Determination 887989

Storm water damage claim declined; make-safe and mould remediation handling

FirmSuncorp Group
Decided2022-11-25
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,000
Amount claimed$84,000
SourceAFCA PDF

Summary

The complainants claimed water damage after a storm, which the insurer declined as caused by gradual deterioration and excluded factors. AFCA upheld the decline but required the insurer to reimburse make-safe costs, fund further mould remediation and half of damaged contents, and pay $2,000 non-financial loss.

Damage from gradual deterioration and maintenance issues is excluded and not a single storm event, but the insurer's assurance on make-safe reimbursement and its inadequate mould and make-safe handling make it liable for those costs and compensation.

Issues

Subjects and remedies

financial hardshiphome or building damagenatural disasterpay compensationpay interestpay non financial lossprovide documentsreassess claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 887989 Financial firm AAI Limited Determination | Case number: 887989 Page 1 of 9 Case number: 887989 23 November 2022 1 Determination overview 1.1 Complaint The complainants hold a building and contents insurance policy with the financial firm (insurer). They lodged a claim on 24 February 2022 for water damage following a storm. The insurer denied the claim, saying the damage was the result of gradual deterioration and maintenance issues, and there were no storm-related openings to the roof. The complainants believe the claim should be paid. They have also raised concerns about the insurer’s make- safe, its failure to remediate mould, and its overall handling of the claim. 1.2 Issues and key findings Is the insurer liable for the claim? No. The available evidence shows the cause of the damage was not a single-storm event, but was the result of excluded factors. The insurer is entitled to decline the claim. Is the insurer liable for further costs regarding the make-safe work? Yes. The insurer indicated it would undertake necessary make-safe work. It then told the complainants they were welcome to source their own tradespeople for any repairs or make- safes and the insurer would reimburse quotes that were fair and reasonable. In reliance on that, the complainants undertook work, including stripping out affected ceiling and wall linings. The insurer is required to reimburse them for their claim-related make-safe work undertaken, plus statutory interest. It is also required to cover the cost of additional remediation work which should have been carried out, as identified by restorer FEN. As well, the insurer is required to contribute towards the contents damaged by mould because of delays/failings in its dealing with the make-safe. Is an award of compensation warranted in the circumstances? Yes. The insurer is required to pay $2,000 as compensation for non-financial loss for unnecessary delay, upset and inconvenience caused to the complainants. Why is the outcome fair? It would not be fair to require the insurer to cover a claim for damage which is excluded under the policy. However, it is fair in the circumstances that it meet the cost of make-safe it undertook to complete, and additional make-safe work as recommended by its expert. It is also fair that the complainants be compensated for their claims experience. 1.3 Determination This determination is substantially in favour of the insurer. As set out in detail in section 2.1 below, the insurer is required to: reimburse the complainants’ costs incurred for make-safe work, plus statutory interest; cover half the mould-damaged contents; cover the costs of the balance of make-safe work identified by restorer FEN. It is also required to pay $2,000 compensation for non-financial loss. Determination | Case number: 887989 Page 2 of 9 2 Reasons for determination 2.1 Is the insurer liable for the claim? Complainants bear onus of establishing a claimable loss The complainants bear the initial onus of establishing they have a prima facie (or valid) claim. Their policy covers listed insured events. That means the complainants need to establish, on the balance of probabilities, one of the insured events listed in the policy, such as storm, was the cause of the damage. Damage not caused by an insured event is not covered. Cover for storm (and other insured events) is also subject to terms, conditions and exclusions. For example, the policy specifically excludes cover for damage caused by, connected with or arising from gradual deterioration, wear and tear, subsidence, or the building not being in good condition (such as a failure to maintain the property). The policy defines ‘storm’’ as: a single weather event being, a cyclone or severe atmospheric disturbance. It can be accompanied by strong winds, rain, lightning, hail, snow or dust. Evidence shows pre-existing issues with the roofing, and more broadly The insurer engaged builder R to report on the cause of the damage. R attended on 4 March 2022 and noted:  the roof was in poor condition, and the gutters were leaking from rust holes that were visible from walking around the house  the complainants would have been aware of that from the recent pre-purchase building inspection report they had arranged and which had set out a number of maintenance issues with the roof (they had only purchased the property a few months before)  property has leaked in multiple locations throughout the front lounge  property has leaked around the stove flue and skylight  ingress that has occurred in both locations was detected to have entered through roofing related issues, including heavily rusted roof sheets and rust where previous solar panels were installed  mould has started to occur in the property  roof system has no storm-related damage or openings  if the roof was in average, water-tight condition no ingress would have occurred. The complainants rely on the advice of their builder NR regarding the cause of the damage. NR concluded that the house guttering had back-flowed in the eaves and flooded down through the inside of the walls. NR reported:  rear of the house is sitting 50mm lower than the rest of the house  plumber says the sewer pipes have dropped in different locations under the house  skylight and fire flue have both leaked causing damage to the ceiling  mould has grown on the rear face of the cladding, which contains asbestos. The complainants have stated that prior to the storm, the roof had no holes or issues resulting in water ingress and there was no mould or cracking. Instead, they say the volume of rain experienced in the storm caused a back-flow of water under the eaves and into the property. Determination | Case number: 887989 Page 3 of 9 However, the complainants have also said that when they purchased the home in July 2022 they had a building inspection. They say their builder noted that the roof would need replacing within the next 12 months (there were no leaks, but 3 sheets had signs of wear and tear); foundations were good and there was no termite damage. Having regard to the other expert evidence provided, I am not persuaded the pre-purchase inspection conclusions (as reported by the complainants) reflect a comprehensive or fully accurate assessment of the condition of the property. The complainants have also acknowledged they had bought the house to renovate it and were in the process of obtaining quotes. When he attended, R did note the house was in the process of renovation. In response to the report of builder NR, R provided a further response (having re-attended on 26 April 2022), stating:  the settling to the property is pre-existing  flue and skylight issues likely pre-existing as the roof is in such poor condition  it is not possible for the eaves to have flooded inside the house as the eaves are raked, meaning if the gutter has overflowed, it cannot run uphill of the rake eave into the wall frame. The insurer engaged roof expert SRS to report on the condition of the roof and whether that contributed to the damage. SRS concluded (on 9 March 2022):  lounge room has suffered water dripping and mould growth after prolonged rain in late February and early March 2022  insured has carried out a make-safe with removal of walls and flooring  wood-burning stove has leaked around top plate downstream affecting skylight area  roof has a serviceable life of less than five years with some sections in poor condition requiring repair; possible water ingress present  roof over the lounge room has areas of rust and corrosion  potentially an older solar panel system rested on the roof in these areas  the entire roof has evidence of multiple repair attempts, suggesting this roof has had multiple leak issues in years past  the removed tarp exposed galvanised roof sheets with large rust and corrosion present  all sheet laps have in recent times had silicone applied in an attempt to prevent water ingress  slipper sheets have been installed and rust between laps of sheeting has occurred and are heavily rusted towards end of roof sheeting directly over main area of ingress internal of lounge room  no storm-related damage or openings causing ingress were detected  entire roof system is past its serviceable life and is recommended for complete replacement. The insurer then arranged for engineer JHA (on 19 July 2022) to assess the causation of the sunken footings. JHA concluded:  the dwelling is estimated to be 55 years old and is considered to have been poorly maintained and in poor condition considering its age  site drainage around dwelling is inadequate, as made apparent by the ponding water towards the rear side of the subfloor  roof gutter is leaking water on the eastern side of the dwelling, as well as a drainage pipe not connected  inspection of the subfloor noted water ponding with poor site drainage, which would cause ground differential movement over a long period Determination | Case number: 887989 Page 4 of 9  eastern water pipe has not been installed as per regulations, causing water to leak at rear right end side of the dwelling; over an extended period, this will cause foundation movement  high differential movement was located at the rear end of the dwelling where the damaged gutter is located and where the water is ponding around the piers in the subfloor  there is a 78mm variation and gradual slope from the front to the rear of the dwelling  cause of the movement may be attributed to several factors: > downpipe discharge around foundations > site drainage conditions > abnormal moisture conditions  damage was not caused by a single event but due to the combination of long-term processes relating to differential foundation movement. On balance, damage was from excluded factors and not a single storm event The available evidence shows a property which had already been experiencing long-term deterioration, rust, and corrosion. That applied particularly to the roof. As well , the property’s foundations had, on balance, been impacted by changes in soil moisture content, causing the drop in the foundation. This was all caused by numerous factors not related to a single insured event. Although the complainants’ builder NR said that back-flow under the eaves was the cause of the water ingress, and the complainants indicate their roofer said the roof was in sound condition, they have also reported they were told it would need replacing within 12 months, when they purchased the house. That reasonably suggests issues of current or potential concern (which the other expert evidence confirms). Having considered all the available evidence, I am more persuaded by the insurer’s reports , where the conclusions reached are consistent with the photographic evidence. The photographs show obvious signs of deterioration, including holes through rust. I also note the complainants have not provided a formal written report from their roofer. I am not satisfied the complainants have established the cause of the water ingress and damage to the property was a single insured storm event. Instead, I am satisfied, on balance, the available evidence shows the damage was the result of excluded factors, including gradual deterioration and maintenance issues. That means the insurer is not liable for the claim under the policy. 2.2 Is the insurer liable for further costs regarding make-safe? Insurer performed initial minimal mould remediation only The policy provides some cover for other repair or rebuilding costs. The policy says the insurer will cover the reasonable and necessary costs of any temporary work required to make the damaged building safe; although, the policy does state the insurer will only do this when the insured is covered for the cost of rebuilding or repairing the damaged parts of the building. The i nsurer initially appointed C G to attend on 8 March 2022 and do what was necessary to make the property safe , even before a claim decision had been made . That is reasonable in the circumstances. Determination | Case number: 887989 Page 5 of 9 CG found no damage to the limited contents in the property at the time, and noted floor coverings and wall linings had already been removed by the complainants, revealing advanced mould growth . CG said they undertook i nitial make safe remediation . The insur er’s claim file notes show that on 25 March 2022, the complainants called the insurer and said mould was spreading . They asked about removing contents from the property. The i nsurer reportedly told the complainants it was up to them whether to move the con tents to a safe place to ensure there was no further damage. It is not clear what contents, if any, the complainants removed. C G contacted the i nsurer on 3 June 2022 to advise the contents in the property had been damaged while the home had been locked up . CG said mould growth was visible , but attributed that to the complainants ‘ interfering with areas which had previously been subject to make safe repairs ’ . It is not clear what form that ‘ interference ’ took. In any case, the evidence shows the property had been developing mould at a significant rate due to the moisture content from water ingress, and the home being left closed up and not dried out. The insurer then arranged for restorer FEN to attend for further mould remediation, but FEN advised the insurer that on 16 June 2022 the complainants had told them they had made arrangements for another company to attend and the job was therefore cancelled. FEN’s attendance was later re-arranged, and they took moisture readings, and formulated a scope of works which they said they would complete, once approved by the insurer. FEN’s report to the insurer (with photographs labelled 20 June 2022) had confirmed the property was affected with significant levels of mould and a strip-out was required to make it safe. FEN also recommended that a builder/roofer was required to tarp the rest of the roof as only half of the roof had been tarped; electrician to complete a make-safe; asbestos sampling required. They also suggested a contents assessment and inventory be conducted. However, by the time the complainants had contacted FEN to schedule the further mould remediation work, the insurer says the decision had been made to decline the claim. That meant no further mould remediation was carried out by the insurer. Insurer liable for additional make-safe costs Although the insurer was entitled to decline the claim, this decision was not definite until after the receipt of the engineer’s report in July 2022. While the insurer had previously informed the complainant of its decision to decline the claim, it was also in correspondence with the complainant confirming the claim was ‘ on hold ’ until the engineer’s report was received. In the meantime, the insurer continued to provide the complainants with temporary accommodation. Earlier in the claim (in an email of 11 March 2022), the insurer had informed the complainants they were welcome to source their own tradespeople for any repairs or make-safes and the insurer would reimburse quotes that were fair and reasonable. In reliance on that assurance, the complainants arranged certain make-safe work themselves (including stripping out of walls). In the course of that work, asbestos was found. It is not clear why the necessary significant drying of the property and further make-safe did not occur in the meantime; nor which of the parties was expecting to do that. I do acknowledge, however, the complainants have indicated they did not have excess funds available to them, apart from what had been set aside for the roof itself. Determination | Case number: 887989 Page 6 of 9 As already noted, the policy does confirm the insurer will make the property safe if it is covering the cost of repairing or rebuilding the property. However, it is standard industry practice for the insurer to undertake at least initial make-safe to the property during the claims process and pending a final claim decision. I am satisfied the insurer was responsible to do what it could do to stop the spread of mould at the property until its final claim decision. I am satisfied its own internal assessor identified what was required to achieve this, as did FEN. That included properly tarping the roof (which both FEN and SRS found was inadequate). Although the insurer correctly declined the claim, the evidence shows it had informed the complainants it would cover the reasonable cost of make-safe work. That is before the further spread of mould occurred. I am satisfied it is fair and appropriate that the insurer reimburses the complainants the costs they incurred in doing that work. They say that amounted to about $11,000 for removal of 50% of the affected wall linings and ceilings (which were found to contain asbestos), which is all they could afford. It is not clear what other make-safe they completed in reliance on the insurer’s assurance they would be covered for that. The complainants are required to provide evidence of the make-safe work they undertook and the respective costs incurred. The insurer is required to cover those costs. Statutory interest is also payable on those amounts, calculated from the date the complainants paid, to the date of settlement. To be clear, the insurer is not liable for any additional or non-claim related work undertaken by the complainants in connection with their planned renovation of the property. I am also satisfied, on balance, the insurer should be held liable for the cost of the further mould remediation/make-safe which was not carried out. That is summarised in the ‘works to be completed’ section of FEN’s June 2022 report. (If some of that work is included in what the complainants themselves have already undertaken, then it is not required to be covered twice.) I consider that fair because, even if some initial mould was the result of factors not covered under the policy, the insurer was on notice of the existence and spread of mould while the claim was being assessed and investigated. I consider it should reasonably have been more proactive and thorough in dealing with that, and with the other aspects of its initial make-safe (such as the adequacy of the tarps on the roof) in the absence of which, further water ingress occurred and the mould was allowed to increase. The insurer is required t o obtain reasonable quotes for that work identified in FEN’s report , and cash settle the complainants the respective costs, increased by 15% to reflect the transfer of risk, to cover contingencies, and to ensure the amount would be sufficient for the complainants, as retail customers, to have the work completed themselves. Insurer to contribute to damaged contents The complainants believe the insurer should pay the full sum insured for their damaged contents ($84,000). The policy defines ‘contents’ as ‘ household items used primarily for domestic purposes. Contents are items which are generally not permanently attached to the building’. To be clear, carpets are excluded from cover as part of the ’building’, and so form part of the contents. As noted above, the insurer had suggested to the complainants that they had the choice whether or not to remove contents items from the property once it became clear that mould was spreading. I also note CG had commented (when they attended on 8 March) that there was not a large amount of contents in the property, since the complainants were currently Determination | Case number: 887989 Page 7 of 9 undertaking renovation work. The photographs provided by the various parties, however, do show a considerable amount of contents items (from kitchen utensils, to furniture and artwork). It is not clear what, if any, contents the complainants removed from the property when it first became clear that mould was starting to affect them (and when that was presented as an option by the insurer). I consider the complainants should reasonably be held at least partly responsible for loss and damage suffered as a consequence of not removing contents before the mould progressed. However, I also consider the insurer’s handling of the matter may have confused the complainants about what it might be prepared to cover. For example, t he insurer’s claim file notes show the insurer told the complainants to throw out mouldy contents but keep photos as evidence of what was lost/damaged. At the same time, that does not mean the complainants should simply have left items in the house to suffer further damage. In their 20 June 2022 report, restorer FEN indicated a contents assessment and inventory needed to be completed. The complainants have provided a number of photos showing damaged contents, however I have not seen a comprehensive or detailed list of items or values. The parties should work together to compile a list of damaged contents and corresponding values (as detailed as possible in the circumstances). I consider it fair that the insurer then contributes half the reasonable value of the damaged contents. I note the complainant has already provided certain quotes, including for carpet, which may assist in that process. To be clear, even though the insurer is not strictly liable under the terms of the policy for the damaged contents (because the initial claim and damage was not from an insured event), I consider the way it mishandled the make-safe (including inadequacy of the tarp on the roof, which allowed further water to enter the already compromised building, and delays in progressing the matter) led to further avoidable damage. Insurer provided adequate temporary accommodation The policy provides cover for reasonable and necessary temporary accommodation costs for the time it will take to repair or rebuild the building so that it can be lived in again. This benefit is payable when the insured is covered for loss or damage to the building to the extent it cannot be lived in. The available evidence shows the property could not be lived in (given the presence of mould, amongst other issues). Whilst this section of the policy indicates temporary accommodation will only be provided in the case of an accepted claim, it is reasonable for temporary accommodation to be provided until a final claim decision is reached, when a property is not safe for occupation. The insurer has paid approximately $60,000 in temporary accommodation to suitably house the complainants while it was assessing and determining the outcome of the claim. There was some back and forth regarding potentially obtaining and placing a caravan on the property. However, the insurer continued to provide temporary accommodation away from the property. I acknowledge the complainants have issues with the number of properties they needed to reside in and the inconvenience this caused, pending the final claim decision. However, I am Determination | Case number: 887989 Page 8 of 9 satisfied the insurer provided an adequate level of accommodation for the complainants in the circumstances. It is not required to pay anything further for accommodation. 2.3 Are complainants entitled to an award of compensation? AFCA can award non-financial loss compensation Under its Rules, AFCA can award non-financial loss compensation if there has been an unusual degree or extent of inconvenience caused by an error of the insurer. This inconvenience can include physical inconvenience, general time taken to resolve the claim and the extent to which the insurer’s actions interfered with the complainants’ expectation of enjoyment or peace of mind. However, AFCA takes a conservative approach to awarding this type of compensation and expects complainants to accept a normal degree of inconvenience associated with a claim. Compensation warranted in the circumstances I acknowledge the claim necessitated engaging multiple trades including builders, plumbers, engineers and restorers, all during in a high claim period due to significant weather events. However, the insurer could have dealt with the make-safe and mould remediation more thoroughly and more proactively, particularly given the recommendations from their experts. There was a level of miscommunication and unclear instructions, resulting in the property being left closed up for an extended period without appropriate drying and attention. This caused significant distress to the complainants who were witnessing the expanding mould growth, and receiving unclear advice as to what would occur. This also, not unreasonably, prompted the complainants to engage their own trades to deal with certain work. As well, the insurer’s handling of the engagement of the engineer caused an unnecessary delay and further inconvenience to the complainants. The reports provided earlier in the claim by R and the internal assessor confirmed an engineer was required to assess the slab movement at the rear of the property. The insurer failed to arrange for an engineer to attend within a reasonable timeframe after these reports were received. This caused further delay in providing a final claim decision. All that occurred at a time when the complainants were already experiencing considerable upset and uncertainty about their home and their future. The insurer is required to pay the complainants $2,000 in non-financial loss compensation. 2.4 Why is the outcome fair? It would not be fair to require the insurer to cover a claim when the evidence does not show the damage was the result of a single insured event, but was instead from excluded factors. At the same time, however, it is fair that the insurer be responsible for additional costs incurred, and upset and inconvenience experienced by the complainants because of the insurer’s handling of the matter. Determination | Case number: 887989 Page 9 of 9 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.