Determination 883079

Insurer's settlement of machinery breakdown claim by compressor replacement rather than full unit replacement

FirmHollard
Decided2023-01-05
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant in part
Amount awarded$5,688
Non-financial loss—
Amount claimed$11,220
SourceAFCA PDF

Summary

The complainant's business air conditioner compressor burnt out and he replaced the whole unit at a cost of $11,220, then sought full replacement cost from the insurer, which had offered the cost of the compressor. AFCA decided the unit could have been repaired and the insurer's liability is limited to the damaged parts, but required it to add a 20% contingency to its $4,740 estimate.

The policy limits the insurer's liability to the cost of repairing or replacing the damaged machinery parts where replacement parts are available, and full unit replacement was a mitigating step driven by age rather than the damage.

Issues

Subjects and remedies

business interruptionhome or building damagepay claim

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 883079 Financial firm The Hollard Insurance Company Pty Ltd Determination | Case number: 883079 Page 1 of 4 Case number: 883079 8 December 2022 1 Determination overview 1.1 Complaint The complainant lodged a claim with the financial firm (insurer) under his business insurance policy. This is for the damage sustained to the air conditioner unit. The insurer accepted the claim and offered the complainant the cost of the compressor’s replacement being the damaged part. The complainant disagrees and seeks the replacement of the air conditioner unit. 1.2 Issues and key findings Is the insurer liable for the replacement of the unit? No. The exchanged information shows, on balance, the air conditioner unit could have been repaired as the replacement of the damaged parts was available. The insurer is required to add 20% contingency to its offer. 1.3 Determination This determination is in favour of the insurer. Within 14 days of the insurer receiving notification the complainant accepts this determination, the insurer is required to pay the complainant $5,688 (excluding GST)  $4,740 for the replacement of the damaged parts  plus $948 being 20% contingency for the transfer of risk  less policy deductibles. Determination | Case number: 883079 Page 2 of 4 2 Reasons for determination 2.1 Is the insurer liable for the replacement of the unit? No. The exchanged information shows, on balance, the air conditioner unit could have been repaired as the replacement of the damaged parts was available. The insurer is required to add 20% contingency to its offer. There is no dispute the air conditioner unit is damaged There is no dispute:  the air conditioner ’s compressor has burnt out  the complainant established a valid claim under the terms and conditions of the policy  the complainant lodged the claim after he replaced the unit  the complainant paid $11,220 for the replacement of the entire unit. The complainant says he followed his technician’s advice and replaced the unit. This is due to the age and state of the unit. The insurer says the compressor could be successfully replaced and this settlement method is in line with the policy. The exchanged evidence shows the original compressor is no longer available however there is a generic replacement compressor available. This is consistent with the complain ant’s technician (LC) findings. I note the insurer’s policy outlines how the claim should be settled. The insurer’s policy states the insurer will pay the cost to repair or replace the damaged machinery. Further, if the damaged replacement part is unavailable, the insurer will not pay more than the cost of the similar parts which are available at the time. I note the Machinery Breakdown sum insured shown on the policy is $10,000. The insurer is required to increase its offer by 20% The co mplainant’s main argument is that the unit should be replaced as suggested by LC. In his letter, LC says the compressor can be replaced. However, LC recommends the replacement of the air conditioner unit on the basis  the air conditioner is old  it is commercially viable to replace the air conditioner rather than maintain the old unit  other parts of the unit might fail given its age. I am satisfied the evidence shows the unit required replacement due to its age, condition and location rather than the nature and extent of the damage. I consider the replacement of the entire unit is a mitigating step by the complainant given the age of the unit. Having reviewed the exchanged evidence, I am satisfied the insurer is liable for the replacement of the compressor. The insurer’s assessor (ST) estimated the replacement of the damaged parts to be $4,740 (excluding GST). The insurer is required to add another 20% contingency given the quote is not an actionable quote. Within 14 days of the insurer receiving notification the complainant accepts this determination, the insurer is required to pay the complainant $4,740 plus $948 being 20% contingency for the transfer of risk totalling $5,688 (excluding GST) less policy deductibles. Determination | Case number: 883079 Page 3 of 4 2.2 Why is the outcome fair? The insurer is entitled to rely on the policy wording to establish the extent of its liability. The policy limits the insurer’s liability to the damaged parts. Determination | Case number: 883079 Page 4 of 4 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.