the complainant questioned this given he is also a builder, there is no basis to
conclude J’s evidence is false or it could not do the work for the amounts offered.
For the other items, the insurer has not provided a submission addressing this. Having
reviewed the two scopes of works, it does not appear these items have been included. Given
the complainant’s position has not been refuted by the insurer, then the scope of works
should be amended to address these items. This excludes the last bullet point which will be
addressed in the contingency and discussed later.
For the make safe invoice, the insurer did not make a specific submission on this to AFCA. I
do note the insurer sent an email dated 28 April 2022 indicating the invoice appears to be
maintenance work. This was supported, to an extent, in a subsequent assessor’s report done
the following day.
In reviewing the make safe invoice, I note it was done by the complainant’s building c ompany
and included the following items:
1. cleaning and removing of existing floating floor
2. concreting of existing flooring where it has been undermined by flood
3. waterproofing of subfloor masonry and footing
4. clearing, cleaning and repairing of existing drainage and roof guttering
5. plumbing and drainage: ‘camera and jettering stormwater’
Determination | Case number: 889815 Page 5 of 6
As I am not persuaded the subfloor or piers were damaged by the claimed event, I do not
accept items involving this area should be included. This excludes items 2 and 3.
The plumbing invoice for the camera and jetting appear to be for clearing tree roots. This is
not related to the insured event. This should be excluded as well.
I accept the first item should be covered as it appears clearly related to the claim. For the
fourth, this also appears to be claim related and should be included.
Claim should be settled in this way
I accept the insurer’s costing is fair given it is verified by J. However, it should engage J to
amend the scope of works and quotes to include these missing items:
repair and replacement of floating floor at front door entrance
front door to ground floor area
remove and replace sliding door unit to bathroom
render and paint external brickwork once it is replaced
Once J does, the insurer can cash settle the claim based on this updated scope of works and
quotes. It should also include a 15% contingency. I consider this contingency is fair due to the
following:
the insurer’s quotes are not all actionable as part of J ’s quotes were for liability only
there is a potential for additional damage occurring due to the works – this can include any
other external damage caused by the works highlighted by the complainant
the risks of the works passing to the complainant and th e loss of the insurer’s guarantee of
works
No interest is payable given this should be based on current quotes.
The insurer should also reimburse the complainant for the make safe invoice for the items
that are claim related. I have allowed $4,219.65 based on the following:
allowing the amounts for items 1 and 4
allowing a proportion of the builder’s margin based on the proportion allowed for the four
items
adding GST
The insurer should pay interest on this amount pursuant to section 57 of the Insurance
Contracts Act 1984 (the Act). Interest is payable from 28 April 2022, being when it first
responded to the make safe invoice, until payment is made.
Determination | Case number: 889815 Page 6 of 6
3 Supporting information
3.1 The AFCA processes
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.