Home / IAG / Determination 888869

Determination 888869

Insurer limited liability for leaking stormwater pipe damage, attributing part to excluded causes; complainant sought settlement on her engineer's scope of works

FirmIAG
Decided2023-03-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant's home was damaged by leaking stormwater pipes, and the insurer limited its liability based on its own scope of works. AFCA found in favour of the complainant, requiring a new scope of works by her engineer, a cash settlement on builders' quotes plus 15%, and a contribution of up to $5,000 to her professional costs.

The leaking pipes were the proximate cause of most damage, so the Wayne Tank principle did not apply and the claim should be settled on the complainant's engineer's scope covering the affected areas.

Issues

Subjects and remedies

home or building damagepay claimpay compensationreassess claim

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 888869 Financial firm Insurance Manufacturers of Australia Pty Ltd Determination | Case number: 888869 Page 2 of 11 Case number: 888869 28 February 2023 1 Determination overview 1.1 Complaint The complainant lodged a claim with the financial firm (the insurer) in October 2018 for damage to her property, after water was discovered leaking from multiple stormwater drains. The insurer has sought to limit liability based on a scope of works (SOW) prepared by its structural engineer SW and quote from buildings services company UB. The insurer accepts damage has been caused by leaking pipes but says surface drainage issues, the reactive foundation soils and faulty design and workmanship contributed to the remaining damage. The complainant relies on several engineering reports from her structural engineer RB and plumber C to say the SOW relied on is inadequate and most of the damage should be covered. 1.2 Issues and key findings Should the insurer increase its settlement offer? Yes. The panel is satisfied that the insurer should increase its settlement of the claim based on the report from the complainant ’ s engineer RB as set out in section 2.1 of this determination. Is the insurer required to contribute to the complainant’s professional costs? Yes. The insurer is to contribute up to $5,000 to the complainant’s professional costs Why is the outcome fair? The available information indicates the proximate cause of most of the damage has been caused by the leaking pipes. It is fair in the circumstances that the claim be settled based on a SOW prepared by RB covering the agreed damage. 1.3 Determination This determination is in favour of the complainant. Within 14 days of the complainant’s acceptance of this determination the insurer is to:  appoint RB to prepare a SOW to cover the repairs to the areas of influence shaded in pink and green as identified in the sketch in RB ’s report  on receipt of the SOW, appoint two independent builders to provide actionable quotes for completion of the repairs as per the SOW. The insurer may then cash settle the claim based on the higher of the quotes plus a 15% uplift to cover contingencies  under AFCA rule D.5 pay the complainant up to $5,000 contribution to the complainant’s professional costs incurred subject to the provision of the relevant invoices or receipts. Determination | Case number: 888869 Page 3 of 11 2 Reasons for determination 2.1 Should the insurer increase its settlement offer? Yes. The panel is satisfied that the insurer should increase its settlement of the claim based on the report from the complainant’s engineer RB as set out in this determination. No dispute property sustained damage due to leaking stormwater pipes The complainant has the onus to establish on the balance of probabilities (that is more likely than not) that the loss or damage falls within the terms of the policy. The complai nant’s Home and Contents policy was incepted in December 2012 and provided cover for a series of listed events including water and oil leaks. Particulars of cover are set out in section 3.3 of this determination. There is no dispute that there was water leaking from the storm water service. The complainant provided a report from her plumber RP dated 18 October 2018 confirming the CCTV inspection revealed the stormwater service to be in bad condition with water easily able to leak into the trenches under the house. The insurers engineer RC reported on 19 February 2019 that water had been escaping for an unknown period resulting in differential movement of the footings and damage to the property. The insurer accepts the water leaks contributed to the damage claimed. The insurer, relying largely on reports from engineers RC and SW says the damage was contributed to by inherent long-term foundation movement and general building movement. Such damage is excluded under the terms of the policy. The insurer has also suggested damage caused by a kitchen waste pipe had occurred prior to inception of the policy. The panel accepts the complainant has established the claim falls within the terms of the policy. To the extent the insurer seeks to limit its liability the insurer must show, on balance, the damage was caused by a policy exclusion or it is otherwise entitled to decline the claim. No evidence the kitchen waste pipe was leaking prior to policy inception While the insurer says the kitchen waste pipe started leaking prior to the policy inception in 2012, there is no substantial evidence to demonstrate this. The plumbers report from CDC confirms a broken pipe was identified under the kitchen area. CDC referred to it as an old stormwater pipe. Initially it was considered a possible source of a leak and likely poor workmanship. CDC has since confirmed it had been disconnected. It was not connected to anything and has not been connected to either the sewerage or stormwater lines. The pipe had concrete poured into it to stop any water getting in. The panel is satisfied there is no persuasive evidence to establish the pipe was a source of a leak pre-dating 2012 or the claimed damage to the property. Insurers reports differ as to cause of damage While there is no dispute there was damage caused by the leaking pipes, the expert reports differ as to the extent of that damage. Significantly however, both the insurer’s expert RC and the complainant’s expert RB are in broad agreement that about 70% of the damage is attributable to the leaking pipes. Determination | Case number: 888869 Page 4 of 11 R C’s initial report says the lack of drainage a long the southern wall caused the founding soil to swell, contributing to damage. After receipt of further reports, RC revised its conclusion in March 2020 and considered 70% of the damage due to plumbing issues, 20% due to ineffective drainage and 10% due to natural sol movement. The insurer’s engineer SW provided reports in August 2022 and October 2022. SW considered the breakage in the wastewater pipe adjacent to the kitchen has caused water ingress to the surrounding soil, spreading to the subfloor, and subsequently flooding the subfloor. The escape of water from the breakage within the pipe has contributed to differential movement and damage to the allocated rooms in the radial influence zone indicated including the kitchen, living, dining, laundry & lounge. SW considered the damage in the remaining rooms about the eastern side of the property was unaffected by the escape of water and pre-existing in nature. This included damage to bedroom 3, bathroom, toilet, master bedroom & ensuite, bedroom 2, hallway and entry. SW says the damage to this area is outside the radial influence zone and attributable to factors such as foundation reactivity, inherent thermal movement, age-related wear and tear & deterioration and insufficient drainage/subfloor ventilation. Complainant ’s reports more persuasive The complainant’s plumber, RP, noted multiple pipe breaks below the property. This first was under the driveway in the north side. The second pipe was at the rear west of the property. The complainant’s engineer RB first attended the property in April 2021 at which time he had access to the various plumbing reports and engineering reports from RC. RB did moisture testing 300m below the pipes revealing moisture of 36%. This confirms a substantial and continuous leak, which would have initiated heave and most of the failures within the plumbing. The borehole testing confirms the degree of movement within the middle of the property. RB provided a sketch with the area he thought was influenced by the leak shaded in pink and green. The area not influenced but likely due to natural soil movement was shaded in blue. In response to SW’s report dated 14 October 2022, RB noted that the highest location is in fact the south-east corner as is the whole south side of the building. Most of it is away from the zone of influence that they wish to believe is accurate. The reality is that water does not flow uniformly through soils, it flows through trenches far more quickly than it does through normal soil. It was RB’s firm opinion that the leaks that have been prolific in the property have flowed the trenches and have influenced the building beside those trenches. The sketch in the original report indicates the area’s most lik ely influenced by the leak being in pink. RB ’s findings are based on extensive soil and moisture testing. RB ’s level survey identified the highest points to be at the south-east corner of the dwelling, being the furthest location away from the leaking pipe. This is consistent with water flowing through the trenches and influencing the building near these trenches. If the damage had been due to the factors identified by the insurer, it is likely the type of ground movement would not have been heave. The panel is satisfied RB ’s findings support the view the leak was substantial and has affected the founding soils beyond the areas identified by SW. Wayne Tank principle does not apply The panel has considered whether the Wayne Tank principle applies. Basically, that principle provides that if there are two or more causes of damage of equally proximity, one an insured Determination | Case number: 888869 Page 5 of 11 event and one an excluded event, the exclusion will apply to defeat the claim. The panel acknowledges and accepts that some of the damage as identified by RB and SW was not related to the events. That damage is identified in the area shaded blue in the sketch provided by RB. The panel is satisfied however that the Wayne Tank principle does not apply to the remaining damage. There is no evidence the damage existed prior to the water leaks. While there is some information to suggest the natural soil movement contributed to some of the damage, there is no evidence that natural soil movement had caused any damage prior to the water leaks. Exactly how long the water had been leaking is unknown, but it is clear the water leaks had been substantial. Multiple leaks have been identified. These leaks caused the damage claimed. This is consistent with:  RB ’s explanation about water flowing through the trenches and the level survey results  the house having stabilised following the drying out period (this indicates the damage was caused by the leaks)  the fact substantive damage should have been observed before 2018, if the damage was caused by a leak before inception in 2012  the report from RB shows the ground is very wet, consistent with leaks being the cause. Based on the information available, including the reports from RC and RB, the panel accepts that the proximate, that is the dominate or effective cause of the damage was the leaking pipes. The panel does not accept the surface drainage issues or reactive foundation soils were of equal proximity in causing the damage identified by RB and RC. Insurer is liable to increase settlement offer The panel is persuaded by the report from RB dated 11 May 2020 that damage shaded pink and green in the sketch provided by RB (section 3.4 of this determination) should be covered under the terms of the policy. The area shaded blue is likely due to foundation movement and excluded from cover. The panel notes the complainant has completed all relevant maintenance work to the sewer and stormwater service (completed by CDC in 2020) and that the recommended to year drying out period has now lapsed. Accordingly, the panel determines that within 14 days of the complainant’s acceptance of this determination the insurer must:  engage RB to provide a SOW to cover the damage identified in the areas shaded pink and green in the sketch provided in the report of 11 May 2020,  on receipt of the SOW, appoint two independent builders to provide actionable quotes for completion of the repairs as per the SOW.  the insurer may then cash settle the claim based on the higher of the quotes plus a 15% uplift to cover contingencies including the transfer of risk.  interest is not payable given the settlement will be based on a current quote. If the parties are unable to agree on the quantum, the complainant can lodge a new complaint at AFCA for a decision on this point. 2.2 Is the insurer requi red to contribute to the complainant’s professional costs? Yes. The insurer is to contribute up to $5,000 to the complainant’s professional costs Determination | Case number: 888869 Page 6 of 11 The insurer is to contribute to the cost of the complainant ’s expert reports Under Rule D.5, AFCA may determine an insurer contribute to legal or other professional costs incurred by a complainant during a complaint. Unless exceptional circumstances apply, AFCA will not require an insurer to contribute more than $5,000 to these costs. When determining whether an insurer should contribute to the payment of professional fees incurred, AFCA will consider the complexity of the complaint, whether the advice was reasonably needed and whether the costs incurred were because the expert advice was genuinely required. In t he panel’s view, the complainant’s engineering and plumbing reports were necessary to assist in establishing her case. The complainant provided reports from RP, CDC and RB (x3). The panel is satisfied the insurer should reimburse the complainant for the costs incurred in obtaining those reports. The panel considers it fair in the circumstances the insurer contributes up to $5,000 in total for all the professional costs incurred by the complainant during this complaint, subject to the complainant providing the insurer with the relevant invoices for the reports. 2.3 Why is the outcome fair? The available information indicates the proximate cause of most of the damage has been caused by the leaking pipes. It is fair in the circumstances that the claim be settled based on a SOW prepared by RB covering the agreed damage. Determination | Case number: 888869 Page 7 of 11 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes an ombudsman, a member with significant experience in consumer and small business advocacy, a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Expert reports Record Key points Insurer ’s enginee r (RC ) Report 12 - 02 - 2019  Garden beds are allowing water to migrate to the soil below the dwelling.  Civil drainage did not exist along one or more walls.  A wastewater pipe l eft uncapped has been discharging water onto the subfloor soil for an unknown period .  The discharged water migrated through the founding soil in the area, causing stumps to subside and stumps further away to swell. Determination | Case number: 888869 Page 8 of 11 Record Key points  The lack of civil drainage along the sou thern wall caused the adjacent founding soil to swell, contributing to the damage in the laundry and western - most bedroom and causing damage near the southern wall.  The damage to the driveway has been caused by natural seasonal movement and settlement of t he subbase.  The l eak under the kitchen would not have resulted in water finding its way to the underside of the pavement. Insurer ’s engineer (RC) Report 24 - 03 - 2020  The level surveys indicate relatively little movement has occurred over the last 12 months.  The aesthetic damage appeared unchanged in most cases.  The founding soil has not reached a new moisture equilibrium, as defects are still present in the plumbing systems.  In effective drainage and a tree were sighted during the reinspection. Insurer’s builder (LO) Report 24 - 03 - 2020  T he stormwater plumbing was in a bad condition and had been leaking water under the house, which the plumber believed has contributed to the movement issues.  The property had evidence of existing movement - related is sues within both the conc rete driveway and the brick veneer of the property.  Despite this , a CCTV inspection has shown water escaping from the stormwat er plumbing underneath the property. Complainants plumber ( RP ) Report 18 October 2018  There are two poi nts of legal discharge on the property .  One through the driveway to the north with a discharge into a pit , and another one locat ed to the rear of the property.  Water is easily able to escape the current damaged drain and has been leaking into the trenc hes under the house. Insurer’s builder ( SP ) Report 20 - 07 - 2020  During inspection of the stormwater system, SP found the entire stormwat er system has been renewed with PVC. T he new lines are in good condition, with no areas of concern.  There is no evidence of any cracks or breaks within the pipes and no signs of any blockages. Insurer’s engineer (RC) Report 02 - 10 - 2020  The temporary civil drainage has prevented water from ingressing to the soil and migrating below the footings.  The drying out period has elapsed, and the repairs can now begin.  It is recommended graded concrete paving is installed around the perimeter of the dwelling when possible. Complainant’s engineer (R B ) Report 11 - 05 - 2021  The garage is solid brick, using brick piers, timber rafters, and a standard tin pitched roof. The main driveway into the garage is two strips of concrete that are in average condition. Beside the hous e, the paving is from the building to the fence.  As to the externals of the property we noted that the site is very flat and by today's standards site drainage, i.e. the grading of the ground away from the building, has not been initiated, thus there is some potential for localised wetting up in some areas. Determination | Case number: 888869 Page 9 of 11 Record Key points  There are no major trees in and aro und the property, save for the tree at the neighbour's house, but it is at a sufficient distance away and unlikely to be causing any effect (currently). Complainant’s engineer (R B ) Report 18 - 08 - 2021  The moisture levels in the two samples indicat ed a very high moisture regime. Above 30% would indic ate a leak, and 36% moisture content means a substantial leak.  Noting this was 300mm below the invert levels of the pipes and thus a substantial and continuous leak initiating heave and possibly initiating most of the failures within the plumbing.  The plumber CP indicated all static testing was initiated, and all found to be perfect, thus all the leaks have been eliminated.  The major leak , picked up adjacent to the kitchen sometime back , has now been corrected, b ut its effects i.e. water running in the trench has moved all the ground on the southern side of the building and has initiated most, if not all, of the high moisture content along that line.  This in turn has heaved the southern side of the building for i ts complete length.  The stormwater line runs across the back of the kitchen area and down the complete southern side of the building towards the front street.  The moment the failure existed adjacent the kitchen, the trench became incredibly wet and remaine d so, causing heaving of the building.  There is heaving on the western side of the property and dislocation and heaving along the southern length of the boundary.  T he northern portion of the lounge living area has also been heaved. Complainant’s engineer (R B ) Report 21 - 10 - 202 2  Plumber C Ps report defined the pipe as an old stormwater pipe and correctly noted it has been disconnected.  The upstream and downstream ends go i nto dirt and/or are blocked off. T hus, it cannot convey any moisture as it is not con nected to anything.  RI d is agrees with the interpretation that moisture moves in a uniform circle from a given point. It does n ot , it moves along trenches as it is willed and free to do. Insurer’s engineer (SW) Report 02 - 08 - 2022  E scape of water within the pipe has contributed to differential movement and damage to the rooms , including the kitchen, living, dining, laundry & lounge .  The damage in the remaining rooms in the eastern side are unaffected by the escape of water and are pre - existing in nat ure . T hes e include bedroom 3, bathroom, toilet, master bedroom & ensuite, bedroom 2, hallway and entry.  The areas outside the zone of influence are unrelat ed to the wastewater pipe breakage, and are attributable to the following factors: > f oundation reactivity > i nher ent thermal movement > a ge - related wear and tear & deterioration > i nsufficient civil drainage/subfloor ventilation/maintenance as outlined by RC . Determination | Case number: 888869 Page 10 of 11 Record Key points Insurer’s engineer (SW) Report 14 - 10 - 2022  Some of the highest points in RI’s level survey w ere at the s outh - e asternmost corner of the dwelling, which is the furthest location away from the claimed leaking pipe.  Given RI acknowledged ‘the site is very flat by today’s standard site drainage’, the escape of liquid beyond the zone of influenc e would not have been pla usible.  T he higher degree of fluctuation in foundation material moisture over the las t six years has resulted in more severe foundation reactivity and prominent movement and damage within the building fabrics.  SW reaffirms any damage outside of the zone of influenc e is attributable to inherent foundation reactivity and general building movement and is unrelated to the claimed leaking pipe event. 3.3 Relevant policy provision Water and oil leaks If loss or damage is caused by water or oil leaking or escaping from an item shown here. Covered water leaking or escaping from: - house gutters, drainpipes or pipes - sanitary fixtures – for example, baths or toilets - appliances – for example, washing machines or dishwashers ………….. Not covered water leaking or escaping from a shower recess or shower base costs to repair or replace the item that the water or oil leaked or escaped from RB property damage sketch (17 August 2021) Determination | Case number: 888869 Page 11 of 11

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.