Home / Suncorp Group / Determination 883621

Determination 883621

Earthquake damage claim declined by insurer

FirmSuncorp Group
Decided2023-01-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed under home and contents insurance for earthquake-related cracking damage to his property after the insurer's assessor recommended an engineer's causation report. The engineer attributed the damage to long-term differential foundation movement, and AFCA found the insurer entitled to deny the claim.

The complainant bears the onus of establishing that earthquake damage occurred, and the insurer's engineering evidence, together with the general exclusion for ground movement, was not displaced.

Issues

Subjects and remedies

no remedy

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 883621 Financial firm AAI Limited Determination | Case number: 883621 Page 1 of 6 Case number: 883621 30 January 2023 1 Determination overview 1.1 Complaint The complainant held a home and contents insurance policy with the financial firm (insurer). In October 2021 he lodged a claim, following an earthquake. The insurer assessed the claim and following the assessor’s statement that the damage may have been caused by an earthquake, appointed an engineer to determine the matter. The engineer rejected the claim on the basis that the damage was a result of differential settlement of the foundations of the building. This matter has been the subject of a preliminary assessment which is in favour of the insurer. The complainant rejects this, and the matter has been referred for determination. 1.2 Issues and key findings Why the insurer entitled to deny the claim? On the information provided to me, on balance, I am satisfied as follows:  the assessor (PB) accepted there was possible earthquake damage, but an engineer should be appointed  the insurer’s engineer (M) found that the damage was because of differential settlement of the foundations of the building and not earthquake  the complainant holds an insured events policy including earthquake  nothing has been provided which disputes the engineer’s finding. On the information provided I am satisfied that the insurer is entitled to deny the claim. It is noted that damage to a ceiling in the wardrobe was reviewed under a separate claim with the insurer agreeing to cover the costs of repairing for the damage. This claim has not been dealt with in this determination. Why is the outcome fair? The complainant has been given the opportunity to address all matters raised by the insurer. Whilst I accept that PB did consider the possibility of the damage being related to the earthquake he also recommended that an engineer be appointed to provide a causation report. Whilst the complainant may have considered that this indicated the damage was earthquake related, the engineering report rejects this. The insurer has accepted other damage not the subject of this claim. In the circumstances it would be unfair to require the insurer to compensate the complainant. 1.3 Determination This determination is in favour of the insurer. The insurer is not required to undertake any further action. Determination | Case number: 883621 Page 2 of 6 2 Reasons for determination The complainant holds home and contents insurance with the insurer. Following an earthquake, a claim was lodged in October 2021 in relation to cracks at the property. The insurer assessed the property which indicated that the damage observed was consistent as a result of the earthquake , however, recommended that an engineer’s opinion should be obtained. The engineer did not support the claim on the base of an earthquake. The insurer rejected the claim. 2.1 Was the insurer entitled to deny the claim? Onus on complainant The complainant must establish, on balance of probabilities, that he suffered a loss caused by an event to which the policy responds this is as known as a prima facie or valid claim. The complainant’s policy provides cover for loss or damage caused by listed events. Included in listed events are earthquake. If the complainant can establish a valid claim the responsibility is then on the insurer to show that an exclusion applies. It is therefore up to the complainant to establish in the first instance that earthquake damage occurred to the property. Product Disclosure Statement (PDS) The insurer has referred to the PDS as follows: ….. Determination | Case number: 883621 Page 3 of 6 Expert Reports The insurer initially obtained a report from an assessor (PB). PB recommended: ‘ An engineer be appointed to provide Causation Report on possible earthquake damage to the insured’s property, and a repair SOW should resultant damage be identified.’ SOW is an abbreviation for Scope of Works. PB obtained the information by a site visit on November 4, 2021. The insurer appointed an engineer (M). M attended the property on 11 February 2022 and provided a report with large number of attached photographs of damage. M dealt with the issues in relation to the earthquake and stated: ‘Had 22 September 2021 earthquake event caused or contributed to the cracking damage to the house, we would have expected to observe more wide spread damage to the walls on the building throughout, and not predominantly confined to the few locations observed during the inspection.’ M referred to Geosciences Australia website and in particular to the shaking intensity map. M stated that the earthquake event was light in the area that the complainant lived. And stated: ‘Li ght ground vibrations from an earthquake would not, in our opinion, cause the damage to the building, as observed during our site inspection.’ M then dealt with the issue of differential foundation soil movements. M noted that part of the cracking damage due to vibrations from earthquake most commonly present as clean and sharp and are of a jagged appearance. He noted that the internal cracking observed which were generally occurring in straight lines indicated the cracks extend along common crack propagation routes. Determination | Case number: 883621 Page 4 of 6 He also noted that multiple cracks observed to the cornices presented signs of previous repairs which he said further indicated that long term and ongoing movement-related cracking has occurred to the building. He also noted that there was no indicated movement to the roof tiles above the area in the walk-in robe which had sustained ceiling. M came to the conclusion: ‘In our opinion, the damage observed to the building has not been caused or contributed to by the earthquake event on 22 September 2021, or any other single definable event. It is M opinion that the approximate cause of the cracking and movement – related damage to the building is due to the combination of long-term and ongoing differential foundation movements due to underlying reactive soils and long-term thermal building movements. ’ Insurer entitled to deny claim The complainant says that the assessment report confirmed the damage was consistent with a new earthquake and that ground movements is what happens with earthquakes. Whilst I accept the complainant may have been confused by the initial statement by the PB, I am satisfied by reading the report that PB provided an initial assessment but, as stated in the report this was subject to a final determination being undertaken by an engineer to determine the causation. The report by M dismisses the causation being the earthquake and instead refers to long- term and ongoing differential foundation movement. Whilst the policy provides coverage for earthquake I am not satisfied that the complainant has established that the earthquake caused the damage and I have taken into account both reports provided by the insurer in making this assessment. The PDS provides cover for damage to the building caused by landslides or substance proved occurred in 72 hours. However, the general exclusions under the policy exclude ground movement including shrinkage or other ground movements. On the information provided, on balance, I am not satisfied that the complainant has been able to show that the damage was caused by events which are included under the policy. The insurer has provided sufficient information to show that, on balance, the earthquake did not cause the damage and further that the engineer’s report has strongly confirmed this. In the circumstances the insurer is entitled to deny the claim. 2.2 Why is the outcome fair? The complainant has been given the opportunity to address all matters raised by the insurer. Whilst I accept that PB did consider the possibility of the damage being related to the earthquake he also recommended that an engineer be appointed to provide a causation report. Determination | Case number: 883621 Page 5 of 6 I have considered the provisions of the policy and nothing the complainant has raised convinces me the damage to the property was caused by the earthquake. I am satisfied that PB’s report required the engineer to further examine the property. The engineer rejected the damage as earthquake related. The insurer has accepted other damage not the subject of this claim. In the circumstances it would be unfair to require the insurer to compensate the complainant. Determination | Case number: 883621 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.