Home / Allianz Australia / Determination 881137

Determination 881137

Insurer declined business interruption claim for additional costs of pumping flood water from lake

FirmAllianz Australia
Decided2023-02-28
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant
Amount awarded$44,675
Non-financial loss—
Amount claimed$44,675
SourceAFCA PDF

Summary

A business owner's flood claim for additional costs of pumping water from a lake to restore the business was declined by the insurer. AFCA found the costs were covered and required payment of $44,674.89 plus statutory interest.

The flooded earthen bund was insured infrastructure/road, and the pumping costs were additional increase in cost of working necessarily incurred, with no exclusion established by the insurer.

Issues

Subjects and remedies

business interruptionhome or building damagenatural disastersmall businesspay claimpay interest

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 881137 Financial firm Allianz Australia Insurance Limited Determination | Case number: 881137 Page 1 of 6 Case number: 881137 24 February 2023 1 Determination overview 1.1 Complaint The complainant ‟s company holds a business insurance policy with the financial firm (insurer). He lodged a claim for loss and damage to the insured property and stock due to a flood event, as well as for consequential losses relating to business interruption. The insurer accepted the claim in part and settled some aspects of it. However, the insurer denied cover in relation to the additional (business interruption) costs incurred in pumping out water from the lake on the property. The complainant does not accept that decision. He maintains the property suffered physical damage in the flood, and that resulted in additional costs which were necessarily required to return the business to operation. He believes those costs should be covered. 1.2 Issues and key findings Is the insurer entitled to deny the claim for pumping of water? No. The insurer is liable for the claimed costs which represent an „additional increase in cost of working‟ under the Business Interruption section of the policy. Why is the outcome fair? The outcome is fair because the policy provides a benefit for the additional costs of working, and the complainant incurred those costs in response to the defined flood event. The insurer has not established an exclusion applies or that it is otherwise entitled to decline the claim. It would not be fair for the insurer to decline cover in the circumstances. 1.3 Determination This determination is in favour of the complainant. The insurer is required to accept the disputed component of the claim for business interruption, and pay the complainant $44,674.89, together with statutory interest (under section 57 of the Insurance Contracts Act 1984 ) on this amount, calculated from 12 January 2022 (the date the insurer declined this component of the claim) until the date of settlement. Determination | Case number: 881137 Page 2 of 6 2 Reasons for determination 2.1 Is insurer entitled to deny the claim for pumping of water? Policy provides cover for business interruption The Material Damage section of the policy is described as follows in the PDS: This Section covers You for Property Insured that is accidentally Damaged at the Situation during the Period of Insurance which is not otherwise excluded and provides a number of automatic additional benefits and extra covers. There is an optional benefit to include cover for Flood. The complain ant‟s certificate of insurance (COI) shows he had taken out the optional flood cover. The policy also covers business interruption in certain circumstances: This Section covers You for Consequential Loss from the interruption of or interference with the Business that is caused by a Defined Event that occurs during the Period of Insurance The COI shows the complainant had cover under Part B Consequential Loss of Profits of the Business Interruption provisions. The complainant had also taken out, under Part B, the optional benefit for the „ additional increase in cost of working ‟ , which is: the increase in cost of working (not otherwise recoverable under the Policy) necessarily and reasonably incurred during the Indemnity Period to resume or maintain the normal running of the Business. Flood event caused loss/damage to the insured property The insurer engaged loss adjuster S to assess the cause and extent of damage from the flood. S confirmed:  a significant rainfall event occurred on or around 23 March 2021, which resulted in approximately 400mm rainfall across a four-day period  the nearby C River topped its banks on 20 March 2021 with the water inundating the insured property, including the lake access road and bridge  the lake, which covers the majority of the insured land, normally maintains a water level of 4m above sea level, but following the inundation from the river, the water level sat at 8m above sea level  stock, plant equipment and the access road and bridge were damaged. The complainant pointed out (and S acknowledged) that with the significantly increased water level in the lake from the flood, it was not possible to continue normal business operations. There is no dispute a flood event caused damage to insured property and stock, and that business operations were adversely impacted. Determination | Case number: 881137 Page 3 of 6 Additional costs incurred to restore business operations The purpose of the complainant‟s business is to extract river stone and river sand from the lake for sale, once that material is processed and cleaned. The business does this by positioning an excavator on an earthen bund which has been constructed running off the lake edge into the lake. The excavator extracts the river stone and sand. The bund has been formed over time using the excavator and extracting material. The bund includes a road from the mainland onto the bund. Due to the flood event, the bund was almost entirely submerged under water and the road was not usable. The complainant says he incurred costs to pump out the excess water from the lake so as to restore access to and the functionality of the bund. Flood damage was to the bund, rather than the lake In the policy, „flood‟ means: the covering of normally dry land by water that has escaped or been released from the normal confines of any of the following: a. a lake (whether or not it has been altered or modified); b. a river (whether or not it has been altered or modified); … e. a reservoir… The policy also explains: When “Flood” cover is shown in the current Schedule as covered, We will cover loss of or Damage to Property Insured caused by Flood … and Damage(d) means any physical loss of, destruction of or damage to the Property Insured so as to lessen its value or any physical loss. The insurer says it does not insure the lake. It submits the policy is clear that the insurer will not pay loss or damage to „canals, dams, tunnels, reservoirs other than tanks and their contents‟ (emphasis added). I do not accept the insurer‟s argument the exclusion for loss or damage to reservoirs under the event for flood is applicable in the circumstances. This is because the body of water is not a reservoir. In all reports by S, the body of water is referred to as a lake. In the lease agreement, it is referred to as a lake. The words „lake‟ and „reservoir‟ are not defined in the policy. The definition of a „reservoir‟ according to the Macquarie Dictionary is a „ natural or artificial place where water is collected Determination | Case number: 881137 Page 4 of 6 and stored for use, especially water supplying a community, irrigating land, and furnishing power ‟. I am not satisfied the water was being „collected‟, or stored for use in that commonly understood sense. Instead, water simply accumulated over time due to rainfall into the area of the extraction pit which was being progressively excavated for other purposes. The insurer also submits, as the lake is not dry land, it does not fall within the scope of cover for „flood‟. It says, in any case, no damage was incurred to the lake. I accept the lake itself is not dry land. However, I consider the earthen bund which extends into the lake does represent „normally dry land ‟ , and this is clear from the evidence of aerial photographs over the years. The bund was clearly impacted by the flood event. In their 3 rd report, S reports the complainant as saying that, after lowering the water level in the lake, he then had to remove some deposited silt material from the surface of the pad area and undertake some minor works to re-form the surface. There is no argument the complainant was unable to resume normal business until the bund was no longer affected by the floodwater and it was able to be reinstated to functional operation. Bund represents infrastructure, and includes a road The policy defines Property Insured as: all tangible property both real and personal shown as insured on the Schedule in respect of each Section and not otherwise excluded which belongs to You, or for which You are legally responsible, or have assumed responsibility to insure prior to the occurrence of any Damage. The complainant specifically insured „ bridges, roads and infrastructure ‟ under the Material Damage section of the policy. Those terms are not defined in the policy. The Macquarie Dictionary defines a „ road ‟ as: 3. the track on which vehicles etc. pass, as opposed to the pavement. The Macquarie Dictionary defines „ infrastructure ‟ as: 3. the buildings or permanent installations associated with any organisation or operation. I am satisfied the earthen bund incorporates a road consistent with the dictionary definition, and the bund should reasonably be considered to be „i nfrastructure ‟ as it is a necessary „ installation ‟ into the lake serving a particular purpose for the operation of the business. I acknowledge S‟s report advising the bund has been slowly deconstructed by the complainant with a mind to removing it completely and starting to extract from a different section of the pit. Nonetheless, in respect of its structure and purpose at the time of the flood event, I am satisfied it is infrastructure and there was a road for the purposes of the policy. Determination | Case number: 881137 Page 5 of 6 Insurer is not entitled to decline claim Based on the available evidence, I am satisfied:  the policy covers roads and infrastructure  the earthen bund is infrastructure and contains an access road, and so falls within the scope of cover under the policy  the bund was inundated by flood water and damaged in that event  the complainant incurred consequential loss from the interruption to the business caused by the „defined event‟ of flood  that involved additional costs necessarily and reasonably incurred to resume the normal running of the business (by pumping water from the lake so as to lower the level, and restore access to and functionality of the bund)  the insurer has not established an exclusion applies, or that it is otherwise entitled to decline the claim. The complainant is claiming the cost of hiring and operating water pumps, and obtaining the associated local council permits. That totals $44,674.89. The insurer is required to settle the claim by paying the complainant $44,674.89, together with statutory interest (under section 57 of the Insurance Contracts Act 1984 ) on this amount, calculated from 12 January 2022 (the date the insurer declined this component of the claim) until the date of settlement. 2.2 Why is the outcome fair? The complainant‟s policy provides cover for physical accidental loss or damage to his property (including from flood), as well as for business interruption arising from a defined event. Damage occurred to the bund, which is part of the insured property and falls within the scope of cover under the policy (as both road and infrastructure). Remediation of that damage, in order to resume normal business operations, reasonably required the pumping of water from the lake. The costs involved represent consequential losses/additional costs of working for which the insurer is liable under the policy. It is fair, in the circumstances, that it covers those costs. Determination | Case number: 881137 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.