Home / Hollard / Determination 879541

Determination 879541

Scope of works, excess, matching of flooring and benchtop, temporary accommodation and delay on two accepted home claims

FirmHollard
Decided2023-05-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$31,059
Non-financial loss$1,500
Amount claimed$197,573
SourceAFCA PDF

Summary

The complainant disputed the insurer's scope of works, excess, matching and accommodation allowances on two accepted home claims and sought a much larger settlement. AFCA largely upheld the insurer's assessments, allowed a possible pantry benchtop replacement under the matching clause, a 20% uplift if cash settled, and ordered $1,500 for delay.

The insurer's scope of works and accommodation estimates were accurate and flooring damage was under the 40% matching threshold, but the benchtop matching clause might apply and the insurer's delay warranted non-financial loss compensation.

Issues

Subjects and remedies

home or building damagepay claimpay non financial lossreassess claimrepair or rectify

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 879541 Financial firm The Hollard Insurance Company Pty Ltd Determination | Case number: 879541 Page 2 of 10 Case number: 879541 31 March 2023 1 Determination overview 1.1 Complaint The complainant held a home listed events policy for building and contents with the financial firm (insurer). The complainant had 2 claims lodged with the insurer under a policy for home listed events and a policy for home accidental damage the claim lodged in relation to dam age flooring that occurred on 6 January 2022 was accepted by the insurer agreeing to coverage of $9,952.19. The insurer also agreed to reduce the excess from $5,000 to $1,500. This was rejected by the complainant. The second claim was in relation to damage to the stone bench top due to a hot object being placed on the surface which, occurred on 1 February 2022. The insurer accepted the claim and set the damage at $15,510.17 with an excess of $300. The complainant has disputed the excess of $5,000 for the first claim and has also requested that the flooring in the hallway, dining room and kitchen should be replaced due to damage in relation to that claim. The insurer has rejected this as the policy provides a matching benefit only applicable where over 40% of the flooring is damaged. The complainant also requested that the 2 Scope of Works (SOW) be combined. A dispute has arisen over the extent of temporary accommodation and the complainant has also raised issue of compensation for delays in the claim. The complainant has provided a (SOW) for $142,500 for both claims and seeks $55,000 for temporary accommodation. 1.2 Issues and key findings Is the complainant entitled to further compensation? On the information provided to me, on balance, I am satisfied as follows:  the complainant has established that she has valid claims  in relation to the first claim for the damage flooring the insurer ’s assessment and Scope of Works (SOW) is $11,910.88  in relation to the first claim there is no information to show that more than 40% of the floor is damaged  the policy provides a matching policy if over 40% of the flooring is damaged  the policy contains an excess of $5,000  in relation to claim 2 the insu rer’s ( SOW) is $19,148.35  in relation to second claim there is a deductable on the policy of $300  the matching provision may entitle the complainant to the replacing of the benchtop in the pantry  the works will require the complainant to vacate the property  the insurer says 10 days alternative accommodation is appropriate in relation to the first claim  the insurer says 3 days alternative accommodation is appropriate in relation to the second claim  the complainant has raised issues that further works maybe required upon removal of the bench top. Determination | Case number: 879541 Page 3 of 10  the complainant has provided and (SOW) for $142,500 for both claims  the complainant is seeking $55,000 for temporary accommodation  the complainant seeks for this matter to be cash settled. In the circumstances if the complainant accepts a cash settlement of the claims the insurer is to increase this settlement by the sum of 20% to cover contingency and loss of guarantee.  The complainant has a further claim in relation damage to a painting which the insurer has accepted. Decision The insurer is not required to combine the two claims. The insurer is not required to match the flooring throughout the rest of the house. The SOW for the first claim of $11,910.88 is correct. The insurer is entitled to apply the $5,000 excess. Alternative accommodation of 10 days is sufficient for both claims. The SOW for the second claim of $19,148.35 is correct subject to the matching provisions. The insurer is entitled to apply the $300 excess. If the damage benchtop cannot be matched to the benchtop in the pantry, and the damaged benchtop is more than 40 % of the total of the two benchtops the complainant is entitled to have the pantry benchtop replaced. An estimate of the time the complainant needs alternative accommodation will need to be reassessed. Otherwise I accept 3 days is sufficient. If the pantry benchtop needs replacing a further SOW will be required. The complainant has previously requested a cash settlement. If the matter is cash settled, the insurer is to pay a 20% uplift on the amounts paid excluding accommodation, to cover contingencies and loss of guarantee. Is the complainant entitled to non-financial compensation? The insurer has accepted that there was a delay in assessing the claim and providing an outcome between 4 February, when the claim was lodged and 1 April with the broker having to contact the insurer several times. The insurer has obviously accepted that this delay was not appropriate. I am satisfied that the offer of $1,500 is appropriate in this particular matter. The insurer is to pay non-economic loss of $1,500. Why is the outcome fair? The insurer has provided (SOW) in relation to both matters. The insurer is prepared to undertake the repairs to the property. I am not satisfied, on balance, that the complainant provided sufficient information to show that the (SOW) she has provided is required under the current claims. The complainant seeks to cash settle and this determination has been drafted allowing this to occur. In the circumstances it would be unfair to require the insurer to compensate the complainant further. 1.3 Determination This determination is substantially in favour of the insurer. Determination | Case number: 879541 Page 4 of 10 Upon acceptance of this determination the complainant is to indicate whether they wish the insurer to undertake the repairs for both claims. Should they wish to cash settle the matter the insurer is to pay the sum of $11,910.88 in relation to the first claim and $19,148.35 in relation to the second claim. The insurer is to uplift the cash settlement by the amount of 20% to cover contingencies and loss of guarantee. The implementation of changes required should the pantry benchtop need replacing are set out in 2.1. The insurer is to pay the complainant up to 13 days or alternatively accommodation, under the terms of the policies. The complainant is to provide proof of accommodation and confirmation of payment. The insurer is also to pay $1,500 non-financial compensation. Determination | Case number: 879541 Page 5 of 10 2 Reasons for determination 2.1 Is the complainant entitled to further compensation? The complainant has lodged 2 claims the first for a loss which occurred on 6 January 2022 when a bicycle toppled over and damaged wooden flooring, and the second claim which was lodged on 1 February 2022 when a stone bench top was damaged due to a hot object being placed on the surface. Product Disclosure Statement (PDS) The insurer has referred to the PDS which has been provided in relation to each policy. For convenience I will refer to the claim lodged for loss on 6 January 2022 as claim 1 and the claim for damage that occurred on 1 February 2022 as claim 2. Claim 1 The home listed event policy provides a benefit for accidental damage. The insurer has accepted the claim and I accept that the damage is covered under the terms and conditions of the policy. The PDS provides as follows: … … Determination | Case number: 879541 Page 6 of 10 The insurer has accepted alternative accommodation is to be provided under both claims. Expert reports Claim 1 The insurer obtained a report and a (SOW) by CC who inspected the property on 14 February 2022 the report noted that the complainant stated that on 6 January 2022 the property suffered damage when a bike was knocked over damaging the hardwood floor. C C noted damage to the entrance, ‘ timber hardwood floor dented (Denting and scratching of 6 timber floor planks) CC also noted that the complainant had submitted a further claim for the damage to the stone bench tops and if accepted these repairs would require to be completed at the same time as this claim.’ CC carried out a (SOW) providing a total of $11,910.88. The insurer has advised that the assessor has confirmed only equates to 2% of the hallway. This has not been disputed by the complainant. Claim 2 The insurer obtained a report (SOW) from CC who inspected the property on 14 February 2022 in relation to the damage to the bench top. CC noted that the complainant ‘advised that they had set a hotpot aside kitchen sink without any protection below. The insured advised that they notice a crack starting to appear on the stone bench top, so they decided to lodge a claim with the insurer.’ CC inspection noted a hairline crack to 70mm stone bench top in the kitchen CC confirmed that the benchtop is not repairable and estimated for all stone bench tops to be replaced in the kitchen as a match will not be possible. CC also allowed for the glass splash back to be replaced. CC provided a (SOW) in a total sum of $19,148.35. The Certificate of Insurance (COI) for the claim 2 provides for an excess of $300. Quotation by complainant’s repairer The complainant has obtained a quotation from (TC) and a (SOW). The (SOW) does not itemised the costs as set out merely providing a total of $146,520. I do , however, note that there is an item which is noted as ‘Lay New Big River Timber Armour Flooring in Blackbutt 138 x 14 to downstairs. The quotation and SOW repairs also notes that the works could take between 8 to 10 weeks. The complainant has provided a quotation for accommodation for a period for July to 11 September is $53,073.44. The complainant has also provided an email from the floor supplier indicating that it is not possible to carry out a blending process when a relatively small area of flooring needs replacing. It is also notes when the top finish is sanded back the repair area ‘is most likely to appear as different from the balance of the project.’ Determination | Case number: 879541 Page 7 of 10 I am not satisfied that the information provided by the complainant is a SOW which accurately reflects the works that are required under the terms of the policy. I am satisfied the insurer’s SOW is accurate as is their estimate of alternative accommodation. The insurer has further referred to the PDS in relation to the bench top in the walk-in pantry as follows: ‘We will pay for the damaged portion of fixed coverings to walls, floors and ceilings only in the room, hall or passage where the damage occurred. We will not pay any costs f or replacing undamaged property.’ The complainant has made a further submission in relation to the damaged flooring area noting that it is not possible to blend the flooring as set out in their expert reports further the complainant has said that: ‘We acknowledge that the damage to the flooring is not over 40% but we are simply trying to explain that when you try to replace a fixed flooring like it has been suggested you will damage the rest of the flooring and then it will eventually need to be replaced. Which both the flooring layers and suppliers have confirmed.’ The complainant also says that the bench top will need to be replace. It is noted that the insurer has agreed to this. The complainant says that once it is replaced the bench top will be, most likely, different from the bench in the pantry. The complainant also says it is most likely that there will be more damage to the floorboards during the replacement of the benchtop. Nothing has been provided to me to confirm there will be further damage. Matching part of policy. The policy provides for a matching provision if more than 40% of damage material when replacement cannot be matched to undamaged material. I am satisfied the information provided, on balance, that the damage to the flooring is substantially less than the 40% requirement. In the circumstances I am satisfied that the insurer’s (SOW) provides for replacement of the flooring and that there is no requirement under the policy to replace any further. Bench top The insurer accepted the claim for the bench top and has noted that the complainant stated that further damage could occur to the kitchen in the removal of the bench top. The insurer has also accepted the glass back will need to be replaced. In the normal process of repairing under the supervision of the insurer any further damage that arises is paid for by the insurer. In current circumstances the complainant has requested a cash settlement. Should this matter be cash settled the insurer is to pay an uplift of 20% to cover contingencies and loss of guarantee. Determination | Case number: 879541 Page 8 of 10 The other issue that arises in relation to the bench top is whether the bench top in the pantry should also be replaced as it is unlikely that it would be possible to obtain a matching bench top. The insurer has referred to the PDS as set above in relation to replacement of the bench top in the bu tler’s pantry. I am not convinced that this section of the PDS refers to the bench top. The context of the clause is in relation to fixed coverings, walls, floors and ceilings. It does not refer to other items. In the circumstances I am not satisfied that this section excludes the damage to the bench top and the undamaged section of the butler’s pantry. However, there is I note that the clause is confusing as it goes on:  ‘we will try to match any material used to repair Your Buildings with original materials. If We cannot, We will use the nearest equivalent available to the original material, however if:  If it is impossible to acquired new material to replace damage material that reasonably matches the undamaged portion to a similar extent as immediately prior to the loss or damage occurring and  The amount of the damaged material cannot be matched the undamaged material is more than 40% of the total material that would have to be replaced if all the matching and undamaged material was replaced, then We will replace both the damage and undamaged material.’ In the circumstances I am satisfied if the bench top consists of more than 40% of the total benchtops when combined with the bench top in the butler’s pantry, then the insurer would be required to replace it under this clause. Accommodation The insurer has provided a (SOW) and indicated that the total period that it is likely that the property will be uninhabitable is 13 days. I am not satisfied that any information has been provided confirms a longer period than this. The insurer is to pay a total 13 days accommodation. Damage to painting The complainant has lodged a claim for damage to a painting. The insurer has agreed to pay the repair quote of $630 which includes freight. Nothing has been provided to show the complainant disputes this. Complainant may seek a cash settlement If the complainant seeks a cash settlement the insurer is to settle the claim as follows:  Pay $11,910.88 together with a 20% uplift for the first claim. The insurer is entitled to deduct the $5,000 excess under this claim.  Pay $19,148.35 in relation to the second claim plus an uplift of 20%. The insurer is entitled to deduct the $300 excess under this policy.  Pay $630 dollars for the repair and freight of the painting damage. Determination | Case number: 879541 Page 9 of 10  The insurer is to 13 days accommodation under the terms as set out in the policies. The complainant is to provide details of the accommodation together with proof of payment and the insurer is to refund this sum. Should the pantry benchtop require replacing under the matching provisions the complainant is to obtain a quotation for the repairs in the form of a scope of works. The quotation is also to estimate the extra time the repairs will require, taking into account that some of the work may be possible at the same time the complainants are vacant from the property for the other repairs. The complainant is to provide the SOW to the insurer who is entitled to undertake their own assessment to verify the accuracy of the scope of works. The insurer is to pay the amount with an uplift of 20% as with the other payments. Should the complainant not choose a cash settlement the insurer is to undertake the repairs including assessing whether the pantry benchtop is replaced under the matching provisions, together with the requirement for any further alternative accommodation. 2.2 Is the complainant entitled to non-financial compensation? AFCA will only award compensation for non-financial loss where, there has been an unusual amount of:  physical inconvenience  time taken to resolve a situation  interference with the complainant’s expectations of enjoyment or peace of mind. In assessing this AFCA expects complainants:  to be moderately robust  bear the normal degree of inconvenience experience when a problem occurs, and  take reasonable steps to minimise inconvenience suffered. Current circumstances I am satisfied that the insurer did not act as speedily as should have been expected. It is appropriate that the insurer pays $1,500 for non-financial compensation. Determination | Case number: 879541 Page 10 of 10 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.