Text of the determination
Determination
Case number 875471
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 875471 Page 1 of 9
Case number: 875471 22 December 2022
1 Determination overview
1.1 Complaint
The complainant holds a home insurance policy with the financial firm (insurer). On 11
December 2021, he lodged a claim for storm damage on 9 December 2021 after a retaining
wall at his property collapsed.
The insurer denied the claim on the basis that the damage was not caused by a storm but
rather structural defects, wear and tear and gradual deterioration. It also said it was not a
retaining wall but an embankment. The complainant disputes the decision saying, among
other things, that the engineer‟s opinion is based on unreliabl e weather data and that an
intense localised storm can cause this kind of damage.
He seeks that the insurer accept the claim and cover the damage to his property.
1.2 Issues and key findings
Is the insurer entitled to decline the claim?
No. The complainant has established a valid claim. Having regard to all the available
information, I am not satisfied, on the balance of probabilities, that the insurer has established
that the gradual deterioration exclusion applies. Accordingly, the insurer is now required to
cover the repairs as detailed below. The insurer is also required to reimburse the
complainant‟s professional costs up to $5,000, subject to the necessary supporting
documentation being provided.
Why is the outcome fair?
The outcome is fair because the insurer has not established, on the balance of probabilities,
that the gradual deterioration exclusion applies. Accordingly, the insurer is required to cover
the damage to the complainant‟s property and reimburse his professional costs.
1.3 Determination
This determination is in favour of the complainant.
The insurer must work with the complainant to obtain a scope of works and quotes to carry
out the repairs. The complainant may then be cash settled with a 20% contingency.
If the complainant accepts the determination, it must provide the insurer with the requisite
supporting information within 21 days. Once received, the insurer must then pay the
complainant‟s professional costs up to $5,000 within 14 days of receipt.
Determination | Case number: 875471 Page 2 of 9
2 Reasons for determination
2.1 Is the insurer entitled to decline the claim?
No. The complainant has established a valid claim. Having regard to all the available
information, I am not satisfied, on the balance of probabilities, that the insurer has established
that the gradual deterioration exclusion applies. Accordingly, the insurer is now required to
cover the repairs as detailed below. The insurer is also required to reimburse the
complainant‟s professional costs up to $5,000, subject to the necessary supporting
documentation being provided.
Onus on complainant to establish a valid claim
The initial onus is with the complainant to establish on the balance of probabilities (that it is
more likely than not) that the loss or damage claimed falls within the terms of the policy. This
is known as a valid (or prima facie ) claim.
Once the complainant has established a valid claim, the onus shifts to the insurer to establish,
on balance, the application of a policy exclusion or that it is otherwise entitled to decline the
claim under the policy.
Policy covers insured events subject to exclusions
The insurer‟s policy consists of the policy schedule and product disclosure statement (PDS).
It is not in dispute the insurer provided the policy documents to the complainant.
The policy is an „insured events‟ policy. This means not all loss and damage is automatically
covered. Rather, only loss or damage caused by one or more of the insured events, and not
subject to exclusions, is covered.
The insured events are set out in the PDS and include storm. The policy provides cover for:
Loss or damage as a result of:
storm (including named cyclone)
rainwater
flood, or
wind.
The PDS does, however, make it clear that cover for storm does not include:
Water entering your buildings:
…because of a structural defect, faulty design or faulty workmanship…
Landslide or subsidence is also an insured event and covers:
Determination | Case number: 875471 Page 3 of 9
Loss or damage as a result of a landslide or subsidence if the loss or damage
occurs within 72 hours of an insured event [including] a storm, rainwater, flood or
wind…
The policy also includes a general exclusion for damage which is caused directly or indirectly
by, amongst other things:
settling, shrinkage or any movement or earth
settling shrinkage or expansion in buildings, foundations, walls or
pavements
erosion, rust, corrosion, gradual deterioration, depreciation, wear or tear…
a defect in an item, structural defects, faulty or poor workmanship or
design
For the purpose of the policy, retaining walls form part of the buildings and are covered under
the policy. Therefore, in order the establish a valid claim, the complainant must show that the
damage to the retaining wall was caused by an insured event.
Parties have provided reports regarding the damage and cause
The key expert evidence is summarised in Section 3.2 of this determination.
The insurer has relied on the reports prepared by its engineer. It says:
in determining the proximate cause of damage to the retaining wall, the weather data
(force acting on the retaining wall) must be assessed in conjunction with the structural
capacity of the retaining wall (resistance to the applied forces);
it is reasonable to assume the retaining wall would have experienced similar rainfall
intensities in the past 25 years and has not failed;
there was no drainage present behind the retaining wall to keep the timber dry and from
rotting;
given the condition of the timber retaining wall, the retaining wall has deteriorated and has
failed in conditions it was able to withstand in the past;
on this basis the cause of the damage is attributed to long-term deterioration; and
an unmaintained timber retaining wall would inevitably fail without intervention.
The complainant relies on expert reports from a meteorologist and an engineer and says:
there was a vast amount of rainfall in a very short period. This is a significant factor and
very different to having the same amount of rain over the course of a 24-hour period;
most of the rainfall from the storm most likely fell between 6:34pm and 7:04pm and rainfall
rates may have exceeded 100mm/hr for short periods;
it is not correct for the insurer to try and define the retaining wall as an embankment;
the structure had been in place for over 25 years without issue;
heavy rain is the sole cause of the damage and the evidence of this is overwhelming; and
it is seeking that the insurer pay to repair all the damage caused by the rain.
Determination | Case number: 875471 Page 4 of 9
Proximate cause of the damage must be established
The complainant needs to show the proximate cause of the damage being claimed was, on
balance, the storm event in order to establish a valid claim. The insurer must establish that
the proximate cause falls within a policy exclusion in order to decline the claim.
The proximate cause of a loss is the dominant, effective or operative cause. It does not have
to be the first, the last or the sole cause.
If there are several causes, each needs to be examined for qualities of reality, predominance
and efficiency to identify the proximate cause. For example, if one cause would have caused
the loss in any case, and the other one would not have done so without the first, then the first
is the proximate cause.
Available information does show damage has been caused by storm
Having reviewed all of the available information provided by both parties, I am satisfied, on
the balance of probabilities, that the 9 December 2021 storm event caused the damage to the
retaining wall. I am persuaded by the information provided by the complainant since:
the storm event was one of high intensity with high volumes of precipitation in a very short
period of time. It is estimated that rainfall exceeded 100mm/hour for short periods;
while I accept the timber sleepers had deteriorated over time and been in a run-down state
for some years, there had been no problem with the structure for over 25 years; and
despite the state of the timber sleepers, the retaining wall has not been damaged even
after the 21 March 21 storm event (which resulted in over 100mm rainfall for the 24-hour
period). I am not satisfied, on balance, that the gradual deterioration of the sleepers was
the proximate cause of the damage.
I note that there have been some inconsistencies and changes of opinion in the insurer‟s
expert reports. For example, the insurer initially submitted the structure was an embankment
not a retaining wall. It later accepted it was in fact a retaining wall as set out in its engineer‟s
report. The insurer also considered there was no storm on 9 December 2021. However, it
then accepted that there was in fact a storm and, further, that there was a significant amount
of rainfall in a short period. I accept that this intense rainfall can result in very different
conditions compared to the same level of rainfall recorded in a 24-hour period. This is a key
consideration in determining the proximate cause of the damage.
In terms of the size and slope of the rock wall, the experts have differing opinions about the
appropriate standards to be applied. Based on this, I am not persuaded that the insurer has
provided sufficient information to establish that the rock wall was unstable.
I also do not consider there is any basis to find the structural defects exclusion should apply.
While this argument was originally raised by the insurer, it appears that it is no longer being
pursued. In any event, I do not consider there is sufficient evidence to support this exclusion.
Accordingly, the complainant has established a valid claim for damage caused by an insured
event. I am not persuaded the information provided by the insurer is persuasive in
establishing that graduate deterioration was the proximate cause of the loss and therefore do
not consider the claim should be excluded.
Determination | Case number: 875471 Page 5 of 9
Claim should be settled in this way
The parties are to engage an independent structural engineer to inspect the property and
provide a full scope of works for the repair of the retaining wall.
The engineer should be one agreed to by the parties. This can be done by the insurer
providing a list of three engineers that the complainant can choose one from. Alternatively,
the complainant can provide three choices for the insurer to choose from. The engineer
should be appropriately licenced and qualified to do this.
The engineer‟s costs are to be borne by the insurer.
Once this engineer has been engaged and has completed the scope of works, each party can
obtain at least one, and no more than two, quotes based on that scope of works.
If only one quote is obtained, then the insurer is to cash settle the claim based on that quote
plus a 20% contingency. If more than one quote is obtained, then the insurer is to cash settle
the claim based on the average of those quotations with a 20% contingency.
The contingency is to address the fact the risks of the works are passing to the complainant
and the likely possibility that there may be variations required during the works.
Insurer is to reimburse the complaint for professional costs
Under Rule D.5, AFCA may decide a financial firm should contribute to the professional costs
incurred by a complainant in the course of a complaint. These costs can be awarded if the
complainant needed an expert to understand or establish their claim. These costs are
normally capped at $5,000 unless exceptional circumstances apply.
I am satisfied that the reports of EA and WW have assisted the complainant in establishing a
valid claim under the policy. However, it does not appear that all supporting information has
been provided (we have only seen an invoice from EA for $2,000 and WW for $660, both
from August 2022). Accordingly, if the determination is accepted, the complainant must
within 21 days provide the insurer with copies of all tax invoices for EA and WW which it
wishes to claim along with confirmation that payment has been made. The insurer must then
pay the complainant‟s professional costs up to $5,000 , within 14 days of receiving the
supporting information.
2.2 Why is the outcome fair?
The outcome is fair because the insurer has not established, on the balance of probabilities,
that the gradual deterioration exclusion applies. Accordingly, the insurer is required to cover
the damage to the complainant‟s property and reimburse his professional costs.
Determination | Case number: 875471 Page 6 of 9
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Key Expert Reports
EXPERT KEY POINTS
Insurer‟s engineer, EIS
(3 January 2022)
the damage is due to a built-up embankment ad this is not
considered a retaining wall structure;
the area did not receive any rainfall activity on the claimed
date of loss;
on 21 March 2021 the area experienced rainfall of 130mm
which is more than the month rainfall recorded for the entire
month of December with 73mm;
if the embankment were to collapse due to a on-off storm
event, it would have occurred in March 2021 (but this did not
occur);
the collapsed embankment is consistent with the unstable
Determination | Case number: 875471 Page 7 of 9
height and length ration of the embankment;
the structure was however constructed prior to the inception
of the Building Code of Australia;
the embankment was unstable and naturally and gradually
mobilised towards a more equilibrium slope ratio of 2:3; and
the collapsed embankment is a result of the inadequate
slope of the embankment and not a result of a par ticular
storm event.
EIS supplementary
report – 1
(16 May 2022)
the area of the collapsed soil is an un - retained embankment
and not a retaining wall under NCC BCA 2019;
if a retaining wall had been constructed, the volume of rain
that fell would not have resulted in the collapse of the
structure;
the retaining wall would have provided the adequate weight
to resist the earth and hydrostatic pressure from the storm
event. It would also include drainage provisions to prevent
hydrostatic pressure build up behind the retaining wall;
the previous claim at the property related to the retaining
wall in front of the timber deck. The present claim relates to
a different area of t he property along the driveway;
Complainant‟s engineer,
EA
(9 August 2022)
t he lower one third of the revetment comprises horizontally
laid timber “sleepers” forming a vertical wall. The remainder
i s sloping soil with the surface of embedded stones;
the collapse appears to have been triggered by heavy
rainfall intensity during a storm. The water builds up
hydrostatic pressure behind a wall that is approximately
twice that from dry earth. That is why the majority of
retaining wall failures are caused by w ater that cannot drain
fast enough;
the collapsed structure had been in place for at least 25
years without signs of distress. In that time it would have
experienced varying climatic conditions and has proved
stable;
any investigation should address the f act that the structure is
longstanding and has failed only under intense local rainfall;
the correct engineering classification for this type of structure
is found in the Australian standards for earth - retaining
structures. S 4678 2002 defines the slopes that are
retaining structures where the faces are between 70 and 90
degrees; and
the strength of the soil needs to be determined although this
does not appear to have been done by the insurer‟s expert.
The dimensions and soil classification are critical; and
the local storm should be included in any assessment of the
stability of the structure.
EIS supplementary
report – 2
(16 August 2022)
it has changed its view on the proximate cause of the
damage based on new information received that:
Determination | Case number: 875471 Page 8 of 9
> the damage related to the timber sleeper retaining wall;
> the retaining wall was not observed at the location of the
collapsed embankment or in a recognisable state;
the damage to the timber sleeper retaining wall is a result of
the long - term deterioration of the timb er sleepers and not a
storm event;
if the retaining wall was not in poor and dilapidated condition
it would not have failed as evident from the prior storm
events ;
the complainant‟s engineer fails to acknowledge the
deterioration of the timber sleepers;
t h e complainant‟s report ha s only reviewed the intensity of
the rainfall activity. However, in determining the cause of
the damage, the action (rainfall) and the resistance of the
structure (timber retaining wall) must be considered;
t he timber sleeper ret aining wall was buried in the ground
without any adequate drainage system to prevent rotting of
the timber; and
o n this basis, it is expected that overtime the retaining wall
deteriorate and not be able to resist the same hydrostatic
pressure that it would in the past .
EA supplementary
report – 1
(22 August 2022)
it has only been asked to comment on the reports of the
insurer‟s expert. EA has not visited the site and proposed a
causation of the failure, however it is able to do so if asked;
the insurer‟s expert report in reply to EA‟s report abandons
the original conclusion of an unstable slope and rejection of
rainfall intensity involvement. Further, it acknowledges that
the intense rainfall at the location had a detrimental effect;
and
the rai nfall commented on by the insurer‟s expert of „60mm
in a rain gauge‟ is being compared to other locations daily
total. What is important is that reading was collected in
approximately 30 minutes, ie. a rate of 120mm/hour.
Complainant‟s
meteorologist, W W
(8 September 2022)
rainfall that occurred in the surrounding areas on the 9th of
December (in order of proximity to the claim address)
included Maroota ( 58mm ), St Albans ( 54mm ) Conoelands
( 36.4.mm ), Lower Mangrove ( 43mm ) and Colo Heights
( 43mm );
at least one private weather station recorded 60mm and ,
based on rainfall data in the region and available radar data ,
this is well within the realms of likely possibility;
in his opinion, most of the rainfall from the storm most likely
fell between 6:34pm and 7:0 4pm and rainfall rates may have
exceeded 100mm/hr for short periods ;
heavy rainfall occurred at the Maroota Weather Station (the
closest to the property) on 21 March 2021 , 18 September
2019 , 26 February 2018 and 5 January 20 16 (103mm,
67mm, 66mm and 108mm respectively ). However, the main
Determination | Case number: 875471 Page 9 of 9
difference between the se events and the storm on 9
December 2021 is that the four events were all primarily
rainfall events that contained many hours of rainfall that
resulted in high 24 - hour totals. This is a very differe nt event
to the 9 December storm event that consisted of a few
showers and storms, including one very heavy
thunderstorm ; and
it is his opinion that the rainfall event that occurred on 9
December 2021 was likely more intense in terms of rainfall
rates than the other four rainfall events .
EIS supplementary
report – 3
(23 September 2022)
WW‟s report does not alter EIS‟s position;
i n determining the proximate cause of damage to the
retaining wall, the weather data (force acting on the retaining
wall) must be assessed in conjunction with the structural
capacity of the retaining wall (re sistance to the applied
forces);
it is reasonable to assume the retaining wall would have
experienced similar rainfall intensities in the past 25 years
and has not failed;
giv en the condition of the timber retaining wall, the retaining
wall has deteriorated and has failed in condition s it was able
to withstand in the past ;
on this basis the cause of the damage is attributed to long -
term deterioration;
an unmaintained timber retaining wall would inevitably fail
without intervention; and
no drainage was present behind the retaining wall to keep
the timber dry and from rotting.
E A supplementary report
– 2 and email
(2 1 and 2 6 November
2022)
the soft clay site has not been veri fied. This is an omission
and should be confirmed by a geotechnical engineer and the
height revision should also be explained;
the water flow from the intense storm was, in his opinion, the
primary factor;
hydrostatic pressure at least doubles the design load;
with running water there are also drag forces; and
drainage allows water to seep away to a discharge point at
the end of a pipe however all drainage systems are
overwhelmed in high intensity rainfall ingress because the
outflow cannot be accommodated .