Determination 887222

Delay in completing home repairs after accepted water damage claim; refusal to pay loss of rent and temporary accommodation

FirmIAG
Decided2023-07-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$21,857
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The complainant's home was damaged by a water leak and repairs were completed about 11 months late. AFCA rejected further temporary accommodation costs but ordered the insurer to pay rental loss, interest and $3,000 non-financial loss.

The insurer's unexplained repair delay breached the utmost good faith duty under section 13 of the Insurance Contracts Act, so it could not rely on the rental loss requirement under section 14.

Issues

Subjects and remedies

home or building damagepay compensationpay interestpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 887222 Financial firm Insurance Manufacturers of Australia Pty Ltd Determination | Case number: 887222 Page 2 of 8 Case number: 887222 17 July 2023 1 Determination overview 1.1 Complaint The complainant’s home was significantly damaged by a water leak while she was away on holidays. She discovered the damage on her return and lodged a claim with the financial firm (insurer) on 8 February 2022. The insurer accepted the claim, authorised repairs, and provided the complainant with temporary accommodation for a while. However, disputes arose around the insurer’s :  claims handling and delay in completing the home’s repairs  refusal to pay compensation for temporary accommodation after 4 March 2022  refusal to pay compensation for loss of rent. 1.2 Issues and key findings Must the insurer pay more for temporary accommodation? No. The complainant has not incurred temporary accommodation costs after 4 March 2022. Must the insurer pay any other compensation? Yes. The insurer failed to repair the home in a timely manner and consequently, failed to act with utmost good faith towards the complainant. This deprived her of a fair opportunity to earn rental income and caused her unusual delay, inconvenience and interference. Given this, it would not be fair or consistent with an obligation to act with utmost good faith for the insurer to refuse the complainant compensation for rental loss and her poor claims experience. Why is the outcome fair? The insurer’s failure to act with utmost good faith caused the complainant rental losses. It also caused her unusual delay, inconvenience and interference. Given this, it is fair the insurer compensates the complainant for rental losses and for her poor claims experience. 1.3 Determination This determination is in favour of the complainant. Within 14 days of being notified of the complainant’s acceptance of this determination, t he insurer is to pay her:  $21,857.14 for the rental losses it caused her  interest on the above amount under section 57 of the Insurance Contracts Act 1984 (the Act) from 20 April 2023 until she receives her compensation  $3,000 as compensation for non-financial loss. Determination | Case number: 887222 Page 3 of 8 2 Reasons for determination 2.1 Must the insurer pay more for temporary accommodation? No. The complainant has not incurred temporary accommodation costs after 4 March 2022. No dispute insurer has accepted complainant’s claim There is no dispute the complainant’s home sustained extensive damage from a water leak in or around early February 2022 and this rendered the home unliveable. There is also no dispute the insurer accepted the complainant’s claim and authorised repairs. The insurer also accepted the complainant was entitled to temporary accommodation, which it says was provided and available to her until 29 July 2022. Complainant says insurer must still pay for accommodation after 4 March 2022 The complainant says the insurer did not provide her with temporary accommodation until 29 July 2022 as it claimed. She says the insurer only provided her with temporary accommodation until 4 March 2022. The complainant says she made her own accommodation arrangements after 4 March 2022. Notwithstanding this, she says the policy entitles her to temporary accommodation for the duration of her home’s repair. Therefore, the insurer must pay her compensation for temporary accommodation until her home is repaired. Complainant has not incurred accommodation costs after 4 March 2022 The relevant policy terms about temporary accommodation are set out in section 2.1 of this determination. I accept these terms entitle the complainant to temporary accommodation. However, the complainant must show she continued to incur temporary accommodation costs after 4 March 2022 for the policy to continue providing this benefit. The complainant has not shown this. I understand the complainant and her representative were about to get married at the time and had bought another property together. I also understand the complainant had lived at this property after 4 March 2022. Since the complainant has not continued to incur temporary accommodation costs after 4 March 2022, there is no requirement for the policy to respond in this instance. Determination | Case number: 887222 Page 4 of 8 2.2 Must the insurer pay any other compensation? Yes. The insurer failed to repair the home in a timely manner and consequently, failed to act with utmost good faith towards the complainant. This deprived her of a fair opportunity to earn rental income and caused her unusual delay, inconvenience and interference. Given this, it would not be fair or consistent with an obligation to act with utmost good faith for the insurer to refuse the complainant compensation for rental loss and her poor claims experience. Complainant says insurer ’s repair delays caused rental loss The complainant says the insurer has unreasonably delayed her home ’s repair. She says the repair was supposed to be completed within four to six weeks, but this did not happen. In a 16 May 2023 submission, she explained: At the latest conversation, [I] was informed repairs would be completed by 28/4/2023. The [insurer] notified [me] via phone call that an electrical fit off needed to occur and once that was complete, they needed to engage [S] to put the furniture back in place. [I] went to the property on 4/5/2023 and the furniture was not back in place. Further, the sink the builder said would be replaced due to accumulating a lot of mould being stored in the house with water damage, was not replaced. It was put back in. It is plastic and the mould is ingrained in it. It appears to have had a surface clean. There has been no further communication from the builder or the insurer to confirm the works are complete. (sic) The complainant says th e insurer’s failure to complete her home repair in a timely manner prevented her from renting out her home. She explained she was already planning to do this before the claim as she was about to get married and had bought another home with her partner. She says she told the insurer this early into the claim and supplied it with a rental appraisal. She denies ever telling the insurer’s builder she was intending to sell the property. Insurer says complainant is not entitled to loss of rent The insurer has not responded to the complainant’s complaints about the delays in the home ’s repair or its claims handling, other than saying the repair was completed on 20 April 2023. The insurer only responded to her complaint about rental loss, which it says she is not entitled to. It says her home was owner-occupied at the time the claimable loss occurred and the policy only covers rental loss if it was already rented out at then. The insurer further says the complainant:  did not disclose (or provide documents to show) she would be renting out the home  told its builder (JF) that she was intending to sell the home. Complainant has not strictly met the policy’s rental loss requirements The relevant policy terms about rental loss are set out in section 2.1 of this determination. I accept the complainant has not strictly met the requirements to claim rental loss benefits under these terms. Based strictly on the policy terms, her home must have already been leased out when the claimable loss occurred. There is no dispute the home was still owner- occupied when the claimable loss occurred. Determination | Case number: 887222 Page 5 of 8 Utmost good faith requires insurers to resolve claims in a timely manner However, section 13 of the Act says it is an implied term of an insurance contract that parties are to act with utmost good faith towards each other. Case law also recognises that an insurer would breach section 13 of the Act if it fails to resolve a claim in a timely manner, like, completing a home ’s repair in a timely manner. Section 14 of the Act further says an insurer can be prevented from relying on a provision of an insurance contract, if to do so would mean the insurer fails to act with utmost good faith Insurer has failed to act with utmost good faith towards complainant The exchanged information shows the insurer’s builder JF:  issued its assessment report and scope of works on or around 18 March 2022  estimated repairs would take about 4-6 weeks to complete. Allowing the insurer say three weeks (i.e. 21 days) from 18 March 2022 to finalise its assessment, decision, and organise repairs to begin, I consider the home ’s repair should have begun by 8 April 2022 . This means the home’s repair should have been completed by 20 May 2022 based on a six-week repair timeframe. There is no dispute the home’s repair was not completed by then. The insurer’s 21 September 2022 email outlined a list of repairs that remained outstanding as at September 2022 . This included an ‘electrical fit off’ which the complainant says was still not done at the time of her AFCA complaint. The insurer says the home’s repair was completed on 20 April 2023, which the complainant has since acknowledged. However, the insurer has not given any explanation why the repair was only completed that day, 11 months after when it should have ordinarily been completed. I note the insurer informed the complainant on 21 March 2022 that its builders were ‘spread very thin at moment due covid and weather event’. However, i t has not provided any information to substantiate that the home’s repair was in fact delayed because of such matters. Its submissions to AFCA also does not appear to address or explain the delays. Without any reasonable explanation for the delay, I can only conclude there was no reasonable basis for it. Given this, I am satisfied the insurer had failed to act with utmost good faith towards the complainant and breached section 13 of the Act. Not consistent with utmost good faith for insurer to refuse rental loss claim I am also satisfied it would not be fair in all the circumstances or consistent with the insurer’s obligation to act with utmost good faith for it to refuse the complainant’s rental loss claim. The complainant has acted fairly and reasonably by moving into another home she had purchased. This saved the insurer from further exposure to temporary accommodation cost. The complainant also gave the insurer notice several times that she was intending to rent out her home once repairs were complete. The insurer’s claim notes show she first mentioned this even before repairs began. The relevant 28 February 2022 note says: [The complainant] called temp accommodation will expire 04/03/2022 she needs just one more night and she will be moving into a new house. has sent a letter rental appraisal [complainant] was intending to put the property on the market for rent when she moved out She is getting married and settling on another property Determination | Case number: 887222 Page 6 of 8 and moving out of the current property. Due to the incident she cannot yet get tenants into the property and does not have a signed leased [complainant] has had to hold off advertising and letting the property … (sic) Given this, I accept the insurer was clearly on notice of the complainant’s intention to rent out her home. I also accept it was reasonable for the complainant to expect that it would complete her home’s repair within the 4- 6 weeks’ timeframe JF identified. The insurer failed to do this without reasonable basis, and this unfairly deprived the complainant of fair opportunity to earn rental income from her home. Given this, it would not be fair for the insurer to rely on the policy’s r equirement that the home must have been leased out before the claimable loss occurred. It would also be inconsistent with its obligation to act with utmost good faith if the insurer is allowed to do so. I am satisfied the insurer must compensate the complainant for the lost opportunity to earn rental income from her home. Insurer ’s repair delays caused complainant $21,857.14 in rental losses As noted earlier, my calculations indicate the home’s repair should have been completed by 20 May 2022 based on a six-week repair timeframe. Allowing say 30 days from then for the home to be rented out, I consider the home should have been rented out by 19 June 2022. There are 306 days between 19 June 2022 and 20 April 2023 (both dates inclusive). The complainant has provided rental appraisals showing her home could be rented out between $450 and $550 a week. The insurer has not disputed these amounts. Taking the average (i.e. $500), I am satisfied the insurer’s repair delays have caused the complainant $21,857.14 in rental losses up to and including 20 April 2023 [i.e. ($500 x 306 days)/7]. I am satisfied the insurer must compensate the complainant this amount. Insurer is to compensate complainant for rental losses and non-financial loss I am also satisfied the insurer must pay interest under the Act on this amount. Interest is to run from 20 April 2023, the date repairs were finally completed, until the complainant receives her compensation. It is also fair that the insurer pays the complainant $3,000 as compensation for non-financial loss. This is to account for the unusual delay, inconvenience and interference caused by its failure to meet its repair commitment to her in a timely manner. Determination | Case number: 887222 Page 7 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairnes s AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. 3.2 Relevant policy wordings Other benefits … Loss of rent for landlords … If a listed event causes loss or damage to your home and your tenants are unable to live in your home and need to move out so it can be repaired or rebuilt. We pay this benefit on top of your Buildings sum insured. Covered under Buildings Insurance  the rent you lose during the reasonable time it should take to repair or rebuild your home for up to 12 months from when the listed event took place. Not covered  if you or your family live in your home. … Temporary accommodation for home owners … If a listed event causes loss or damage to your home and you are unable to live in your home and you need to move out so it can be repaired or rebuilt. We pay this benefit on top of your Buildings sum insured. Covered under Buildings Insurance We pay these costs for the reasonable time we agree it should take to repair or rebuild Determination | Case number: 887222 Page 8 of 8  costs for temporary accommodation that we agree are reasonable and appropriate for you, your family and your pets that you normally keep at your site  any additional living expenses that we agree are appropriate  costs to remove and store your contents and then retur n them to your home. your home for up to 12 months from when the listed event took place … How we settle your buildings claim We will choose to settle your claim for loss or damage to your home or ‘other benefits’ in one of the following ways. Our choice will have regard to the circumstances of your claim and consider any preference you may have. 1. Arrange for repairers, builders or suppliers to repair or rebuild your home. 3.3 Relevant case law considered Australian Securities and Investments Commission v Youi Pty Ltd [2020] FCA 1701