Home / Suncorp Group / Determination 882088

Determination 882088

Claim denial for water ingress damage to business premises after February 2022 weather event

FirmSuncorp Group
Decided2023-05-02
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for flood and storm water damage to two business premises after a February 2022 weather event, and the insurer denied the claims as flood damage excluded by the policy. AFCA found the properties were mainly inundated by flood and upheld the denial, but ordered the insurer to assess stock and contents damage up to 100mm at one property under its earlier offer.

Under the policy, the storm cover excludes flood, and the complainant bears the onus to show damage falls within cover; expert evidence showed the initial and peak inundation was caused by floodwater overflowing from a creek.

Issues

Subjects and remedies

business interruptionhome or building damagenatural disasterreassess claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 882088 Financial firm AAI Limited Determination | Case number: 882088 Page 1 of 6 Case number: 882088 4 April 2023 1 Determination overview 1.1 Complaint The complainant holds a business insurance policy with the financial firm (insurer). A claim was lodged for loss and damage after two of his business premises were inundated during a significant weather event in February 2022. The insurer denied the claims relying on hydrologist reports. The insurer says the cause of damage was flood which is excluded from cover under the terms of the policy. Since bringing the complaint to AFCA, the insurer offered to cover 100mm at the rear lowest section of the building surrounding the toilet area. This offer relates solely to property (SG). The complainant says the water that initially inundated his properties was rainwater-run off before mixing with the flood waters. 1.2 Issues and key findings Is the complainant entitled to cover for storm related damage? No. On balance the evidence shows the properties were initially inundated by flood water coming out of the drainage system nearby the properties. Damage caused by flood is excluded under the policy and the insurer is entitled to deny the claims. However, it is fair the insurer honours its offer to cover the lower level of property SG, up to 100mm, consistent with its offer made via email. The insurer is otherwise entitled to rely on the terms and conditions of its policy to deny liability for the remainder of the damage claimed. 1.3 Determination The determination is in favour of the insurer. Within 14 days of the complainant’s acceptance of this determination the insurer must:  Assess and determine the extent of damage to stock and contents at the level 100mm at the rear lowest section of the building surrounding the toilet area at property SG. The insurer is otherwise entitled to rely on the terms and conditions of the policy to deny liability for the balance of the damage claimed. Determination | Case number: 882088 Page 2 of 6 2 Reasons for determination 2.1 Is the complainant entitled to cover for storm related damage? No. The panel is satisfied both properties were initially inundated due to the nearby BC overflowing the stormwater drainage network. The insurer, however, offered to cover the lower level of property SG. It is fair it does so. Complainant has the onus to establish valid claims It is established insurance law that the complainant has the initial onus to prove, on the balance of probabilities (that is, more likely than not), that the loss or damage claimed falls within the terms of the policy. This is commonly called a valid claim. On 28 February 2022, the first claim was lodged for property GC and on 7 March 2022, a second claim was lodged for property SG, for water ingress damage to stock, contents and claims for business interruption. Under policy section 1- property damage, the policy confirms that it covers accidental damage. However, this is subject to a sub limit of $250,000 and does not cover loss or damage caused by any of the insured events (1 to 10) listed in the policy and their relevant exclusions Therefore, the relevant section for consideration is under insured event 5, which provides cover for storm, wind and rain (including snow, sleet or hail). This includes run-off of rainwater that accumulates directly on and flows across normally dry ground or that overflows from public roadside gutters, channels and drains that are normally dry or swimming pools, spas or saunas. Under the event storm, the policy specifically excludes loss or damage caused by flood, unless otherwise covered by a specific endorsement. The policy defines flood to mean: The covering of normally dry land by water that has escaped or been released from the normal confines of any of the following(sic): ▼ a lake (whether or not it has been altered or modified); ▼ a river (whether or not it has been altered or modified); ▼ a creek (whether or not it has been altered or modified); ▼ another natural watercourse (whether or not it has been altered or modified); ▼ a reservoir; ▼ a canal; or Determination | Case number: 882088 Page 3 of 6 ▼ a dam.. The complainan t’s COI confirms that flood cover was not selected, and the complainant has not disputed this. Policy section 5 provides cover for business interruption. Cover for business interruption requires a valid claim to be made under policy section 1 for property damage. The onus is therefore on the complainant to establish that the loss or damage claimed falls within the cover provided under the policy. The panel will consider below whether the insurer is liable for each of the claims at property SG and property GC. Property SG ’s initial inundation caused by flood Both parties provided expert reports and the complainant provided a video specific to the property at SG, which he says shows rainwater first entered the property. The insurer ’ s hydrologist (WR) concluded the initial inundation above floor level:  Was caused by floodwater from BC flowing back up the stormwater pipe network to GC Street.  the peak inundation of the subject property, to a maximum depth of about 1.7 m above the car park ground level and about 1.12 m above floor level at the front of the property SG, was caused by floodwater overflowing from BC. WR relevantly explained:  Based on a car park ground level of about 1.7 mAHD, a 0.3 m step up to the ‘middle’ floor level and a 0.11 m step up to the ‘front’ f loor level, the floor levels are estimated to range from 1.7 mAHD at the rear of property SG to about 2.1 mAHD at the front of property SG.  The topographic data shows that water from BC would overtop SG Road between P and W streets and overflow to the surrounding low-lying areas once water levels in BC reached about 1.5 mAHD. From about 2.0 mAHD, water overflowing from BC between P and W streets would overflow directly to property SG from the south.  Property SG was inundated to a peak depth of approximately 1.7 m above ground level in the car park (measured at one of the shipping containers), and about 1.12 m above floor level at the front of property SG (measured at the front door).  Peak BC levels of approximately 4.6 mAHD and 2.7 mAHD were recorded at around 2038 hours on 27 February and 0804 hours on 28 February, at the B Hills and BC mouth gauges respectively.  The peak one-hour rainfall intensity of 68 mm/hr occurred in the hour to 1344 hours on 27 February.  Rainfall severity is described as an annual exceedance probability (AEP) which is the probability that a given rainfall total over a given duration will be exceeded in any one year.  For durations from 5-minutes up to 3 hours, recorded rainfalls had AEPs in the range of 37.2% (1 in 2 AEP) to 3.73% (1 in 26 AEP).  Longer duration rainfalls were much more severe, with AEPs up to 0.13% (1 in 749 AEP). The complainant exchanged a video taken at 1:08pm on 27 February 2022, which he says provides conclusive evidence that rainwater entered property SG prior to the BC breaking its banks. He says that this also coincides with the peak rainfall intensity recorded. Determination | Case number: 882088 Page 4 of 6 The complainant also exchanged a report from his expert HD. However, the panel is not persuaded the detail in this report is as extensive as the insurer ’ s report. HD, in summary, has explained the possibility that stormwater runoff entered the property first, however, having considered all the data the panel is satisfied WR has explained its position in more detail with supporting data confirming what has occurred. The panel is satisfied WR has shown in its findings that the creek water coming up through the storm water drainage had already begun to pool on the ground and thus it was a mix of rainwater and floodwaters from BC. WR relevantly explains:   Water from BC backflowing up the stormwater pipe network would mix with any stormwater in GC Street that was prevented from draining freely by elevated creek water levels.  From about 1.5 mAHD, water from BC would overtop SG Road between P and W streets and overflow to the surrounding low-lying areas. From about 2.0 mAHD, water from BC would overflow directly to property SG via the overflow location between P and W streets, as well as via the area of low ground to the south.  Debris marks on fencing along BC at SG Road in the vicinity of the property confirm that BC did overtop its banks (and SG Road) during the event.  Recorded water level data shows that BC water levels at the property would have been high enough to surcharge to GC Street via the stormwater pipe network, during each high tide cycle from Saturday 26 February. This receding tidal influence explains the direction of flow observed in the video of 1.08pm on 27 February.  WR concluded that although the minimum property SG floor level (1.7 mAHD) is below the level at which BC would overflow directly to property SG (2.0 mAHD), local stormwater runoff alone would not have been sufficient to inundate property SG above floor level because:  Recorded short duration rainfall intensities, that would produce the most significant local stormwater runoff response, were not severe during the event.  BC water levels at the property would have been high enough to surcharge to property SG via GC Street from about 0600 hours on 26 February. This is more than 24 hours before the period of most intense rainfall and recorded rainfall intensities at this time were not severe. In relation to the FVC type stormwater manhole at GC street, WR advised, the presence of the FVC at GC Street did not cause it to alter its findings regarding the initial and maximum above floor level inundation at property GC. However, WR advised that the presence of the FVC at GC Street did cause it to revise its findings regarding property SG as follows:  it is possible that local stormwater runoff, which was prevented from draining away by creek floodwaters, could have accumulated to a maximum level of about 1.9 mAHD (about 0.2 m above ground level) in the low areas of the property SG car park;  local stormwater runoff alone would not have been sufficient to cause above floor level inundation of the ‘middle’ and ‘front’ areas of the building;  Initial above floor level inundation of the ‘middle’ and ‘front’ areas of the building, as well as the maximum inundation at the property, was caused by floodwater overflowing from BC. Determination | Case number: 882088 Page 5 of 6 The panel is persuaded by WR ’s report which has shown on balance that floodwater had overflowed the stormwater drainage and into the street once it exceeded 1.5 mAHD and this initially occurred on 26 February 2022, at approximately 0600. The rainfall intensity indicates the event was prolonged and was unlikely to cause significant stormwater run-off. Rather, it was the prolonged rain that contributed to the creek overflowing the drainage network. This also occurred well before the peak rain fall at the time recorded by the complainant at 0108 hours on the 27 February 2022. T he panel accepts WR’s view that the video show s BC had already topped its banks and was level with the stormwater runoff around property SG at this time. The panel is satisfied the rainwater run off at this time had already mixed with the flood waters coming up through the stormwater system as explained by WR. WR has also explained there is not a floodgate installed within the stormwater network and HD has not provided any persuasive evidence to overcome this. On the other hand, the panel notes the insurer made an offer via email of: We provide acceptance for storm water ingress up 100mm at the rear lowest section of the building eminently adjoining the carpark, predominantly around the toilet area only. It is believed that any contents/stock in this area would be above floor level and affected by storm water ingress up to 100mm. Whilst the panel is satisfied the available evidence shows all damage was most likely caused by a mix of flood and storm water (flood), it is fair the insurer honours this offer and assesses its liability for stock and contents for this section of damage to property SG. Outside of this the insurer was correct in denying the claim on the basis the damage to property SG was caused by floodwater arising through the stormwater network outside of BC. Property GC ’s inundation caused by flood The panel is persuaded property GC was damaged by flood waters only. WR concluded the following:  Some water may have entered property GC through the roof. However, this does not appear to have caused any damage on the upper level of property GC.  The initial and peak inundation of property GC, to a maximum depth of about 0.7 m above the ground floor level was caused by floodwater overflowing from BC.  Property GC’s floor level is estimated to be between about 2.5 mAHD to 2.6 mAHD. The evidence does not support rainwater runoff entered the property GC which sits much higher than SG Road. Rather, property GC was initially inundated by flood water from BC. The insurer has established flood was the proximate cause of damage to the property GC and is entitled to deny the claim in its entirety for this property. Given the complainant has not established a claim for property damage under the policy, the insurer is also entitled to deny the claim for business interruption. Determination | Case number: 882088 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with significant experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.