Home / Allianz Australia / Determination 872068
Determination 872068
Delay in repairs under builder contract affecting rental loss
Summary
A landlord's tenanted property damaged by a May 2020 storm was not repaired within the insurer's builder's 105-day contract period. AFCA decided the insurer must pay further rental losses of $9,829.60 and $3,000 for non-financial loss, despite the policy rental loss limit having been paid.
The insurer is responsible for its authorised builder's unexplained failure to complete repairs within the agreed timeframe, so the resulting additional rental losses are direct financial loss outside the policy limit.
Issues
- Repairs or contractors primary · upheld
“The insurer failed to complete repairs within an agreed timeframe without reasonable basis; PIB's failure caused the complainant to incur additional rental losses.”
- Delay secondary · upheld
“Repairs were not completed by 4 January 2021 as agreed under the 105-day Construction Period; completed on or around 4 May 2022.”
Subjects and remedies
home or building damagenatural disasterthird party authoritypay compensationpay non financial loss
Text of the determination
Determination
Case number 872068
Financial firm Allianz Australia General Insurance Limited
Determination | Case number: 872068 Page 2 of 7
Case number: 872068 21 December 2022
1 Determination overview
1.1 Complaint
The complainant ’s tenanted property (the property) was significantly damaged by a storm in
May 2020. It was insured with the financial firm (insurer) under a landlord’s policy at the time.
The complainant claimed for the damage and rental loss. The insurer accepted the claim. It
authorised repairs to its builder ‘PIB’ and paid the complainant $34,031.42 for rental losses.
The complainant disputes the compensation paid for rental loss. He says the insurer took 18
months to repair the property when it was supposed to complete repairs in 105 days.
The insurer says it paid more than the policy limit for rental loss and it would not be fair to
require it to pay more.
1.1 Issues and key findings
Is the complainant in entitled to more compensation?
Yes. The insurer failed to complete repairs within an agreed timeframe without reasonable
basis. This caused the complainant to incur rental losses he would not otherwise have
incurred. It also caused him unusual delay, inconvenience and interference. Therefore,
compensation for further rental losses and non-financial loss is warranted.
Why is the outcome fair?
The insurer’s failure to complete repairs within the agreed timeframe caused t he complainant
additional rental losses and unusual delay, inconvenience and interference. Given this, it is
fair the insurer pays further compensation for his rental losses and some compensation for
non-financial loss.
1.2 Determination
This determination is in favour of the complainant.
Within 14 days of being notified of the complainant’s acceptance of this determination, t he
insurer is to pay him:
$9,829.60 for his additional rental losses
$3,000 as compensation for non-financial loss.
Determination | Case number: 872068 Page 3 of 7
2 Reasons for determination
2.1 Is the complainant in entitled to more compensation?
Yes. The insurer failed to complete repairs within an agreed timeframe without reasonable
basis. This caused the complainant to incur rental losses he would not otherwise have
incurred. It also caused him unusual delay, inconvenience and interference. Therefore,
compensation for further rental losses and non-financial loss is warranted.
Complainant must prove a valid claim
The complainant has the initial onus to establish, on the balance of probabilities, he suffered
a loss covered by the policy. This is known as a prima facie or valid claim. Once established,
the onus is then on the insurer to prove an exclusion or limitation applies if it seeks to deny or
limit its liability for the loss.
Policy covers rental loss if property is unliveable due to an insured event
The complainant’s policy is made up of a certificate of insurance and product disclosure
statement, which form the terms of his cover.
The relevant policy extracts about rental loss are set out in section 3.2 of this determination.
In summary, the policy covers rental loss if the property is damaged and becomes unliveable
because of an event the policy covers. The policy says the property is ‘unliveable’ if it is
damaged to an extent:
‘normal domestic activities’, like cooking, sanitation or cleaning one’s self cannot occur
local authorities will not allow the property to be inhabited.
No dispute insurer accepted claim for storm damage and rental loss
There is no dispute the property was significantly damaged by storm and was considered
‘unliveable’ from 20 May 2020. There is also no dispute the policy covers storm damage and
the insurer accepts liability for storm damage and rental loss.
The dispute is about the extent of the insurer ’s liability for the complainant’s rental losses.
Complainant’s maximum policy entitlement for rental loss is $22,421.43
The maximum benefit ordinarily payable for rental loss under the policy is the lower of 10% of
the building sum insured or 12 months’ rent.
The property was insured for $321,000 and was leased out at $430 a week at the time of
loss. 10% of the building sum insured is $32,100, whereas 12 months’ rent i s $22,421.43 (i.e.
$430/7 x 365). This means the comp lainant’s maxim um policy entitlement is $22,421.43.
The insurer paid the complainant $34,031.42 for his rental losses. Viewed solely from a policy
perspective, I accept no further rental loss benefits would be payable under the policy.
However, it is not correct to consider the whole of the complainant’s rental loss claim on this
basis. A distinction must be drawn between rental loss arising from the claimable event and
rental loss arising from the insurer’s failure to meet its repair commitment to the complainant.
Determination | Case number: 872068 Page 4 of 7
Insurer’s builder agreed to complete repair within 105 days
The exchanged information shows the complainant and P IB entered into a building contract
on 21 September 2020. The contract provided for a 105-day ‘Construction Period’ . This
period included allowances for weekends, public holidays, off days, weather related delays,
securing plans, permits and specialised trades, and specialised material supply delays.
The contract says PIB will complete works ‘within a reasonable time’. How ever, it is entitled to
an extension of the ‘Construction Period’ for variations beyond its ‘reasonable control’ and
‘were unforeseen at the contract date’.
Insurer’s builder failed to complete repair within 105 days as agreed
105 days from 21 September 2020 falls on 4 January 2021. There is no dispute the repairs
were not completed by then. As of March 2022, t he property’s window coverings and shade
sail were still not installed. These were eventually cash settled on or around 20 April 2022.
I am satisfied the complainant could not relet the property until these works were completed.
It is unreasonable to expect the complainant to relet the property without window coverings.
Allowing 14 days for the outstanding works (from when the cash settlement was paid), I
consid er the property’ s repair to only have been completed by 4 May 2022.
PI B’s failure to complete repairs within agreed timeframe caused rental loss
Neither the insurer nor PIB explained the cause of the delay or showed a reasonable basis for
it. This was despite the complainant specifically referring to the agreed repair timeframe in the
PIB building contract in numerous correspondences and submissions.
While there were additional works that resulted in some variations being issued, the
exchanged material does not indicate PIB sought an extension of the ‘Construction Period’ .
There is also no suggestion or evidence these variations arose because of factors beyond its
‘reasonable control’ and that ‘were unforeseen at the contract date’.
Without any explanation, I can only conclude there was no reasonable basis for the delay.
Given this, I am satisfied PI B’s failure to complete the required repairs within the agreed
timeframe caused the complainant to unnecessarily incur additional rental losses.
Insurer is to compensate complainant for rental losses and non-financial loss
The complainant would only have incurred 229 days’ worth of rental loss had the repairs been
completed by the agreed 4 January 2021 date. Based on a $61.43 daily rental rate, the pol icy
would have covered $14,067.47 worth of rental losses for the period up to then.
As repairs were only completed on or around 4 May 2022, the complainant incurred another
485 days’ worth of rental losses (i.e. $ 29,793.55) he should not have incurred. These losses
were directly due to PIB’s failure to complete the required repairs by the agreed date.
This means another $9,829.60 is still compensable to complainant, derived as follows:
Total rental losses on and from 21 May 2020 to 4 May 2022 $43,861.02
Less: total paid by the insurer to date $34,031.42
Outstanding amount payable $ 9,829.60
Determination | Case number: 872068 Page 5 of 7
Insurer says it is unfair to require it to pay more compensation
The insurer says it is unfair to require it to pay more compensation because it already paid
more than the maximum policy limit for rental loss. It also says:
the property was no longer ‘unliveable’ by 26 November 2021, as the only outstanding
works then were installation of the property’s blinds and shade sail
the policy excludes consequential loss of any kind.
Unfair for insurer to avoid responsibility for its failure to meet its promise
I do not accept these submissions.
While I accept the insurer may have paid more than the maximum policy benefit for rental
loss, the referred policy provisions are not applicable. The complainant’s additional rental
losses did not arise from the claimable event.
Rather, they arise from the insurer’s failure to meet its commitment to complete repairs in 105
days, as promised. It is unfair for it to avoid responsibility for financial losses caused by its
failure to complete repairs within the promised timeframe.
Ultimately, PIB failed to complete the required repairs within 105 days as promised. The
complainant could not fairly relet the property until after 4 May 2022 because of this failure.
Under basic contractual principles, the complainant is entitled to compensation for financial
losses arising from this failure. As PIB is the insurer’s authorised builder, the insurer is
responsible for such losses.
Rental loss is direct financial loss
Under the AFCA Rules, AFCA can award compensation of up to:
$542,500 for direct financial loss
$5,400 for indirect financial loss
$5,400 for non-financial loss.
The AFCA Rules do not define direct or indirect financial loss.
Whe n reviewing AFCA’s jurisdiction, Australian courts have said direct loss is loss that ‘ flows
naturally from the breach without other intervening cause ’.
The insurer took an unreasonably long time to complete repairs, and the complainant could
not let the property until repairs were complete. Loss of rent flowed naturally from the
insurer’s failure to complete repairs. There was no other intervening cause t hat prevented the
complainant from deriving rental income from the property. Therefore, the additional loss of
rent is direct financial loss. It is subject to AFCA’s jurisdictional limit of $542,500 for direct
financial loss and not the jurisdictional limit of $5,400 for indirect financial loss.
Insurer is to compensate complainant for rental losses and non-financial loss
The insurer must pay the complainant an additional $9,829.60 for loss of rent.
I am also satisfied it is fair the insurer pays the complainant $3,000 as compensation for non-
financial loss. This is to account for the unusual delay, inconvenience and interference
caused by its failure to meet its repair commitment to him.
Determination | Case number: 872068 Page 6 of 7
3 Supporting information
3.1 The AFCA process
AFCA’s approach i s based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. I have reviewed and considered
all information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this
determination to the issues that are relevant to the outcome.
3.2 Relevant policy terms
3 General exclusions.
Of course, insurance can ’ t cover absolutely everything. Here are the general
exclusions that apply to all cover described in this PDS …
Your policy does not cover any loss or damage that is caused by or arises from:
…
Consequential loss.
In addition to the above types of loss and damage, your policy does not cover
consequential loss of any kind.
…
4.4 Landlord additional benefits.
This summary of additional benefits is a reference tool only. For further details of
the relevant terms and conditions, limits and exclusions on cover, refer to the
page numbers shown.
…
Building additional benefits.
If we agree to pay a claim for loss or damage to your building, we will also pay for
the additional benefits listed below that are directly related to that loss or damage.
Some additional benefits are paid in addition to the sum insured and some are
paid as part of the sum insured.
These additional benefits do not apply to claims made under optional Landlord
Extras cover.
Determination | Case number: 872068 Page 7 of 7
Benefits paid in addition to your building sum insured.
…
Loss of rent.
If the property is leased at the time of an
insured event and the loss or damage
makes the property unliveable and rent
payments cease, then we will cover the
lost rent.
This expense will only be paid during the
repair or replacement period and only
while the property remains unliveable.
… Up to 10% of the
building sum
insured or the
amount of lost rent
for up to 12 months
from the date of the
event, whichever is
less
…
unliveable when a building is so damaged that normal domestic activities like
cooking, sanitation and personal hygiene cannot take place, and local authorities
will not provide permission for the home to be inhabited.
3.3 Relevant case law considered
Australian Capital Financial Management Pty Ltd v Australian Financial Complaints Authority
Limited [2021] NSWSC 1577
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.