Home / Youi / Determination 874718
Determination 874718
Claim settlement and mould damage repairs
Summary
The complainant's home was flooded by a burst hose fitting and the insurer later denied cover for mould in the toilet and bathroom, then offered a cash settlement and stopped repairs. AFCA found the mould was caused by the flood, that cash settlement was unfair, and ordered the insurer to complete repairs and pay $3,000 for non-financial loss.
Under the PDS the insurer must repair damaged buildings where possible, and cash settlement is unfair where the insurer abandoned partly completed repairs and the uninsured damage is minor.
Issues
- Claim denial primary · upheld“The available information indicates the damage to the toilet and bathroom was caused by the flooding on 7 January 2022. Therefore, the insurer was not entitled to deny cover for this damage.”
- Claim amount dispute secondary · upheld“It would be unfair for the insurer to cash-settle the claim... the insurer must settle the claim by completing the repairs.”
- Delay secondary · upheld“The insurer did not begin the works for another three weeks... did not resume work until 21 March 2022.”
- Repairs or contractors secondary · unclear“Mould remediation was never properly completed; insurer must appoint expert to repair identified and additional claim-related damage.”
Subjects and remedies
home or building damagenatural disasterpay non financial lossrepair or rectify
Related
Text of the determination
Determination
Case number 874718
Financial firm Youi Pty Ltd
Determination | Case number: 874718 Page 1 of 7
Case number: 874718 21 December 2022
1 Determination overview
1.1 Complaint
The complainant holds a home insurance policy with the financial firm (the insurer). In
January 2022, he lodged a claim for damage caused by a hose fitting bursting and flooding
the lower level of his home. The insurer accepted the claim and started repairs.
In March 2022, the insurer discovered mould in the wall between the toilet and bathroom. The
insurer says the mould was not caused by the flooding, but was caused by a separate event.
The insurer stopped repairs, and offered to settle the claim by paying the cost of the
outstanding repairs.
The complainant says the mould was caused by the flooding. He wants the insurer to
complete the repairs.
1.2 Issues and key findings
Is the insurer liable for the mould damage?
Yes. The available information indicates the mould was caused by the flooding on 7 January
2022, not by a separate event.
Is the insurer entitled to cash-settle the claim?
No. It would be unfair for the insurer to cash-settle the claim, because:
it would be difficult for the complainant to finish work the insurer started
there is a strong possibility of further claim-related damage that has not been identified
the home has no uninsured damage, other than minor pre-existing damage to a skirting
board (with an estimated repair cost of $50)
the policy terms do not entitle the insurer to cash-settle the claim.
The insurer must settle the claim by completing the repairs. Repairs will include the
replacement of the skirting board with pre-existing damage. To account for this, the insurer
may require the complainant to contribute $50 to the cost of repairs.
Is the complainant entitled to further compensation?
Yes. AFCA can award compensation for non-financial loss if an insurer causes an unusual
degree of stress, inconvenience, or delay. The insurer unfairly refused to complete repairs.
This caused an unusual degree of stress, inconvenience, and delay. The complainant is
entitled to $3,000 compensation for non-financial loss.
1.3 Determination
This determination is in favour of the complainant.
Within 14 days of being notified the complainant accepts this determination, the insurer must:
appoint a suitably qualified expert or experts to repair the damage
pay $3,000 compensation for non-financial loss.
Determination | Case number: 874718 Page 2 of 7
2 Reasons for determination
2.1 Is the insurer liable for the mould damage?
Home damaged by escaping water
The complainant says the lower level of his house flooded on 6 January 2022. He lodged a
claim with the insurer on 7 January 2022. According to the insurer’s records, he said the
flooding occurred because ‘ the lead hose fitting from the washing machine & water outlet had
burst off ’. There is no dispute that the policy covers damage caused by water escaping from
the hose fitting.
The complainant says he called family and friends to remove water and carpet.
The insurer appointed a builder, who inspected the house on 11 January 2022. The builder
said:
there was extensive damage throughout the lower level of the house
the damage was consistent with having been caused by a single event: the breaking of the
hose fitting
the house needed ‘invasive structural drying to the internal wall framing’ to prevent further
damage.
The insurer’s claim notes from 11 January 2022 said : ‘ our estimator attended today and has
advised that restoration (drying) is urgently required ’.
The insurer appointed a restorer, who inspected the house on 12 January 2022. The restorer
said the home needed about 10 days of ‘mould remediation works’ , which would include
installing drying equipment for seven days.
On 31 January 2022, the i nsurer’s contractors started the mould remediation works. The
insurer says it apologised for the delay in starting the work.
On 2 February 2022, the complainant says the workers had left the site. On 7 February 2022,
the insurer noted the workers had stopped work because they found asbestos. On 3 March
2022, the insurer says it obtained an asbestos clearance certificate and restarted work. The
insurer’s claim notes indicate work did not actually restart until 21 March 2022.
On 24 March 2022, the builder said they discovered mould in the wall between the toilet and
bathroom. This was in the area affected by the flooding. The insurer says this mould was not
caused by the flooding, but was caused by a separate event.
On 12 April 2022, the insurer decided to deny cover for the damage to the toilet and
bathroom. As the rest of the home could not be repaired without repairing the toilet and
bathroom, the insurer said it would stop repairs. The insurer offered to settle the claim by
paying the cost of the outstanding repairs, not including repairs to the toilet and bathroom.
The insurer has now offered to pay the cost of repairing the toilet and bathroom. However, it
maintains its decision to stop repairs and settle the claim by paying the cost of the
outstanding repairs.
Complainant provided evidence mould is claim-related
There is a piece of rotted skirting next to the toilet, on the wall shared with the bathroom.
There is no dispute that this was present before the flooding on 7 January 2022.
Determination | Case number: 874718 Page 3 of 7
The complainant provided a pre-purchase inspection report by a building inspector who
inspected the home on 10 November 2021. The report said:
there was ‘rotted skirting in [the] down stairs toilet’ which would cost $50 to repair
the property had no rising damp, no dampness, and no mould
the inspection did not include any wall cavities or under-floor areas.
The building inspector reinspected the home on 14 July 2022. The building inspector provided
a written statement saying:
the damage to the skirting noted in the pre-purchase inspection report was due to sub-
standard timber or ‘possible urination events’
there were no water leaks and no mould present during the pre-purchase inspection
any mould now present was due to the flooding on 7 January 2022.
Insurer provided no evidence mould is not claim-related
The insurer says the mould between the toilet and bathroom was not caused by the flooding
on 7 January 2022 but was caused by a separate event. However, the insurer has not said
what the separate event was.
The insurer says it advised the complainant to investigate the cause of the mould. The
complainant provided a statement from his building inspector saying the cause of the mould
was the flooding on 7 January 2022. The insurer has not responded to this.
There is a shower on the opposite side of the wall with the rotted skirting. The insurer says
there could be a leak from the shower. However, none of the expert reports say this. The
insurer did not ask its experts to test whether there was a leak from the shower.
Insurer’s builder says mould could be claim -related
The insurer’s builder’s report of 24 March 2022 said the mould was caused by a ‘new event’.
The report did not say why the builder thought the mould was caused by a new event, or what
the new event was.
The insurer’s builder’s report of 24 March 2022 said the mould was ‘ believed to be new and
occurred separately from the pre-existing issue ’. This means whatever caused the rotten
skirting (pre-existing issue) did not cause the mould.
The insurer ca lled its builder on 6 April 2022. According to the insurer’s claim notes, the
builder said there was a ‘real possibility’ the flooding on 7 January 2022 contributed to the
mould. The insurer appears to have ignored this.
Mould caused by insured event
The toilet and bathroom were flooded with water on 7 January 2022 . The insurer’s experts
said the home needed mould remediation works urgently, and the work would take about 10
days. The insurer did not begin the works for another three weeks, and it stopped after about
two days. The insurer’s claim notes say moisture levels were ‘still high’ when the mould was
discovered on 24 March 2022. This means the environment was conducive to mould growth
for about 11 weeks.
The skirting next to the toilet had pre-existing damage. However, the damage was minor, and
there is no evidence it was associated with any mould or water leaks. There is no other
evidence the mould was caused by anything other than the flooding on 7 January 2022.
Determination | Case number: 874718 Page 4 of 7
The available information indicates the damage to the toilet and bathroom was caused by the
flooding on 7 January 2022. Therefore, the insurer was not entitled to deny cover for this
damage. The insurer must cover this damage as part of the complainant’s claim.
2.2 Is the insurer entitled to cash-settle the claim?
Policy requires insurer to repair damage
The product disclosure statement (PDS) for the complainant’s policy sets out how the insurer
will settle a claim for building damage:
if the insurer can repair the damage, it will repair the damage (and guarantee the repairs)
if the insurer cannot repair the damage, it will pay the reasonable cost of repairs.
The PDS says the insurer may be unable to repair damage if ‘the pre -incident condition of the
buildings prevents us from repairing or rebuilding them’.
The complainant’s home had pre -existing damage to a skirting board. However, this damage
was minor, and would not prevent the insurer from repairing the damage. The insurer has not
provided any other information indicating it is unable to repair the damage. Therefore,
according to the policy terms, the insurer must repair the damage.
Cash settlement not fair in the circumstances
The General Insurance Code of Practice (to which the insurer subscribes) requires insurers to
act fairly to their customers. When an insurer offers to cash-settle a claim rather than
appointing a repairer, AFCA will consider whether the proposed settlement is fair.
The insurer took responsibility for repairs from 11 January 2022 to 12 April 2022. If the insurer
cash-settles the claim, it will leave the complainant responsible for finishing repairs the insurer
started. This may include repairing damage that developed during those three months
because the insurer did not properly dry out the property. It may be difficult for the
complainant to find a builder willing to do this work.
The complainant’s home had extensive water damage, and was in urgent need of mould
remediation, in January 2022. Almost a year later, it appears mould remediation was never
properly completed. Mould was identified in March 2022, and could have spread since then.
For these reasons, the home may have claim-delated damage that has not yet been
identified. The insurer has offered to pay the cost of repairing the identified damage, plus an
extra 15% for possible unidentified damage. However, for the above reasons, the unidentified
damage may be extensive, and an extra 15% may not be sufficient.
A cash settlement will usually be fair if an insured property has a mix of insured and
uninsured damage, and it would be impractical to repair the insured damage without repairing
the uninsured damage. In this case, the only identified uninsured damage is the minor pre-
existing damage to the skirting board. It is unfair for the insurer to refuse to complete repairs
for this reason.
For the above reasons, it would be unfair for the insurer to cash-settle the claim. Therefore,
the insurer must settle the claim by repairing the damage and guaranteeing the repairs.
Insurer must complete repairs
Within 14 days of receiving notice the complainant accepts this determination, the insurer
must appoint a suitably qualified expert or experts to repair the damage identified by its
Determination | Case number: 874718 Page 5 of 7
builder and restorer. The insurer must also repair any additional claim-related damage that is
discovered.
Repairs will include the replacement of the skirting with pre-existing damage. To account for
this, the insurer may require the complainant to contribute $50 to the cost of repairs.
Insurer may only cash-settle if it is impossible to complete repairs
The parties will need to work together to allow the insurer to complete repairs. Depending on
both parties’ conduct, their relationship may deteriorate to the extent that it becomes
impossible for them to work together, and the insurer will not be able to complete repairs.
If it becomes impossible for the insurer to complete repairs, it may settle the claim by paying
the cost of the outstanding repairs. The insurer may not do this unless it has made every
reasonable attempt to complete repairs. If the insurer claims it is impossible for it to complete
repairs, and the complainant claims otherwise, the complainant may lodge another AFCA
complaint.
If it becomes impossible for the insurer to complete repairs, and the insurer cash-settles the
claim, it must pay the complainant an amount that will allow him to complete all outstanding
repairs. It must also pay the complainant an amount that fairly compensates him for the
disadvantages that come with a cash settlement, including the loss of the in surer’s guarantee
and the difficulty of appointing builders to complete the insurer’s repairs. If the parties cannot
agree on a fair settlement sum, the complainant may lodge another AFCA complaint.
2.3 Is the complainant entitled to further compensation?
Insurer must pay $3,000 compensation for non-financial loss
Under the AFCA Rules, we can award up to $5,400 compensation for non-financial loss if a
complainant suffered an unusual degree of stress, inconvenience, or delay because an
insurer mishandled a claim. We do not award compensation for the usual amount of
inconvenience involved in making a claim.
The insurer admits there was a delay between lodging the claim on 7 January 2022 and
starting remediation work on 31 January 2022. The insurer has waived the excess of $1,000
for the inconvenience caused by this delay.
There was another delay between 2 February 2022, when asbestos was discovered at the
home, and 3 March 2022, when the insurer obtained an asbestos clearance certificate. This
was not the insur er’s fault. However, the insurer did not resume work until 21 March 2022.
The insurer has not explained this delay.
From 24 March 2022, the insurer stopped repairing the home. For the reasons set out above,
this was unfair. This has caused a long delay in the repair of the home. The affected rooms
are severely damaged, and will be unusable until they are repaired.
The insurer has mishandled the claim, and this has led to a long delay in the resolution of the
claim. The delay has caused the complainant an unusual degree of stress and
inconvenience.
Having considered the information provided by both parties, I think it is fair for the insurer to
pay the complainant compensation for non-financial loss in the sum of $3,000 (in addition to
the excess waiver of $1,000).
Determination | Case number: 874718 Page 6 of 7
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
3.2 Relevant policy terms
Product Disclosure Statement
Insured events (pages 13 – 16)
Your buildings and contents are covered up to the sum insured shown on your policy schedule for
the following events where they occur at the insured premises.
8. Escaping Water
What is covered?
Loss or damage to the insured propert y caused by escaping water that occurred:
suddenly and without warning; or
slowly over a period of time and you could not reasonably have been aware of it.
…
What is not covered?
Loss or damage which was:
caused by water escaping slowly over a period of time and you could reasonably have been
aware of it;
caused by water escaping:
‒ from a leak in a shower bas e, recess or cubicle;
…
caused by rising damp or seepage of water from the ground.
Determination | Case number: 874718 Page 7 of 7
How we settle your claim (pages 31 – 32)
1. If you are claiming for buildings
If we can, we will settle your buildings claim by:
repairing the damaged parts of your buildings if it is both possible for the parts to be repaired and
economic al for us to repair thos e parts because t he cost of repair is less than the cost of
rebuilding; or
rebuilding the damaged part of your buildings if it is either not possible for those parts to be
repaired or not economical for us to repair those parts because the cost of repair is more than the
c ost of rebuilding.
The circumstances in which we may be unable to repair or rebuild the buildings include:
if materials needed for the repair or rebuild are not readily available;
if the repair or rebuilding cannot commenc e for a significant amount of time ; for example, due to
availability of service providers;
if the pre - incident condition of the buildings prevents us from repairing or rebuilding them; or
if the insured event makes the land uns afe to build on; for example, after an earthquake.
If we cannot repair or rebuild the damaged part of your buildings, we will pay you an amount equal
to the reasonable cost that you would incur to repair or rebuild the buildings up to the limits noted in
your policy. We will undertake a search of the market to determi ne what this cost would be in your
area, based on factors including scope of works and comparison quotes from repairers or builders.
We can use a combination of the above settlement methods if we are able to partially repair or
rebuild the damaged part of your buildings.
Quality guarantee (page 34)
Where we arrange, authorise and pay a service provider for repairs, we will guarantee the quality of
the repairs for as long as you are the owner of the ins ured property. The guarantee includes the
rectification of any defects caused by poor workmanship, or faulty materials, related to thes e
repairs.
The guarantee does not apply to:
general wear and tear or deterioration;
electrical or mec hanical failure of appliances or machines, unless it is a dire ct result of authorised
works related to the claim;
any item exceeding its expected or specified lifespan;
any part of the claim where we pay you to repair, rebuild or replace; or
any repairs you have arranged and/or paid for.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.