Home / AIG Australia Limited / Determination 878472

Determination 878472

Delay and poor handling of a strata flood-related claim; insurer awaiting body corporate solicitor's response before deciding

FirmAIG Australia Limited
Decided2023-03-10
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A unit owner in a strata complex flooded by a creek complained the insurer delayed and failed to communicate about his claim. AFCA found the delay was unavoidable and the insurer acted reasonably, so decided in favour of the insurer.

A hydrology report was reasonably required given the flood exclusion, the delay was unavoidable amid mass claims, and deferral followed the body corporate solicitor's request.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All AIG Australia Limited determinations · Find similar determinations

Text of the determination

Determination Case number 878472 Financial firm AIG Australia Limited Determination | Case number: 878472 Page 1 of 6 Case number: 878472 10 March 2023 1 Determination overview 1.1 Complaint The complainant’s unit was inundated by water in late February 2022. His unit is part of a strata apartment complex that was:  located next to a creek that overflowed at the time  insured with the financial firm (insurer) under a strata policy that did not cover flood. The complainant claimed for the damage to his unit and for loss of rent. He says the insurer failed to decide his claim and is delaying it. He also says the insurer failed to communicate with or update him. He wants the insurer to cover his claimed losses and pay compensation for poor claims handling. The insurer denies delaying or mishandling the claim. It also denies failing to communicate with or update the complainant. 1.2 Issues and key findings Must the insurer accept the claim or pay compensation? Not at this stage. The exchanged information does not support that the insurer was unreasonably delaying or handling the claim. The delays were unavoidable, and it was the body corporate’s solicitor that told the insurer to defer making any claim decisions. Why is the outcome fair? The exchanged information does not show that the insurer was unreasonably delaying or handling the claim. Given this, it would not be fair to require the insurer to provide the remedies the complainant seeks at this stage. It is fair that the insurer only decides his claim if he confirms he does not want the body corporate or its solicitor to represent him. 1.3 Determination This determination is in favour of the insurer. If the complainant still wants the insurer to decide his claim despite the body corporate solicitor’s advice to the insurer, he is to provide the insurer, body corporate, and the solicitor with written confirmation that:  this is indeed his intention  he does not want the body corporate or its solicitor to represent him or his interests  he does not want to participate in any ongoing discussions the body corporate and/or other affected unit owners seem to be having with the insurer. Within 14 days of receiving the above written confirmation, the insurer is to take steps to assess and provide the complainant with a claim decision on losses relating to his unit only. Save for the above, the insurer is not required to accept the claim or pay any compensation at this stage or take any other action in relation to the claim or complaint. Determination | Case number: 878472 Page 2 of 6 2 Reasons for determination 2.1 Must the insurer accept the claim or pay compensation? Not at this stage. The exchanged information does not support that the insurer was unreasonably delaying or handling the claim. The delays were unavoidable, and it was the body corporate’s solicitor that told the insurer to defer making any claim decisions . Complainant says insurer is delaying and not responding to his claim The complainant says the insurer is delaying and not responding to his claim although his unit was not inundated by flood water. He says water that entered his unit was ‘clean and clear rain water’, and he has already given the insurer photos and all evidence available. He also says the insurer failed to communicate with or update him. Given this, the complainant wants compensation for the damage to his unit, loss of rent, and poor claims handling. Insurer says delays were unavoidable and complainant was regularly updated The insurer acknowledges the delays with the claim but says they were unavoidable. It says the relevant event caused significant flooding in many places and it received many claims. This impacted its ability to assess and decide claims in a timely manner. The insurer also says the policy does not cover flood. As the strata complex was inundated by water from the neighbouring creek during the event, it needed to determine if insured property within the complex might have been damaged by flood. Given this, it required a hydrologist’s report before determining its liability for claims relating to the strata complex. The insurer says there was also a delay with the hydrologist report due to the volume of claims arising from the event. When the report was received, it promptly forwarded a copy and its preliminary views on liability to the insured (i.e. the body corporate) and its broker. The insurer also says it gave the strata complex’s body corporate and relevant lot owners opportunity to provide information to dispute its hydrologist findings by 23 June 2022, after which it would formalise its decision on liability. However, the body corporate’s solicitor asked it to withhold making any decision until it hears from the solicitor again. The insurer says it has not yet heard from the solicitor. The insurer also denies failing to contact or update the complainant. It says he was regularly updated through the body corporate manager, the broker, and by it directly. He was also told at the outset that a claim decision could not be made until a hydrologist report is considered. Policy does not cover flood damage There is no dispute the policy covers the strata complex’s buildings and common contents for accidental loss or damage. However, it does not cover loss or damage caused by flood, which the policy defines as: … the covering of normally dry land by water that has escaped or been released from the normal confines of any of the following:  a lake, river, creek, or other natural watercourse (whether or not it has been altered or modified); or  a reservoir, canal or dam. Determination | Case number: 878472 Page 3 of 6 Fair for insurer to require a hydrology report before deciding claim There is no dispute the relevant strata complex is located next to a creek, and water from the creek had inundated the complex at some stage during the event. Claims involving questions whether stormwater runoff and/or floodwater caused damage are usually complex and contentious. Hydrology reports are normally required to assist in determining this and whether an insurance policy would ultimately respond to a claim. Given this, and that the policy does not cover flood, it was fair and reasonable for the insurer to require a hydrology report before deciding claims involving the strata complex. Delay in obtaining hydrology report was not unreasonable or avoidable The insurer says it received notification of claims involving the strata complex on 2 March 2022 and its hydrologist attended the complex 20 days later, on 22 March 2022. The hydrology report was issued on 17 May 2022, about two months later. I do not accept this timeframe was unreasonable or avoidable given the circumstances the insurer was faced with. I also do not accept the complainant was unaware of the reason for the delay or that he was not given updates. The Insurance Council of Australia (ICA) says the February 2022 flooding events in NSW and Queensland resulted in some 240,000 claims (worth an estimated $5.76 billion) being made. This shows the insurance industry faced by a sudden and significant influx of claims, and their ability to assess and decide claims promptly was stretched. There are also usually limited qualified hydrologists available at a given time, so there would naturally be some delay in having a hydrologist attend a property and then issue a report. Complainant was informed of the reason for the delay The exchanged information shows the complainant was informed why a hydrologist report was needed and why there was a delay in receiving a report. This is clear from many correspondences sent to him by the strata complex’s body corporate manager, the broker, and the insurer between 22 March 2022 and 5 May 2022. Collectively, these correspondences also informed the complainant that:  the policy does not cover flood damage and some contents items he had claimed for  the insurer is not in position to confirm coverage for losses covered by the policy until it has received and considered the hydrologist report for his strata complex  the insurer will formalise its position on the claim as soon as it receives the report  he should proceed prudently on the basis cover may not be available. Insurer acted transparently and promptly after receiving hydrology report The exchanged information further shows the insurer acted transparently and promptly after receiving the hydrology report on 17 May 2022. It supplied the body corporate and broker with a copy of the report together with a letter (dated 25 May 2022) setting out its preliminary views on the claims involving the strata complex . The letter outlined the insurer’s :  observations of the hydrology report  intention to decline cover for some insured property on the basis the relevant damages were caused by flood and/or defective construction  intention to accept some insured property may have been damaged by stormwater runoff up to a height of two centimetres between 25 February 2022 and 7pm 27 February 2022 Determination | Case number: 878472 Page 4 of 6  intention to consider information the body corporate and affected lot owners might want to provide to dispute the hydrologist or show damage was caused by stormwater runoff  intention to finalise its decisions on the claims made by 23 June 2022  requirements and next steps for parties wishing to claim for stormwater runoff damage. Body corporate’s solicitor asked the insurer to defer deciding claims Following this, the body corporate’s solicitor wrote to the insurer on 3 June 2022, asking it to defer any claim decisions planned for 23 June 2022. The solicitor explained its client needed more time to consider the hydrology report and the insurer’s preliminary views. However, he does not know how much time was needed, but he will inform the insurer after getting his client’s instructions. Given this, the solicitor asked the insurer withhold making any decisions on claims involving the strata complex and confirm it will afford its client ‘and the Lot Owners’ more time. The insurer says its claim decisions were deferred because of the solicitor’s letter and it is still waiting to hear back from the solicitor. On review of the exchanged information, I find no indication that the solicitor has ever come back to the insurer on this. Majority of claimants seemed inclined to have ongoing discussions I also note the body corporate’s 16 September 2022 update to the affected lot owners says:  members of the body corporate committee met with the hydrologist recently  the hydrologist needs several weeks to review all plans, videos, photos and reports  its solicitor has advised that it was inappropriate for the body corporate and the affected units owners to pursue their claims through the AFCA process for the time being. On balance, this suggests further information was submitted for the insurer and hydrologist ’s consideration following the solicitor’s 3 June 2022 letter . It also indicates the body corporate and majority of the affected unit owners seemed more inclined to have ongoing discussions with the insurer, rather than wanting final decisions on their claims. This seems to explain why the insurer has not received any further advice from the solicitor to proceed with its decisions on the claims, and why no decisions were made. Insurer has not unreasonably delayed or handled the claim I accept the complainant is frustrated and stressed by the delays with his claim. However, I am not satisfied the insurer was unreasonably delaying or handling the matter. A hydrology report was clearly needed for the claim and the delay in obtaining this report was unavoidable. The insurer also promptly exchanged the report and informed the body corporate of its preliminary views. I t was the body corporate’s solicitor tha t asked the insurer to withhold any decision on the claims. Finally, the body corporate and a majority of the affected unit owners seem more inclined to have ongoing discussions with the insurer, rather than having claim decisions being made. As the body corporate typically represents the interests of lot owners, the insurer could not be said to be acting unreasonably or unreasonably delaying the claim by:  cooperating with its solicitor’s request to defer its claim decisions  engaging in ongoing discussions with its representatives, instead of deciding the claims. Given this, I am not satisfied it is fair to require the insurer to accept the complainant’s claim at this stage or pay compensation for poor claims handling. Determination | Case number: 878472 Page 5 of 6 Insurer is to decide complainant’s claim if he gives some written confirmation I acknowledge the complainant believes his unit was not damaged by flood and wants a favourable decision on his claim immediately. From his submissions, he appears to want the insurer to address his own claim individually rather than collectively or together with the body corporate and other lot owners’ claims. If that is his intention, then in the interest of finalising his claim only, I propose he formally writes to the insurer, the body corporate and its solicitor clearly confirming that is indeed his intention. He must also clearly confirm that he does not want:  the body corporate or its solicitor to act for him or represent his interests in the matter  to participate in any ongoing discussions the body corporate and other affected unit owners seem to be having with the insurer. Within 14 days of receiving this confirmation, the insurer is to decide and inform the complainant of the outcome of his own claim based on information it currently has. If the complainant is dissatisfied with the decision, he can then lodge an AFCA complaint about it. Save for the above, I am not satisfied the insurer is not required to take any other action in relation to the complainant’s claim or complaint. Determination | Case number: 878472 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.